Search NASA⌕ Search

DOE OSTI · 23028052

Lessons Learned from Hanford's Purex Tunnel 2 Structural Stabilization Project - 20509

Abstract

In 2019, U.S. Department of Energy (DOE) contractor CH2M Hill Plateau Remediation Company (CHPRC) completed structurally stabilizing the Plutonium Uranium Extraction Plant (Purex) waste storage Tunnel 2 with engineered grout. This action significantly reduced risk to Hanford workers, the surrounding community and environment by preventing future collapse of the tunnel and possible release of radioactive materials. Decades of plutonium production at the Purex facility required construction of two large underground tunnels for storage of highly contaminated plutonium processing equipment that had failed during the operation of Purex and other facilities across the Hanford Site. Following the partial collapse of Purex Tunnel 1 on May 9, 2017, DOE and CHPRC took immediate action to safely stabilize the collapsed section of the tunnel. The hole in the tunnel was filled the next day as a temporary stabilization measure, and no contamination was detected as a result of the partial collapse of the tunnel. Workers then stabilized Tunnel 1 in its entirety by filling with engineered grout, which also encapsulated the radioactive equipment and railcars within the tunnel. Grouting eliminated the risk of further collapse and stabilized the tunnel contents, all while not precluding future remedial actions or final closure decisions. While conducting an integrity analysis of Tunnel 1 by using construction drawings, photos and other historical documents, project teams also analyzed the much larger Purex Tunnel 2. The analysis found Tunnel 2 did not meet current codes for structural integrity, and it may not be able to bear the weight of the soil above the tunnel. Therefore, it was determined that Tunnel 2 was also at risk of collapse. DoE's independent panel of experts determined grouting to be the best choice for stabilizing Tunnel 2 because it provides the highest level of stability and protection, and does not preclude future remedial actions. DOE authorized CHPRC to commence work and the Purex Tunnel 2 Structural Stabilization Project was launched in December of 2017. The paper will discuss the process of recognizing the following critical aspects and risks associated with stabilizing Tunnel 2, and the actions taken by the project team to mitigate these risks, including: - Tunnel investigation and data collection to assist with future remediation; - On-site batching and mock-ups to provide the large quantity of grout required for stabilizing the tunnel; - Workforce involvement and innovative actions that mitigated the project's most significant potential hazards, including traffic control; - Project team high level of execution translated into successful project execution. Sharing lessons learned from this critical risk-reduction effort can enhance the safety and efficiency of other complex and hazardous projects across the DOE complex. (authors)

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Farabee, Al, LaBonty, Andre. 2020-07-01. Lessons Learned from Hanford's Purex Tunnel 2 Structural Stabilization Project - 20509. https://www.osti.gov/biblio/23028052

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2025

The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2025. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of the DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, the evaluation of data collected in 2025 continued to indicate that WVDP activities posed no threat to public health or safety, or to the environment.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗