Software and Firmware-logic Design for the PIP-II Machine Protection System Mode and Configuration Control at Fermilab

The PIP-II Machine Protection System (MPS) requires a dedicated set of tools for configuration control and management of the machine modes and beam modes of the accelerator. The protection system reacts to signals from various elements of the machine according to rules established in a setup database in the form of a Look-Up-Table filtered by the program Mode Controller. This is achieved in accordance with commands from the operator and governed by the firmware logic of the MPS. This paper describes the architecture, firmware logic, and implementation of the program mode controller.

43 PARTICLE ACCELERATORS↗

Experience With Machine Protection Systems At PIP2IT

The PIP-II Injector Test 1 PIP2IT facility accelerator was assembled in multiple stages in 2014 $-$ 2021 to test concepts and components of the future PIPII linac that is being constructed at Fermilab. In its final configuration, PIP2IT accelerated a 0.55 ms x 20 Hz x 2 mA H$-$ beam to 16 MeV. To protect elements of the beam line, a Machine Protection System MPS was implemented and commissioned. The beam was interrupted faster than 10$\mu$s when excessive beam loss was detected. The paper describes the MPS architecture, methods of the loss detection, procedure of the beam interruption, and operational experience at PIP2IT.

43 PARTICLE ACCELERATORS↗

The Web as the Primary Control System User Interface

Fermilab's Control System uses a proprietary application framework written decades ago. Considered state-ofthe- art at one time, the control system now lacks many features we expect from a modern interface and needs to be updated. Our investigation of Web browsers and JavaScript revealed a powerful, rich, and state-of-the-art development environment. We discuss JavaScript frameworks, JavaScript language features, and packaging tools. We also discuss issues we need to resolve before we are confident this can become our primary application platform.

43 PARTICLE ACCELERATORS↗

Experience with Long-Pulse Operation of the PIP2IT Warm Front End

The warm front end of the PIP2IT accelerator, assem-bled and commissioned at Fermilab, consists of a 15 mA DC, 30 keV H- ion source, a 2 m long Low Energy Beam Transport (LEBT) line, and a 2.1 MeV, 162.5 MHz CW RFQ, followed by a 10 m long Medium Energy Beam Transport (MEBT) line. A part of the commissioning efforts involves operation with the average beam power emulating the operation of the proposed PIP-II accelera-tor, which will have a duty factor of 1.1% or above. The maximum achieved power is 5 kW (2.1 MeV x 5 mA x 25 ms x 20 Hz). This paper describes the difficulties encoun-tered and some of the solutions that were implemented.

43 PARTICLE ACCELERATORS↗

Upgrading the Fermilab Fire and Security Reporting System

Fermilab's homegrown fire and security system (known as FIRUS) is highly reliable and has been used nearly thirty years. The system has gone through some minor upgrades, however, none of those changes made significant, visible changes. In this paper, we present a major overhaul to the system that is halfway complete. We discuss the use of Apple's OS X for the new GUI, upgrading the servers to use the Erlang programming language and allowing limited access for iOS and Android-based mobile devices.

43 PARTICLE ACCELERATORS↗