Acceleration of uranium beam to record power of 10.4 kW and observation of new isotopes at Facility for Rare Isotope Beams

The Facility for Rare Isotope Beams (FRIB) is a major nuclear physics facility for research with fast, stopped, and reaccelerated beams that was successfully commissioned in May 2022. A key capability of FRIB is the production of an acceleration of the uranium beam, but this capability requires the facility to work at the design limits of the lowest charge-to-mass ratio and the highest power density on the beam intercepting devices. This paper presents techniques for overcoming the significant challenges in accelerating the uranium beam, culminating in the demonstration of 10.4 kW on target, and the discovery of three new isotopes. The high-power uranium beam enabled us to produce and identify G 88 a , A 93 s , and S 96 e , within the first 24 h of operation. The successful uranium operation at FRIB sets a new record for accelerated uranium beam power above 10 kW and opens a new avenue of research with rare isotopes. Published by the American Physical Society 2024

43 PARTICLE ACCELERATORS↗

Technological developments and accelerator improvements for the FRIB beam power ramp-up

The Facility for Rare Isotope Beams (FRIB) began operation with 1 kW beam power for scientific users in May 2022 upon completion of 8 years of project construction. The ramp-up to the ultimate beam power of 400 kW, planned over a 6-year period, will enable the facility to reach its full potential for scientific discovery in isotope science and applications. In December 2023, a record-high beam power of 10.4 kW uranium was delivered to the target. Technological developments and accelerator improvements are being made over the entire facility and are key to completion of the power ramp-up. Major technological developments entail the phased deployment of high-power beam-intercepting systems, including the charge strippers, the charge selection systems, the production target, and the beam dump, along with support systems, including non-conventional utilities (NCU) and remote handling facilities. Major accelerator improvements include renovations to aging legacy systems associated with experimental beam lines and system automation for improved operational efficiency and better machine availability. Experience must be gained to safely handle the increased radiological impacts associated with high beam power; extensive machine studies and advanced beam tuning procedures are needed to minimize uncontrolled beam losses for the desired operating conditions. This paper discusses the technological developments and accelerator improvements with emphasis on major R&D efforts.

43 PARTICLE ACCELERATORS↗

Commissioning of the Advanced Rare Isotope Separator ARIS at FRIB

The Facility for Rare Isotope Beams (FRIB) at Michigan State University (MSU) consists of a newly constructed linear accelerator and fragment separator that are designed for enhanced production rates of rare isotopes for use in research and other societal applications. Recent activities through to August 2022 took place to commission the Advanced Rare Isotope Separator (ARIS) and carry out the first experiments. This followed commissioning of the newly constructed linac that is designed to provide orders of magnitude higher beam power than the previously coupled cyclotrons. This required that more advanced target, beam dump, and collimation systems of the new separator be designed and constructed to sustain unprecedented conditions by heavy ion beams. Commissioning with ~1 kW beams began recently and results from activities that began in late 2021 are reported here. Comparisons between the previous and current facilities are provided.

43 PARTICLE ACCELERATORS↗

Accelerator commissioning and rare isotope identification at the Facility for Rare Isotope Beams

In 2008, Michigan State University was selected to establish the Facility for Rare Isotope Beams (FRIB). Construction of the FRIB accelerator was completed in January 2022. Phased accelerator commissioning with heavy ion beams started in 2017 with the normal-conducting ion source and radio-frequency quadrupole. In April 2021, the full FRIB driver linear accelerator (linac) was commissioned, with heavy ion beams accelerated to energies above 200 MeV/nucleon by 324 superconducting radiofrequency (SRF) resonators operating at 2 K and 4 K with liquid-helium cooling. Further, in preparation for high-power operation, a liquid lithium charge stripper was commissioned with heavy ion beams up to uranium-238, followed by the simultaneous acceleration of multiple-charge-state heavy ion beams to energies above 200 MeV/nucleon. In December 2021, selenium-84 was produced with the FRIB target using a krypton-86 primary beam, demonstrating FRIB’s capability for scientific discovery.

07 ISOTOPE AND RADIATION SOURCES↗

Commissioning Status of the Linac for the Facility for Rare Isotope Beams

The Facility for Rare Isotope Beams will be completed in late 2021. Here, we report here on the current efforts to commission the first stages of the 200-MeV/u superconducting, continuous wave heavy-ion linac. The statuses of the cryogenic plant and its distribution system, the accelerator cryomodule commissioning and operations, the ion source and front end transport development, the radio-frequency quadrupole commissioning, and then beam dynamics development to support high-power operation are reviewed. Plans for commissioning the remainder of the linac systems are presented.

43 PARTICLE ACCELERATORS↗