LAMP DTL Scoping Studies (Technical Report)

The present studies are based on the preliminary design efforts, and on the Scoping Studies of the “Strawman” design of LAMP front-end upgrade, referred in the text below to as “Feb.2024 Iteration”, presented in. The main accomplishment of present studies was substantial increase of the fidelity of the beam dynamics simulations in the proposed drift tube linac (DTL). The main accent was on development of the methodology for calculation of the longitudinal (synchrotron) and transverse (betatron) oscillations frequencies (phase advance per focusing period) values and providing the accelerating structure focusing lattice that has safe parameters of such oscillations to avoid unwanted emittance growth and possible beam halo formation. The resulting values of the oscillations phase advances are presented in Table 1, and in Figure 5 in the main body of the report. Special efforts were made to achieve the RF power consumption within limits of the existing RF power system and make sure that DTL fits in the existing tunnel. The LAMP scope does not suggest any additional building and/or tunnel construction. Table 1 summarizes some of these results, as well as Table 3 in the main body of the report.

43 PARTICLE ACCELERATORS↗

Write-up on the analytical formalism for DTL Synchrotron and Betatron frequencies estimates

Appendix A contains tables of the DTL tanks geometry, generated using PARMILA code with input parameters of initial and final energy, accelerating gradient, synchronouse phase, and using DTLfish code (part of the SUPERFISH/POISSON package of codes). Details of the design and generation od the DTL geometry will be presented in a separate report. After generation of the DTL geometry and initial beam dynamics simulations, the analytic estimates of the synchrotron and betatron oscillations, as well as presence of the parametric resonance of first order were done. In present report the analytic background of those estimates, as well as the results of these are presented.

43 PARTICLE ACCELERATORS↗

Start-to-end simulation for LAMP front-end scoping studies

We present a design of a new front end in support of the LANSCE Modernization Project (LAMP). This is an updated front-end design that can largely meet LAMP threshold needs. The first half of this report details each section of the front end, including a summary of the physics design and function. The second half simulates several beam formats from the initial source all the way through the final DTL section (i.e. start-to-end simulations). Details and assumptions are described. The following table summarizes the key results for the different beam formats from this study.

43 PARTICLE ACCELERATORS↗

LAMP Low-Energy Region Options: Workshop Report and Ranking Assessment

The LANSCE accelerator complex at Los Alamos National Laboratory provides beam to five user facilities: IPF, pRad, UCN, WNR and the Lujan Center. Each user facility receives a beam tailored to its specific requirements, including species (H+ or H- ) and beam pulse format. The capabilities and beam requirements of the LANSCE user facilities are documented elsewhere. The core components of the LANSCE accelerator complex – the beam source area, drift-tube and cavity-coupled linear accelerators – are more than 50 years old; a critical subsystem for beam delivery to the Lujan Center, the proton storage ring (PSR), is approximately 40 years old, with its last major refresh being completed in the late 1990s. The LAMP project is intended to begin a revitalization and update of the LANSCE accelerator complex, starting with the beam source region, drift-tube linac, and PSR.

43 PARTICLE ACCELERATORS↗

PARMELA simulation of Line-A beamline

This is a short re-work of the previously accomplished simulations, using PARMELA code package. This exercise was done primarily for increase of fidelity and re-formulating the given task for a different beam dynamics (BD) code. The performed simulations showed very good agreement with the abovementioned simulations and confirm the previously produced results with the BEAMPATH code.

43 PARTICLE ACCELERATORS↗

Preliminary Design of a LAMP DTL (Update)

Present report is a continuation of the previously published report LA-UR-23-26600 from 19-Jun-2023 and incorporates the mentioned report as its part. All the additional information is contained in the part III of this report, the DTL Transverse Focusing Scheme. A preliminary Drift Tube Linac (DTL) layout was designed to create an algorithm for developing the conceptual design of the proposed LANSCE Accelerator Modernization Project (LAMP) final section: the proton linear accelerator from 3 MeV to 100 MeV. Preceding reports describe the proposed layouts of the LEBT, the RFQ, and the MEBT subsections of the linac. Initial estimates of the needed RF power for the DTL are also presented in the report. Present report describes the initial layout of the DTL and the first longitudinal beam dynamics (BD) results of the simulations in simplified models. The part III of this report includes the transverse focusing scheme and transverse BD in details.

43 PARTICLE ACCELERATORS↗

Preliminary Design of a LAMP DTL

A preliminary Drift Tube Linac (DTL) layout was designed to create an algorithm for developing the conceptual design of the proposed LANSCE Accelerator Modernization Project (LAMP) final section: the proton linear accelerator from 3 MeV to 100 MeV. Preceding reports describe the proposed layouts of the LEBT, the RFQ, and the MEBT subsections of the linac. Initial estimates of the needed RF power for the DTL are also presented in the report. Present report describes the initial layout of the DTL and the first longitudinal beam dynamics results of the simulations n simplified models. The follow-up reports will include the transverse focusing scheme and beam dynamics in details. Present report in the last section will only describe the planned focusing scheme, based on the existing LANCE DTL.

43 PARTICLE ACCELERATORS↗

Application of Particle Accelerators to Mitigate Energy and Climate Change Problems Facing America

Reliable CO 2 -free baseload power is needed to address ever-increasing demands for electricity while minimizing adverse climate change. Diversified power supply provided by solar, wind, geothermal, and nuclear reactors can displace the use of fossil fuels. The United States (U.S.) is taking a new look at nuclear power as a source of electrical energy and the nuclear industry is proposing new approaches which may minimize capital costs. However, nuclear power comes with a variety of technical problems. Chief among those is managing the used fuel from nuclear reactors. No long-term, practicable solution to this problem is available. The lack of progress on a comprehensive waste management strategy restricts growth in the nuclear power industry and minimizes the role that nuclear energy may serve as part of a zero-carbon future (Bahr, 2021). According to the Nuclear Waste Policy Act of 1982, as amended, the U.S. Government has possession of the used reactor fuel and incurs large annual storage fees paid to utilities to store and safeguard the accumulated used fuel. In effect, short term on-site storage of nuclear waste is the current waste management plan. The amount of used reactor fuel in the U.S. is approximately 80,000 metric tons. While no geologic repository exists within the U.S., the potential site at Yucca Mountain, NV would accommodate 70,000 metric tons, which fails to meet current and future needs. Given the technical and political challenges associated with establishing a single geological storage site, it is necessary for the U.S. to implement technologies that improve the suitability of geological storage by reducing the volume and radiotoxicity of stored material. No extant technology meets this need. Accelerator driven waste burners have been proposed as a scalable method to process used nuclear fuel, however considerable technical challenges remain which impede commercialization. Innovations in design require investigation of novel materials, development of accurate models and simulations, and a comprehensive assessment of safety and performance. This proposal elaborates how LANL is uniquely positioned to make key contributions to this area of research.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Modeling Codes Used for LAMP

LAMP team is planning on using multiple computer codes as tools for modeling beam dynamics, electromagnetics, and plasma environment in ion sources. Below is a description of the computer tools we have been using or planning to use in the future. Most of the codes chosen for the LAMP project are capable to model most of the beam dynamics in LAMP. A judicious choice of the appropriate code to use will be based on speed and fidelity of the modeling with faster calculations produced by simplifying some features.

43 PARTICLE ACCELERATORS↗