Search NASA⌕ Search

Engineering topics

Ortega, Fernando

Publications and source records attributed to Ortega, Fernando.

Operating displays - new concept: high performance displays - 118

New control rooms in Nuclear Power Plants using digital Distributed Control System (DCS) operated with software displays, are providing thousands of signals to the operating crew. When an event happens, the Flood of information provided to operators could obscure the initiator event increasing the operator response time, work load and complicating the selection of the actions to be performed. There are some initiatives that are trying to minimize the 'avalanche effect' as the alarm engineering filtering and prioritization or diagnostic displays. Likewise, new control rooms are lost the availability to know the plant status just with a quick glance to the panel indicators. Regarding Small Modular Reactors, where in some cases four operators should monitor and control twelve reactors, these problems are even more significant. The challenge is to find a solution, based on current digital systems, that supply information to operators in order to prevent events and take early actions to minimize or avoid any unexpected incident. In order to minimize human errors, Tecnatom has developed a specific set of displays, called 'High Performance Displays' (HPD) based on objectives, work environment limitation, and non-anticipated events. These displays are being design following the HFE standards: applying the NUREG-0711 elements to identify the information that they have to content and the NUREG-0700 to design the interface. The function of these displays is monitoring the plant situation in a way that the operators are able to recognize any potential event at a simple glance but controlling thousands of signals through pattern recognition, symmetries, regular polygons and colors. The objective of the HPD is to provide an integrated function minimizing the tunnel effect and reduce the workload during the diagnosis phase. Moreover, HPD enhance operators to take the right actions to anticipate the response to any event, even avoiding it, if possible This paper analyzes how HPD's have been design as well as presents the results of a preliminary validation of their capabilities. The preliminary validation is a reduce validation in a full scope simulator running two representative scenarios of abnormal and emergency operation. The analysis is focused on the first stage of the event, i.e. the detection phase, HPD's have been installed in a generic full scope simulator of a nuclear power plant, digital controlled. Both scenarios have been performed by two different operator crews. The first operator shift has worked with the conventional human machine interface, that is, displays similar to the ones currently installed in existing nuclear power plant with digital control. The second crew, reproduce the same scenarios but with HPD available. The studio collects preliminary data in order to compare results, draw lesson learned from the experience to improve HPD design, and find solutions in terms of reducing human errors, human workload, and increase the availability of the plant. (authors)

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

A structured data model frame for human factors application - 175

Building a Human Factors analysis and Verification and Validation case for new control rooms and even for control room modifications is a highly labor intensive project. Any optimization that can be made in the process translates into savings in the overall control room project schedule and budget. Several support tools from word, to excel, mind maps and databases have been traditionally used by human factors practitioners to conduct the analysis and document its results. While the use of these tools has had satisfactory results, they don't provide in our experience strong enough means for configuration control management, to avoid duplicities, streamline the analysis processes and allow collaborative team efforts. This paper documents how the established practices (methods, processes and tools) were questioned, which were the sources for comparison and how the results were translated into requirements for the new tool constituting the data frame model for Human Factors Engineering applications. The exercise has allowed us to evaluate the efficiency of our current practices in comparison to previous ones while improving our compliance with the quality assurance standards. (authors)

42 ENGINEERING↗

A new APDS approach - alarm processing based on alarm prioritization - 201

We take for granted that the advances in technology bring improvements to the conditions in which humans perform activities associated to them. Is that the case for digital alarm systems in nuclear power plants? The answer is not that simple. A review of the related literature, shows that still, the single most significant problem with alarm systems, is the large number of alarm messages presented to the operator at once. This is an issue that affects analog I and C control rooms with conventional annunciators and gets aggravated in digital I and C based control rooms. Digital alarm systems present the alarms in the form of lists in computer screens. This kind of presentation forces the operator to scroll or navigate pages to review the active alarms. Also, the alarm lists do not allow the operator to apply the pattern recognition practices acquired during training when using with fixed position alarm systems. An Alarm Processing and Diagnostic System (APDS) facilitates the alarm monitoring task by applying alarm reduction techniques based on alarm priorities. It allows the operators to focus on the most important alarms during plant upsets. A new generation of APDS should be based in an improved alarm analysis methodology. To develop such methodology, Tecnatom reviewed applicable standards and our own alarm analysis experiences. This paper documents the process and conclusions of the methodology development. (authors)

42 ENGINEERING↗

Computerized procedure systems: procedure edition and maintenance challenges - 232

Very few nuclear power plants are using computerized procedures to guide the control room operation. A CPS implementation consists of two processes: digitalization and computerization. The former deals with the transformation of paper-based procedure into a digital data; the latter is referred to as the addition to that data of extra information that is meaningful for decision-making. This information may include real-time data (plant parameter values and binary process values to indicate equipment states), provide access to trends and historical data, etc. In order to be efficient and to optimize the digitalization and computerization processes, these set of aids should be implemented at the same time as operating procedures are digitalized There are references of plants having successfully implemented Computerized Procedures Systems (CPS) for emergency procedures, but when questioned about normal or abnormal operating procedures, operators and plant management seem reluctant to take that step. Given that a CPS is meant, by design concept, to increase operation crew efficiency by facilitating the procedures execution and reducing human error, why are we reluctant to enjoy CPS benefits in the most common plant status (i.e. normal operation)? Although there are many answers to this question, one is shared by most of the users: CPSs are not designed for editing and maintaining procedures easily and reliably. Normal operating procedures, in opposition to the emergency procedures, are often reviewed. Nowadays, these edition activities are performed easily with a word processor software and using paper, but what is required when dealing with a CPS? (authors)

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Application of HFE to the design and V and V of a computerized procedure system: benefits and challenges - 234

The application of Human Factors Engineering (HFE) practices to the Human Machine Interface design and subsequent Verification and Validation (V and V) is a widely applied practice when talking about the design of complete control rooms or important control room modernizations, but not so often applied to the design of computerized operator support systems. In order to overcome the challenges faced on designing a Computerized Operation Support System (COSS) that meets the process efficiency requirements and integrates seemingly with hybrid plant operation concept, the involvement of a HFE team early in the COSS design and implementation process along with operation, Instrumentation and Control (I and C) and cybersecurity experts will guarantee the project success. This paper documents the HFE process applied during the design and evaluation of a Computerized Procedure System (CPS) and how final product was shaped to ensure that the transition from paper to computerized procedures will help in meeting Delivering the Nuclear Promise (DNP) goals, improving plant efficiency. The HFE program included the following activities: 1. A review of existing operating experience 2. An analysis of functions and tasks associated to the use and maintenance of CPS 3. A design verification of the system to meet guidelines prescribed in the NUREG-0700 (Rev.2), requirements of the ISG-05 and cybersecurity criteria (NEI 08-09, IEC-62646, EPRI 1015313, these among others). 4. An integrated system validation in a full scope simulator The application of HFE practices in the design and implementation of COSS helps not only to ensure that efficiency and safety improvement requirements are met, but also to evaluate the potential return of the investment, that such tools should bring. (authors)

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Integrated emergency control board including design extended conditions for Krsko NPP - 297

In the aim of implementing post-Fukushima safety measures, Krsko Nuclear Power Plant is developing a Safety Upgrade Program. Krsko NPP is upgrading the remote shutdown capabilities and implementing ways to prevent and mitigate the consequences of potential Severe Accidents. This modification enhances remote shutdown capabilities of the plant to prevent potential severe accidents and improve the ways to mitigate their consequences. Within the set of plant design modifications, addressed the design, construction, and commissioning, of a new Emergency Control Room (EMCB. Tecnatom is the responsible of the design modification of the plant together with Idom, that participates with Tecnatom in the project as a joint venture, who provides a new set of field instrumentation, including its design and the corresponding wiring. EMCB integrates Human- System Interface throughout centralizing capabilities to safety shutdown and cooldown the plant as well as to control the new Design Extension Systems. The process relies on a Human Factors Engineering (HFE) analysis applying a specific methodology based on NUREG-0711 . Tecnatom has developed a specific HFE Program Management Plan to proceed with the analysis in a documented, traceable and reliable way. HFE activities ends with an Integrated System Validation in the actual full scope simulator involving MCR crews. This paper describes different phases of the project, the integrated schedule between HFE and I and C activities, benefits of upgrading main and emergency control rooms beyond design bases and addresses Tecnatom lessons learned obtained during the project execution. (authors)

21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS↗