NASA NTRS2013
This paper discusses a Reliability, Availability, and Maintainability (RAM) independent assessment conducted to support the refurbishment of the Compressor Station at the NASA Langley Research Center (LaRC). The paper discusses the methodologies used by the assessment team to derive the repair by replacement (RR) strategies to improve the reliability and availability of the Compressor Station (Ref.1). This includes a RAPTOR simulation model that was used to generate the statistical data analysis needed to derive a 15-year investment plan to support the refurbishment of the facility. To summarize, study results clearly indicate that the air compressors are well past their design life. The major failures of Compressors indicate that significant latent failure causes are present. Given the occurrence of these high-cost failures following compressor overhauls, future major failures should be anticipated if compressors are not replaced. Given the results from the RR analysis, the study team recommended a compressor replacement strategy. Based on the data analysis, the RR strategy will lead to sustainable operations through significant improvements in reliability, availability, and the probability of meeting the air demand with acceptable investment cost that should translate, in the long run, into major cost savings. For example, the probability of meeting air demand improved from 79.7 percent for the Base Case to 97.3 percent. Expressed in terms of a reduction in the probability of failing to meet demand (1 in 5 days to 1 in 37 days), the improvement is about 700 percent. Similarly, compressor replacement improved the operational availability of the facility from 97.5 percent to 99.8 percent. Expressed in terms of a reduction in system unavailability (1 in 40 to 1 in 500), the improvement is better than 1000 percent (an order of magnitude improvement). It is worthy to note that the methodologies, tools, and techniques used in the LaRC study can be used to evaluate similar high value equipment components and facilities. Also, lessons learned in data collection and maintenance practices derived from the observations, findings, and recommendations of the study are extremely important in the evaluation and sustainment of new compressor facilities.