Search NASA⌕ Search

Engineering topics

Huque, N. A.

Publications and source records attributed to Huque, N. A..

Cavity Qualification and Production Update for SNS-PPU Cryomodules at Jefferson Lab

The Proton Power Upgrade (PPU) project at Oak Ridge National Lab’s Spallation Neutron Source (SNS) currently being constructed will double the proton beam power capability from 1.4 to 2.8 MW by adding seven cryomodules, each containing four six-cell high-beta (β = 0.81) superconducting radio frequency cavities. Research Instruments, located in Germany, built and processed the cavities at the vendor site, including electropolishing as the final active chemistry step. Twenty-eight cavities for seven cryomodules and an additional four cavities for a spare cryomodules were delivered to Jefferson Lab and first qualification tests were completed on all cavities as received from the vendor. The performance largely exceeded the requirements on quality factor and accelerating gradient. Here we present the status of initial cavity qualification tests, rework on unqualified cavities and final cavity qualification with helium vessel prior to installation in cryomodules. In addition, an update on cryomodule production is presented.

Dhakal, P.↗

Managing Procurements in the Time of Covid-19: SNS-PPU as a Case Study

In early 2020, COVID-19 swept across the world. The accelerator industry, like many others, was impacted by disease, delays, shortages, and new working conditions. All Thomas Jefferson National Accelerator Facility (JLab) employees were sent home in mid-March 2020, with many still working remotely now. At the time, JLab was working on the Proton Power Upgrade (PPU) to the Spallation Neutron Source (SNS) at Oak Ridge National Laboratory (ORNL). Procurements had been placed and were being managed, parts were being received and inspected. This paper details the JLab procurement plan for the SNS PPU project, and the mitigations that were developed to continue to support this project smoothly under the limitations imposed by COVID-19.

Wilson, K. M.↗

Status of SNS Proton Power Upgrade SRF Cavities Production Qualification

The Pro­ton Power Up­grade pro­ject at Oak Ridge Na­tional Lab’s Spal­la­tion Neu­tron Source (SNS PPU) cur­rently being con­structed will dou­ble the pro­ton beam power from 1.4 to 2.8 MW by adding 7 ad­di­tional cry­omod­ules, each con­tains four six-cell high beta (\beta = 0.81) su­per­con­duct­ing radio fre­quency cav­i­ties. The cav­i­ties were built by Re­search In­stru­ments, Ger­many, with all the cav­ity pro­cess­ing done at the ven­dor site, in­clud­ing elec­trop­o­l­ish­ing as the final ac­tive chem­istry step. All 28 cav­i­ties needed for 7 cry­omod­ules were de­liv­ered to Jef­fer­son Lab, ready to be tested. The cryo­genic RF qual­i­fi­ca­tions and he­lium ves­sel weld­ing were done at Jef­fer­son Lab. The per­for­mance largely ex­ceed the re­quire­ments, and greatly ex­ceeded the per­for­mance of the orig­i­nal SNS cav­ity pro­duc­tion se­ries. Here, we pre­sent the sum­mary of RF test on pro­duc­tion cav­i­ties to this date.

Dhakal, P.↗

Development of Helium Vessel Welding Process for SNS PPU Cavities

The Spallation Neutron Source Proton Power Upgrade cavities are produced by Research Instrument with all the cavity processing done at vendor sites with final chemistry applied to the cavity to be electropolishing. Cavities are delivered to Jefferson Lab, ready to be tested. One of the tasks to be completed before the arrival of production-ready PPU cavities is to develop a robust helium vessel welding protocol. We have successfully developed the process and applied it to three six-cell high beta cavities. Here, we present the summary of RF results, welding process development, and post helium vessel RF results.

Dhakal, P.↗

Status of SNS Proton Power Upgrade SRF Cavities Production Qualification

The Pro­ton Power Up­grade pro­ject at Oak Ridge Na­tional Lab’s Spal­la­tion Neu­tron Source (SNS PPU) cur­rently being con­structed will dou­ble the pro­ton beam power from 1.4 to 2.8 MW by adding 7 ad­di­tional cry­omod­ules, each con­tains four six-cell high beta (\beta = 0.81) su­per­con­duct­ing radio fre­quency cav­i­ties. The cav­i­ties were built by Re­search In­stru­ments, Ger­many, with all the cav­ity pro­cess­ing done at the ven­dor site, in­clud­ing elec­trop­o­l­ish­ing as the final ac­tive chem­istry step. All 28 cav­i­ties needed for 7 cry­omod­ules were de­liv­ered to Jef­fer­son Lab, ready to be tested. The cryo­genic RF qual­i­fi­ca­tions and he­lium ves­sel weld­ing were done at Jef­fer­son Lab. The per­for­mance largely ex­ceed the re­quire­ments, and greatly ex­ceeded the per­for­mance of the orig­i­nal SNS cav­ity pro­duc­tion se­ries. Here, we pre­sent the sum­mary of RF test on pro­duc­tion cav­i­ties to this date.

Dhakal, P.↗