Search NASA⌕ Search

Engineering topics

Takahashi, Koji

Publications and source records attributed to Takahashi, Koji.

ITER ECH Transmission Line System Design and Status

The electron cyclotron (EC) heating & current drive (H&CD) system on ITER provides plasma heating by generating, transmitting, and launching high-intensity, high-frequency (170 GHz) electromagnetic wave energy steerable across the plasma cross-section. The transmission line (TL) subsystem connects the Matching Optics Unit (MOU) on each of the 24 gyrotrons to the 32 feed points in the four upper launchers and the 24 feed points in the equatorial launcher. Each TL must be able to operate at up to 1.2 MW of input power for up to 1 hour pulse lengths. The TL system contains 50 mm water-cooled corrugated waveguide, 90o miter bends, 140o miter bends, polarizer miter bend pairs, switches, expansion units, pumpouts, DC breaks, MOU-TL adapters, Radio Frequency (RF) loads, and isolation shutter valves. A detailed finite element analysis has been used to verify the thermo-mechanical performance of each component. The microwave performance has been analyzed using a 2-D electromagnetic code combined with a Monte Carlo code. This approach allows the impact of manufacturing and installation tolerances to be assessed and optimized to provide a high probability of achieving the system performance requirements. Prototypes of the waveguide and TL components have been fabricated and tested at high-power. Production contracts are now being issued for fabrication and delivery of the waveguide and components to ITER.

Hanson, Gregory↗

Recent Progress of JT-60SA Project toward Plasma Operation

Superconducting tokamak JT-60SA plays an essential role in fusion research and development by supporting and complementing ITER project, providing directions to the DEMO design activity and fostering next generation scientists and engineers. Since the incident of the Equilibrium Field coil #1 during the Integrated Commissioning (IC) in March 2021, both EU and JA Implementing agencies (IAs) have examined how to ensure safety operation of JT-60SA by mitigating the risk of possible discharge occurrence inside the cryostat. Based on the experience of the Global Paschen tests, the IAs have established a strategy of risk mitigation measures, which is a combination of (i) reinforcement of insulation, (ii) avoiding unnecessary voltage application to the coil systems and (iii) immediate de-energization of the coils when deteriorated vacuum condition is detected. Thanks to the considerable efforts of the Integrated Project Team (IPT) members, the IC restarted in May 2023. After the confirmation of superconducting state of coil systems (TF, EF and CS), the coil energization test and the plasma operation (OP-1) starts. The first plasma was successfully achieved on 23 October 2023 with a limited value of applied voltage and current to the coils. The plasma configuration control will be also confirmed with low plasma current and low auxiliary heating power conditions. Based on the IO-F4E-QST collaboration, activities of JT-60SA have been shared with the IO and provided an important lesson learned for ITER assembly and commissioning, and will provide an outstanding contribution to fusion research at large. After OP-1, Maintenance & Enhancement phase 1 (M/E-1) starts from January 2024, in which in-vessel components are installed, and heating system and diagnostic system are extensively upgraded to allow high power heating experiment planned in OP-2. In order to make the best use of JT-60SA, newly organized JT-60SA experiment team will refine the research plan in the future high heating power operation phase.

Broader Approach activities↗