The MICRO-BOSS scheduling system: Current status and future efforts
Abstract
In this paper, a micro-opportunistic approach to factory scheduling was described that closely monitors the evolution of bottlenecks during the construction of the schedule and continuously redirects search towards the bottleneck that appears to be most critical. This approach differs from earlier opportunistic approaches, as it does not require scheduling large resource subproblems or large job subproblems before revising the current scheduling strategy. This micro-opportunistic approach was implemented in the context of the MICRO-BOSS factory scheduling system. A study comparing MICRO-BOSS against a macro-opportunistic scheduler suggests that the additional flexibility of the micro-opportunistic approach to scheduling generally yields important reductions in both tardiness and inventory. Current research efforts include: adaptation of MICRO-BOSS to deal with sequence-dependent setups and development of micro-opportunistic reactive scheduling techniques that will enable the system to patch the schedule in the presence of contingencies such as machine breakdowns, raw materials arriving late, job cancellations, etc.
Keep this discovery
Explore connections, maps & timelines
Sadeh, Norman M.. 1992-05-01. The MICRO-BOSS scheduling system: Current status and future efforts. https://ntrs.nasa.gov/citations/19930009479
Cite the original work for its findings. Save a collection to share your selection of sources.