As the next phase of Project Tundra, Minnkota Power Cooperative (MPC) completed a front-end engineering and design (FEED) study to install a post-combustion CO 2 capture system (CCS) at the MPC operated (Square Butte Electric Cooperative-owned) Milton R. Young Station (MRYS) Unit 2 (MRY2), a 477-MW power plant fueled by North Dakota lignite. The project team completed the FEED with Fluor’s Econamine FG Plus℠ (EFG+) technology and is taking the next steps leading up to start of construction. Team members included FEED technical lead Fluor Enterprises (Fluor); owner’s engineer and balance of plant (BOP) engineer Burns & McDonnell (BMcD); leading carbon capture consultants (David Greeson Consulting, Hunt International Energy Services); environmental consultants (AECOM, Agora Environmental), other BOP engineering consultants (Golder Associates, Nels); cost-share funding agency, the North Dakota Industrial Commission (NDIC); and the Energy & Environmental Research Center (EERC). Project Tundra’s goal is to implement carbon capture, utilization, and storage (CCUS) in North Dakota, while preserving the use of lignite. Future options could lead to revitalizing legacy oil fields and creating a new CO 2 enhanced oil recovery (EOR) industry. The topic of this report is the FEED study for the carbon dioxide capture portion of Project Tundra. Building on the findings of a pre-FEED study for MRY2, the key deliverables contained in this FEED study are: a) design, costing, and performance data needed to commence project financing activities; b) engineering and material balances required to file for all project permits; and c) a final project schedule. Based on the results of the previous pre-FEED study, MPC and its team evaluated two options to provide the large amount of steam needed to operate the CCS: 1) installation of new natural gas package boilers and a new pipeline to supply natural gas to the facility and 2) extraction of steam from the existing MRYS steam turbine generator. The FEED study was performed using the package boilers option, as it was deemed to have the lowest technical risk, overall cost, and cost uncertainty. A key feature of the design, however, was the mixing the natural gas boilers’ flue gas with the MRY2 flue gas. This increased the size of the CCS system. This design also enabled the tie-in of Unit 1 flue gas for times when Unit 2 is offline. The CCS was designed to capture a combined 12,978 short tons per day (STPD) of CO 2 from the flue gases produced by the existing MRY Unit 2 along with flue gas produced by the new boiler package within the CCS. The 12,978 STPD CO 2 capture is achieved by normally processing 100% of the total available MRY Unit 2 flue gas (considering full load operation) and 100% of the boiler package flue gas, then removing 90% of the CO 2 available from the processed flue gas streams.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Pfau, Gerry, Wolf, Dylan, Laudal, Daniel, Bleth, Craig, Greeson, David. 2023-02-20. Front-End Engineering and Design: Project Tundra Carbon Capture System (Final Report). https://doi.org/10.2172/1987837

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Wyoming Trails Carbon Hub (WyoTCH)

The Wyoming Trails Carbon Hub (WyoTCH) project completed a front-end engineering and design (FEED) study for a commercial-scale, open-access carbon dioxide (CO 2 ) transport pipeline in Wyoming under U.S. Department of Energy (DOE) Award DEFE0032347, funded through the Bipartisan Infrastructure Law Carbon Capture Technology Program and administered by the National Energy Technology Laboratory. The project’s approach of designing a multi-source, multi-destination pipeline, rather than a dedicated line serving a single project, would lower the barrier to entry for individual CO 2 projects. The projects would leverage Wyoming's concentrated industrial and power generation CO 2 sources, its existing CO 2 pipeline infrastructure, and its extensive CO 2 storage and utilization capacity. This is the project's final technical report.

01 COAL, LIGNITE, AND PEAT↗

Engineering-Scale Validation of Novel Algae CO 2 Capture and Bioproducts Technology

The purpose of this project was to advance and scale the algae-based technology Helios-NRG has been developing for capture of CO 2 from the flue gas of coal-burning power plants with conversion of the CO 2 to high-value products. In order to encourage the process becoming commercial and be adoptable, it is essential that the cost of CO 2 be close to net zero or slightly revenue positive. Two methods to achieve this are reducing the cost of operations through efficiencies and selling of products derived from conversion. Helios and the project team partners have accomplished the goals of furthering the technology to be more scalable and substantially lower cost with a defined pathway for commercialization.

01 COAL, LIGNITE, AND PEAT↗

Innovative Biomonitoring and Remediation of Heavy Metals Using Phytotechnologies at the Savannah River Site (SRS) Coal Combustion Product (CCP) Impoundment Sites

The Savannah River Site (SRS) contains legacy coal combustion product (CCP) impoundments that are impacted by elevated concentrations of heavy metals and radionuclides, posing long-term risks to soil health, ecosystem functioning, and environmental sustainability. Traditional environmental monitoring approaches rely primarily on chemical analyses to quantify contaminant concentrations but often provide limited information regarding biological responses or ecosystem recovery. This project addressed these limitations by integrating environmental chemistry, microbial ecology, artificial intelligence (AI), and bioremediation into a comprehensive framework for environmental diagnostics and restoration of contaminated soils. The overarching goal of this collaborative project between Florida A&M University (FAMU) and the University of Georgia's Savannah River Ecology Laboratory (SREL) was to develop innovative biomonitoring and remediation strategies for heavy metal-contaminated CCP impoundment sites at the Savannah River Site. Specifically, the project sought to (i) characterize heavy metal contamination, (ii) determine microbial responses to contamination, (iii) isolate indigenous heavy metal-resistant microorganisms for remediation applications, (iv) develop a microbial ecological health index using machine learning, and (v) optimize fungal-mediated bioremediation using artificial intelligence.

01 COAL, LIGNITE, AND PEAT↗