JLab New Injector Cryomodule Design, Fabrication and Testing

A new Injector Cryomodule (INJ CM) aimed to replace the existing Quarter Cryomodule in the CEBAF tunnel has been developed at Jefferson Lab (JLab). It is scheduled to be first tested in the Cryomodule Test Facility (CMTF) for module performance then the Upgraded Injector Test Facility (UITF) with electron beam. This new cryomodule, hosting a 2-cell and 7-cell cavity, is designed to boost the electron energy from 200 keV to 5 MeV and permit 380 ?A ? 1.0 mA of beam current. The 2-cell cavity is a new design whereas the 7-cell cavity is refurbished from a low loss cavity from the retired JLab Renascence Cryomodule. The INJ CM adopts quite a few designs from the JLab 12 GeV Upgrade Cryomodule (C100). Examples of this include having the cold mass hung from a spaceframe structure by use of axial and transverse Nitronic rods, cavities to be tuned by scissor-jack style tuners and the end cans are actually modified from C100 style end cans. However, this new INJ CM is not a quarter of the C100 Cryomodule. This paper focuses on the major design features, fabrication and alignment process and testing of the module and its components.

Cheng, Guangfeng↗

Cavity Processing and Testing Activities at Jefferson Lab for LCLS-II Production

Cryomodule production for LCLS-II is well underway at Jefferson Lab. This paper explains the process flow for production cavities, from being received at the Test Lab to being assembled onto cavity strings. Taking our facility and infrastructure into consideration, process optimization and process control are implemented to ensure high quality products.

Davis, Giles↗

Progress towards Nb3Sn CEBAF Injector Cryomodule

Operations at 4 K instead of 2 K have the potential to reduce the operational cost of an SRF linac by a factor of 3, if the cavity quality factor can be maintained. Cavities coated with Nb3Sn have been shown to achieve the accelerating gradients above 10 MV/m with a quality factor around 1010 at 4 K. Because such performance is already pertinent for CEBAF injector cryomodule, we are working to extend these results to CEBAF accelerator cavities envisioning coating of two CEBAF 5-cell cavities with Nb3Sn. They will be installed in an injector cryomodule and tested with beam. The progress on this path is reported in this contribution.

Eremeev, Grigory↗

JLab cryomodule assembly infrastructure modifications for LCLS-II

The Thomas Jefferson National Accelerator Facility is currently engaged, along with several other DOE national laboratories, in the Linac Coherent Light Source II project (LCLS II). The SRF Institute at Jefferson Lab will be building 1 prototype and 17 production cryomodules based on the TESLA / ILC / XFEL design. Each cryomodule will contain eight nine cell cavities with coaxial power couplers operating at 1.3 GHz. New and modified infrastructure and assembly tooling is required to construct cryomodules in accordance with LCLS-II requirements. The approach for modifying assembly infrastructure included evaluating the existing assembly infrastructure implemented at laboratories world-wide in support of ILC and XFEL production activities and considered compatibility with existing infrastructure at JLab employed for previous cryomodule production projects. These modifications include capabilities to test cavities, construct cavity strings in a class 10 cleanroom environment, assemble cavity strings into cryostats, and prepare cryomodules for cryogenic performance testing. This paper will give a detailed description of these modifications.

Daly, Edward F.↗

Injector Cavities Fabrication, Vertical Test Performance and Primary Cryomodule Design

After the electromagnetic design and the mechanical design of a β=0.6, 2-cell elliptical SRF cavity, the cavity has been fabricated. Then both 2-cell and 7-cell cavities have been bench tuned to the target values of frequency, coupling external Q and field flatness. After buffer chemistry polishing (BCP) and high pressure rinses (HPR), Vertical 2K cavity test results have been satisfied the specifications and ready for the string assembly. We will report the cavity performance including Lorenz Force Detuning (LFD) and Higher Order Modes (HOM) damping data. Its integration with cavity tuners to the cryomodule design will be reported.

43 PARTICLE ACCELERATORS↗

Summary Report for the C50 Cryomodule Project

The Thomas Jefferson National Accelerator Facility has recently completed the C50 cryomodule refurbishment project. The goal of this project was to enable robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project included removal, refurbishment and reinstallation of ten CEBAF cryomodules at a rate of three per year. The refurbishment process included reprocessing of SRF cavities to eliminate field emission and to increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New 'dogleg' couplers were installed between the cavity and helium vessel flanges to intercept secondary electrons that produce arcing in the fundamental Power Coupler (FPC). Other changes included new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuner. Damaged or worn components were replaced as well. All ten of the refurbished cryomodules are now installed in CEBAF and are currently operational. This paper will summarize the performance of the cryomodules.