The Weapons Pit production manufacturing team completed pit build 21-1 assembly operations on December 23, 2020. This build utilized all essential flow sheet steps and included the second -01 long tube cut off extension and welding activity. This is the best build produced in the MC4597-01 pit program to date. Final out-of-line operations, non-destructive evaluation, and radiography was completed during the week of January 4. Depending on the results from high energy radiography, this pit will be considered to be a candidate for CERT-02 and shipment to Lawrence Livermore National Laboratory in support of pit certification. It is notable that this build was completed while concurrently making Plutonium (Pu) metal, producing additional castings, machining Pu parts for Build 22, completing disassembly of two pits, supporting Nightshade B Pu target characterization, and precision machining of Jasper certification base plates.