The Salt Waste Processing Facility (SWPF), located at the Savannah River Site (SRS) in Aiken, South Carolina, is a multi-billion dollar Liquid Radioactive Waste (LRW) processing facility that represents the keystone for the U.S. Department of Energy (DOE)-EM clean-up mission at SRS. The SWPF facilitates DOE-EM clean-up at SRS by decontaminating the salt waste, which is the dominant volumetric component in the LRW tanks, thereby allowing the cleaned salt waste to be removed from the tanks and stabilized into an approved grout-based final waste form. The small volume of removed radionuclides is sent to the Defense Waste Processing Facility (DWPF) for vitrification. Emptied LRW storage tanks are then grouted into an approved configuration for final closure. The SWPF project is currently 100% complete with design, 80% complete with construction, and 10% complete with commissioning. To date there have been numerous lessons learned with regard to project acquisition, design, procurement, construction, and quality assurance (QA) approaches (both good practices and mistakes) that are considered to be of significant value in improving the state of major project execution within the DOE-EM clean-up program as well as to the wider DOE enterprise. An overview of the current SWPF project status is provided and key lessons learned in the aforementioned areas are presented relative to improving future DOE major project execution performance. Specific areas to be addressed include strategies to optimize integration of design and nuclear safety, constructability tools for design and construction synchronization, commercial grade dedication (CGD) approaches to mitigate atrophy in the nuclear supply chain, and QA perspectives to facilitate effective and efficient project execution. (authors)

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Burns, THomas D.. 2015-07-01. Salt Waste Processing Facility project lessons learned: Acquisition through construction - 15518. https://searchnasa.com/record/osti%3A22824404/salt-waste-processing-facility-project-lessons-learned-acquisition-through-construction-15518

Citations retain the original authors and DOI and include this site’s record URL. If this discovery service contributed to your research, you can also cite Search NASA by Indiciae: BibTeX · RIS.

KEEP EXPLORING

Related reports

West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2025

The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2025. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of the DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, the evaluation of data collected in 2025 continued to indicate that WVDP activities posed no threat to public health or safety, or to the environment.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗