Abstract
Two orbital test plans were prepared to verify one of the passive cryogenic storage tank/feedline candidate designs. One plan considered the orbital test article to be launched as a dedicated payload using an Atlas F burner launching configuration. The second plan proposed to launch the orbital test article as a secondary payload on the Titan E/Centaur proof flight. The secondary payload concept was pursued until January 1973, when work to build the hardware for this phase of the contract was terminated for lack of a sponsor for the flight. The dedicated payload launched on an Atlas F is described.