Valuing the Future Electric Grid: A Bid-Based Approach

Abstract

Energy storage resources (ESRs) and other zero marginal cost (ZMC) resources have unique characteristics that are not fully captured in today’s electricity planning and operations modeling tools. Because the modeling assumptions used in these tools are simplified approximations of how operations and investment decisions occur in the real-world, accurately representing cost and operational characteristics are key for determining how these resources impact price formation. Questions such as—Where should we build new transmission? Will a small modular reactor earn enough revenue to participate in the future electric grid? Is retrofitting a coal plant with carbon capture technology economically feasible?—all require accurate electricity prices, which aren’t available from today’s electricity planning and operations modeling tools. As an example, production cost models (PCMs) are heavily utilized tools that determine the cost and reliability of the electric system. However, as PCMs were developed to help thermal generators manage their fuel inventories, production cost modeling is largely based on fuel prices. Because ESRs do not incur fuel costs, they are often modeled as ZMC resources. In reality, ESRs incur opportunity costs as well as technology-specific (degradation) costs that are non-trivial to calculate but are important for price formation. In this research, we identify options to incorporate more realistic opportunity and degradation costs in ESR bidding algorithms. Expanding available bidding assumptions allows energy system modelers to develop more accurate economic valuations for ESRs, leading to more accurate price formation from leading energy system modeling tools.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Tarufelli, Brittany L. [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Li, Liping [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Eldridge, Brent C. [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Cornachione, Matthew A. [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Gibson, James A. [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Oikonomou, Konstantinos [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Somani, Abhishek [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Weimar, Mark [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)]. 2025-01-01. Valuing the Future Electric Grid: A Bid-Based Approach. https://doi.org/10.2172/2570497

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Nodal capacity expansion planning with flexible large-scale load siting

We propose explicitly incorporating large-scale load siting into a stochastic nodal power system capacity expansion planning model that concurrently co-optimizes generation, transmission, and storage expansion. The potential operational flexibility of some of these large loads is also taken into account by considering them as consisting of a set of tranches with different reliability requirements, which are modeled as a constraint on expected served energy across operational scenarios. We implement our model as a two-stage stochastic mixed-integer optimization problem with cross-scenario expectation constraints. To overcome the challenge of scalability, we build upon existing work to implement this model on a high performance computing platform and exploit scenario parallelization using an augmented Progressive Hedging Algorithm. The algorithm is implemented using the bounding features of mpisppy, which have shown to provide satisfactory provable optimality gaps despite the absence of theoretical guarantees of convergence. We test our approach and assess the value of this proactive planning framework on total system cost and reliability metrics using realistic testcases geographically assigned to San Diego and South Carolina, with datacenter and direct air capture facilities as large loads.

24 POWER TRANSMISSION AND DISTRIBUTION

From zonal to nodal capacity expansion planning: Spatial aggregation impacts on a realistic test-case

Solving power system capacity expansion planning (CEP) problems at realistic spatial resolutions is computationally challenging. Thus, a common practice is to solve CEP over zonal models with low spatial resolution rather than over full-scale nodal power networks. Due to improvements in solving large-scale stochastic mixed integer programs, these computational limitations are becoming less relevant, and the assumption that zonal models are realistic and useful approximations of nodal CEP is worth revisiting. Here, this work is the first to conduct a systematic computational study on the assumption that spatial aggregation can reasonably be used for ISO-scale CEP. By considering a realistic, large-scale test network based on the state of California with over 8000 buses, we find that well-designed small spatial aggregations can yield good approximations but that coarser zonal models may result in large distortions of investment decisions, e.g., capacity under-investment of up to 41% for the lowest resolution model considered.

24 POWER TRANSMISSION AND DISTRIBUTION

Multi-facility analysis using metered power data to quantify MRI energy use and utility bill costs across scanner operating modes

This study quantifies the energy consumption of magnetic resonance imaging (MRI) scanners across discrete operating modes during routine clinical workflows, based solely on electrical power measurements. Although previous studies have investigated MRI energy consumption within single hospitals or specific clinical settings, this research provides a broader and more systematic analysis. Researchers analyzed electrical power data and applied a previously developed semi-automatic method for identifying MRI operating modes using load duration curves for 20 MRI scanners across four different U.S. healthcare facilities, encompassing outpatient, inpatient, and mixed-use clinical settings. A key innovation is the inclusion of localized hourly utility rates to estimate costs, a parameter absent in prior literature. Key findings indicate significant variability in energy and cost profiles between weekdays and weekends. Scanner characteristics, including magnet strength, manufacturer, vintage, location, and clinical setting, influenced average daily energy consumption and power thresholds for operating modes. Notably, the clinical setting of a scanner predominantly determines its energy use. For example, the scanners in outpatient facilities consumed more energy. The breakdown of energy usage and costs by operating modes showed scanners spend between 61% and 93% of their time in nonproductive modes, with one outlier spending 34%. Average daily energy use for the scanners in the study ranged from 160 to 1069 kWh, with energy costs ranging from $\$$9 to $\$$149. This study uses an existing framework to quantify MRI energy behavior, leading to insights that can enable improved performance and cost savings across different healthcare environments.

24 POWER TRANSMISSION AND DISTRIBUTION