Preliminary Technoeconomic Analysis for Power Generation from Coal Water Slurry Using Modular Staged-OMB Gasifier
Abstract
Trimeric performed a technoeconomic analysis for a proposed 5 MWe gross modular gasification power generation facility. The cost estimate was used to determine the economic advantages of the proposed modular, staged-OMB gasifier in comparison to other modular gasifier designs. The project, Staged OMB for Modular Gasifier/Burner, is led by The University of Kentucky Center for Applied Energy Research (UK CAER) and supported by East China University of Science and Technology (ECUST) and Trimeric Corporation. A high-level summary of the findings from this project are presented below.
Explore related subjects
Keep this discovery
Explore connections, maps & timelines
Sexton, Andrew. 2022-02-15. Preliminary Technoeconomic Analysis for Power Generation from Coal Water Slurry Using Modular Staged-OMB Gasifier. https://doi.org/10.2172/1807570
Cite the original work for its findings. Save a collection to share your selection of sources.