DOE OSTI · 1128756
Accelerator/Experiment Operations - FY 2013
Abstract
The low-energy and high-energy neutrino beams, the SeaQuest beam, and the Test Beam in the Meson area were shutoff on May 1, 2012 to begin work on the accelerator upgrades for NOvA (ANU), and for overall accelerator system maintenance. The shutdown of the Main Injector ended July 30, 2013, with the startup of the Accelerator systems for commissioning. Vacuum issues in the Main Injector delayed Commissioning and neutrino running until September.
Keep this discovery
Explore connections, maps & timelines
Dixon, R., Geelhoed, M., Hahn, S., Harris, D., Henderson, S., McFarland, K., Moore, C., Pahlka, B., Plunkett, R., Soha, A. K., Van de Water, R.. 2014-01-28. Accelerator/Experiment Operations - FY 2013. https://doi.org/10.2172/1128756
Cite the original work for its findings. Save a collection to share your selection of sources.