Abstract
Over the last year, the Glenn Research Center's Icing Research Tunnel (IRT) underwent a major $5.2 million rehabilitation project as part of the Construction of Facilities program. The scope of the project included redesign and replacement of the 55-yr-old heat exchanger, the addition of fan outlet guide vanes for flow conditioning downstream of the 25-ft-diameter fan, and redesign and replacement of the C and D corner-turning vanes. The purpose of the rehabilitation was to replace old portions of the infrastructure and to improve the aerodynamic flow quality in the tunnel.
Keep this discovery
Explore connections, maps & timelines
Kevdzija, Susan L.. 2001-03-01. Multimillion Dollar Construction Project Completed in Glenn's Icing Research Tunnel. https://ntrs.nasa.gov/citations/20050199460