The low-energy and high-energy neutrino beams, the SeaQuest beam, and the Test Beam in the Meson area were shutoff on May 1, 2012 to begin work on the accelerator upgrades for NOvA (ANU), and for overall accelerator system maintenance. The shutdown of the Main Injector ended July 30, 2013, with the startup of the Accelerator systems for commissioning. Vacuum issues in the Main Injector delayed Commissioning and neutrino running until September.