Corral Summit Pumped Storage Hydropower Hybrid: Site Suitability Assessment

Abstract

In 2024, Idaho National Laboratory (INL) and Pacific Northwest National Laboratory (PNNL) initiated a technical-assistance project to support Cat Creek Energy, LLC, (CCE) in evaluating site suitability for the proposed Corral Summit Pumped Storage Hydropower (PSH) project in south-central Idaho near Mackay Reservoir. The Corral Summit facility incorporates battery storage and photovoltaic (PV) solar arrays in a Trybrid configuration to deliver large-volume long-duration (LVLD) storage solutions for rural electric cooperatives in eastern Idaho. The evaluation process focused on determining the most-suitable location for the upper reservoir of the PSH system, guided by a comprehensive assessment framework spanning multiple categories, including physical characteristics, environmental constraints, building infrastructure, regulatory constraints, cultural resources and sensitivity, social factors, and power market and grid integration. Each site was analyzed based on a ranking scale (0–1), which scores ranging from “severely disfavored” to “highly favored,” allowing detailed comparisons of site-specific conditions. Categories such as hydraulic head, utilities corridor, land ownership, and transmission-grid limitations emerged as key contributors to the overall assessment. Site 2 (Idaho Trust) demonstrated a slight advantage over Site 1 (Bureau of Land Management) primarily due to favorable outcomes in regulatory constraints, building infrastructure, and power-market integration. However, Site 1 outperformed Site 2 in factors related to physical characteristics and social factors. The report emphasizes the need for further evaluation of both sites before clear determination of which site is preferred, due to the limited information available on either site at the time of this report. Key areas of evaluation to clearly define the preferred site are ecological impacts, cultural-resource surveys, and economic-feasibility assessments. For successful project execution, recommended follow-up actions include seismic and geotechnical surveys, groundwater and habitat monitoring, regulatory reviews of water rights and right-of-way agreements, cultural engagement with local tribal governments, and enhanced stakeholder strategies. These efforts will ensure the Corral Summit Trybrid facility meets local energy needs while balancing environmental, social, and regulatory responsibilities.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Atkinson, Trevor A. [Idaho National Laboratory (INL), Idaho Falls, ID (United States)] (ORCID:0000000275834830), Acharya, Mahesh [Idaho National Laboratory (INL), Idaho Falls, ID (United States)] (ORCID:0000000230097099), Reese, Stephen [Idaho National Laboratory (INL), Idaho Falls, ID (United States)] (ORCID:000000031390292X), Poudel, Bikash [Idaho National Laboratory (INL), Idaho Falls, ID (United States)] (ORCID:0000000188406491), Young, Danielle [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Vesty, Dana [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Adkisson, Kelsey [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], McFarland, Doug [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Giovando, Jeremy [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Weiss, Kyle [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)], Garbe, Jacob [Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)]. 2025-09-30. Corral Summit Pumped Storage Hydropower Hybrid: Site Suitability Assessment. https://doi.org/10.2172/3024391

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Creating a Training Dataset for Semantic Segmentation of Canal Networks for Irrigation Modernization

Canal infrastructure has provided critical irrigation water to the western United States for over a century. To continue providing vital water resources to the semi-arid West, irrigation systems must undergo maintenance and modernization. Many canal companies are resource-constrained, and because funding opportunities often require detailed knowledge of existing infrastructure, they can struggle to secure financial capital. We address this problem by creating training data for a semantic segmentation deep learning model to map canal networks throughout the western United States. To create a diverse and robust training dataset, we labelled 1-m NAIP imagery with the locations of no canals, wet canals, and dry/vegetated canals. Since creating these datasets is time consuming, we first developed a preprocessing methodology to identify canals within our four study areas. We used NAIP imagery and provided canal centerline data to buffer, standardize, and cluster the imagery, automating the labeling process as much as possible. However, this still required manual cleaning and manual classification of canal type. Challenges arose when canals were interrupted (e.g., road culverts or piped sections) or when nearby features shared similar characteristics (e.g., irrigated fields, trees, and shadows). Combining automated preprocessing with manual refinement produced four detailed canal masks to be used in the semantic segmentation model developed by Richard Tapia.

13 - HYDRO ENERGY↗

Representation and Impact of Water Head on Power System Planning and Operation

Representing water head information in power system model files, can provide a more realistic model of the system and thereby inform operation and planning personnel in the decision-making process. This article describes a procedure for modifying the power system model files (steady-state and dynamic) to represent water head information. Additionally, the impact of representing the water head on power system reliability studies including contingency analysis, cascading failure analysis and dynamic frequency response analysis has been investigated, using the modified power system models. This paper considers the detailed Western Electricity Coordination Council model during summer and winter conditions as the test system for the impact analysis. Results show that under reduced water head: 1) the number of critical voltage and branch flow violations increases; 2) chances of cascading failure and island formation increases; and 3) frequency nadir decreases as compared to those of the base cases where the water head information is not represented.

13 - HYDRO ENERGY↗

Floating Photovoltaics in Hydropower Reservoirs in the United States

This report presents a comprehensive analysis of the feasibility of floating photovoltaics (FPV) in federally regulated reservoirs within the continental United States (CONUS) and to present a methodology for capturing the true costs of deployment, potential environmental impacts, and regulatory pathways for open-loop hydropower reservoirs. It is intended for stakeholders who may not be solar industry experts but who are interested in exploring the potential for FPV in their reservoirs. While there are promising opportunities, particularly in enhancing dissolved oxygen (DO) levels and potentially improving compliance with existing hydropower licenses, the current capital costs of FPV are not yet competitive with traditional land-based solar installations at the utility-scale when comparing the LCOE results. A competitive financial outlook is achievable when applying a 30% Investment Tax Credit (ITC) and considering a 5% reduction from the baseline capital expenditures (CapEx) at the Tuckertown Reservoir in North Carolina case study. The study is structured around three key pillars of research: technical potential, environmental impacts and regulatory considerations, and technoeconomic analysis. This report provides a nationwide assessment of the opportunities for FPV in terms of capacity, measured in direct current megawatts (MWDC), in reservoirs managed by the U.S. Bureau of Reclamation (USBR), the U.S. Army Corps of Engineers (USACE), and the Federal Energy Regulatory Commission (FERC). Additionally, the report introduces a heuristic model for estimating the CapEx of utility-scale FPV projects (1–100 MW), offering a baseline cost estimate for stakeholders. Finally, the report applies these models to a case study of a hydropower reservoir in North Carolina to present site-specific results.

13 - HYDRO ENERGY↗