Report on the Acceptance Test of the CRI Y-MP 8128, 10 February - 12 March 1990
The NAS Numerical Aerodynamic Simulation Facility's HSP 2 computer system, a CRI Y-MP 832 SN #1002, underwent a major hardware upgrade in February of 1990. The 32 MWord, 6.3 ns mainframe component of the system was replaced with a 128 MWord, 6.0 ns CRI Y-MP 8128 mainframe, SN #1030. A 30 day Acceptance Test of the computer system was performed by the NAS RND HSP group from 08:00 February 10, 1990 to 08:00 March 12, 1990. Overall responsibility for the RND HSP Acceptance Test was assumed by Duane Carbon. The terms of the contract required that the SN #1030 achieve an effectiveness level of greater than or equal to ninety (90) percent for 30 consecutive days within a 60 day time frame. After the first thirty days, the effectiveness level of SN #1030 was 94.4 percent, hence the acceptance test was passed.