Prototype HB650 Transportation Validation For The PIP-II Project
The PIP-II Project at Fermilab is centered around a superconducting 800 MeV proton linac to upgrade and modernize the Fermilab accelerator complex, allowing increased beam current to intensity frontier experiments such as LBNF-DUNE. PIP-II includes strong international collaborations, including the delivery of 12 cryomodules from European labs to FNAL (3 from STFC-UKRI in the UK and 9 from CEA in France). The transatlantic shipment of these completed modules is identifed as a serious risk for the project. To mitigate this risk, a rigorous and systematic process has been developed to design and validate a transport system, including specifcation, procedures, logistics, and realistic testing. This paper will detail the engineering process used to manage this effort across the collaboration and the results of the first major validation testing of the integrated shipping system prior to use with a cryomodule.