Fabrication experience of the pre-production PIP-II SSR2 cavities at Fermilab

The Proton Improvement Plan-II (PIP-II, [1]) linac will include 35 Single Spoke Resonators type 2 (SSR2). A total of eight pre-production SSR2 jacketed cavities will be procured and five installed in the first pre-production cryomodule. The mechanical design of the jacketed cavity has been finalized and it will be presented in this paper along with fabrication and processing experience. The importance of interfaces, quality controls and procurement aspects in the design phase will be remarked as well as lessons learned during the fabrication process. Furthermore, development studies will be presented together with other design validation tests.

43 PARTICLE ACCELERATORS↗

Progress on the Proton Power Upgrade Project at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion of the project, 2 MW of beam power will be available for neutron production at the existing first target station with the remaining beam power available for the future second target station. The project will install seven superconducting RF cryomodules and supporting RF power systems and ancillaries to increase the beam energy to 1.3 GeV . The injection and extraction region of the accumulator ring will be upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. Equipment is being received from vendors and partner laboratories, and installation is underway with three major installation outages planned in 2022-2024. The project is planned to be completed in 2025.

Barbier, Charlotte↗

Progress on the Proton Power Upgrade at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source (SNS) at Oak Ridge National Laboratory will double the proton power capability from 1.4 to 2.8 MW. This will be accomplished through an energy increase from 1.0 to 1.3 GeV and a beam current increase from 26 to 38 mA. The energy increase will be accomplished through the addition of 7 cryomodules to the linear accelerator (Linac). The beam current increase will be supported by upgrading several radio-frequency systems in the normal-conducting section of the Linac. Upgrades to the accumulator ring injection and extraction regions will accommodate the increase in beam energy. A new 2-MW-capable target and supporting systems will be developed and installed. Conventional facility upgrades include build-out of the existing klystron gallery and construction of a tunnel stub to facilitate future beam transport to the second target station. The project received approval to proceed with construction in October 2020. Procurements are in progress, and some installation activities have already occurred. Most of the installation will take place during three outages in 2022-2023. The project early finish is planned for 2025.

Barbier, Charlotte↗

PERLE A ‘STEPPING STONE’ FOR THE NEXT GENERATION ERLS

PERLE (Powerful ERL for Experiments) is a novel Energy Recovery Linac (ERL) test facility, which has been designed to validate choices for a 50 GeV ERL foreseen in the design of the LHeC and the FCC-eh, and to later serve a set of dedicated nuclear and particle physics experiments. Its main thrust is to probe high current, continuous wave (CW), multi-pass operation with superconducting cavities at 802 MHz (and perhaps testing other frequencies of interest). With very high transient beam power (~10 MW), PERLE offers an opportunity for controllable study of every beam dynamic effect of interest in the next generation of ERL design and become a ?stepping stone? between present state-of-art 1 MW ERLs and future 100 MW scale applications. PERLE design features flexible momentum compaction lattice architecture for six vertically stacked return arcs and a high current, 7 MeV, photo-injector. With only one pair of four cavity cryomodules, 500 MeV beam energy can be reached in three re-circulation passes, with beam currents of about 20 mA. The beam is decelerated in three consecutive passes back to the injection energy. Work on the engineering design of PERLE has just begun.

Bogacz, S.↗

Design, Manufacturing, Assembly, and Lessons Learned of the Pre-production 325 MHz Couplers for the PIP-II Project at Fermilab

Five 325 MHz high-power couplers will be integrated into the pre-production Single Spoke Resonator Type-II (ppSSR2) cryomodule for the PIP-II project at Fermilab. Couplers were procured by both Fermilab and IJCLAB for this effort. The design of the coupler is described, including design optimizations from the previous generation. This paper then describes the coupler life cycle, including design, manufacturing, and assembly, along with the lessons learned at each stage.

43 PARTICLE ACCELERATORS↗

PIP-II SSR2 Cavities Fabrication and Processing Experience

The Proton Improvement Plan-II (PIP-II [1]) linac will include 35 Single Spoke Resonators type 2 (SSR2). A preproduction SSR2 cryomodule will contain 5 jacketed cavities. Several units are already manufactured and prepared for cold testing. In this work, data collected from the fabrication, processing and preparation of the cavities will be presented and the improvements implemented after the completion of the first unit will be highlighted.

43 PARTICLE ACCELERATORS↗

Visual, Optical and Replica Inspections: Surface Preparation of 650 MHz NB Cavity for PIP-II Linac

Surface preparation of niobium superconducting RF cavities is a critical step for achieving good RF performance under the superconducting state. Surface defect, roughness, and contamination affect the accelerating gradient and quality factor of the cavities. We report surface inspection methods used to control the surface processing of 650 MHz cavities designated for the pre-production and prototype cryomodules for PIP-II linac. The cavity surface was routinely inspected visually, with an optical camera, and by microscopic scanning of surface replicas. This article covers details on the surface inspection methods and surface polishing process used to repair the surface.

43 PARTICLE ACCELERATORS↗

State Machine Operation of Complex Systems

Operation of complex systems which depend on one or more other systems with many process variables often operate in more than one state. For each state there may be a variety of parameters of interest, and for each of these, one may require different alarm limits, different archiving needs, and have different critical parameters. Relying on operators to reliably change 10s-1000s of parameters for each system for each state is unreasonable.Not changing these parameters results in alarms being ignored or disabled, critical changes missed, and/or possible data archiving problems.To reliably manage the operation of complex systems, such as cryomodules (CMs), Fermilab is implementing state machines for each CM and an over-arching state machine for the PIP-II superconducting linac (SCL). The state machine transitions and operating parameters are stored/restored to/from a configuration database. Proper implementation of the state machines will not only ensure safe and reliable operation of the CMs, but will help ensure reliable data quality. A description of PIP-II SCL, details of the state machines, and lessons learned from limited use of the state machines in recent CM testing will be discussed.

72 PHYSICS OF ELEMENTARY PARTICLES AND FIELDS↗

Magnetic design of the commutational magnet and quadrupoles for PERLE accelerator

PERLE (Powerful Energy Recovery LINAC for Experiment) is a high-power Energy Recovery LINAC (ERL) facility with 20 mA beam current and beam energy from 250 MeV to 500 MeV featuring three passes through two cryomodules. It is a hub for validation of the ERL technology development towards future energy and intensity frontier machines. Design challenges of PERLE and its beam parameters make it a test-bed to validate multi-turn high current ERL operation for the LHeC. It will be the first ERL for some pioneering experiment of the eN interaction with radioactive nuclei. In this work, design and optimization of the commutational magnet (B-com) used to spread/combine the three beams and one series of the quadrupole magnet is discussed. It gives the design parameters including: yoke geometry, pole profile, and material, and calculation of the excitation current needed to drive the magnet, the coil parameters and the number of turns. The B-com magnet is optimized for a 30° bending angle with magnetic field of 0.88 T along the magnet length and a harmonic content of 0.036%. The quadrupole magnet is designed for a gradient field of 34.15 T/m and experiences saturation above this value. Further studies to avoid saturation and achieve the maximum gradient of 44.1 T/m required by the beam dynamics is undergoing.

Abukeshek, R.↗

State Machine Operation of Complex Systems

Operation of complex systems which depend on one, or more, sub-systems with many process variables often operate in more than one state. For each state there may be a variety of parameters of interest, and for each of these, one may require different alarm limits, different archiving needs, and have different critical parameters. Relying on operators to reliably change 102-105 parameters for each system for each state is unreasonable. Not changing these parameters results in alarms being ignored or disabled, critical changes missed, and/or data archiving inefficiencies. To reliably manage the operation of complex systems, such as cryomodules (CMs), Fermilab is implementing state machines for each CM and an over-arching state machine for the PIP-II superconducting LINAC (SCL). The state machine transitions and operating parameters are stored/restored to/from a configuration database. Proper implementation of the state machines will not only ensure safe and reliable operation of the CMs, but will help ensure reliable data quality. A description of PIP-II SCL, details of the state machines, and plans for imminent use the state machines for CM testing will be discussed.

43 PARTICLE ACCELERATORS↗

PIP-II Linac Cryogenic Distribution System Design Challenges

The PIP-II linac Cryogenic Distribution System (CDS) is characterized by extremely small heat inflows and robust mechanical design. It consists of a Distribution Valve Box (DVB), Intermediate Transfer Line, Tunnel Transfer Line, comprising 25 Bayonet Cans, and ends with a Turnaround Can. Multiple helium streams, each characterized by distinct helium parameters, flow through each of these elements. The CDS geometry allows maintaining an acceptable pressure drop for each helium stream, considering the planned flows and helium parameters in different operation modes. This is particularly crucial for the return line of helium vapors, which return from cryomodules to the cold compressors and thus have very restrictive pressure drop requirements. On both sides of the DVB there are fixed supports for process pipes. One of the DVB design challenges was to route the process pipes in such a way that their shape provided sufficient compensation for thermal shrinkage. This ensures th at the forces resulting from thermal shrinkage acting on the cryogenic valves remain at a level acceptable to the manufacturer. The required thermal budget of the CDS was achieved by thermo-mechanical optimization of its components, like process pipes fixed supports in Bayonet Cans.

43 PARTICLE ACCELERATORS↗

Fermilab PIP-II CDS and CM Cryogenic Controls System

Details on Final design for Cryogenic Electrical & Controls System for Fermilab' s next-gen particle accelerator PIP-II. Electrical Controls System includes instrumentation and controls of Cryogenics Distribution System and Cryomodules. Design includes Siemens PCS7 Controls System with 26 Remote IO Rittal Cabinets and 48 Relay Racks for Temperature Readouts, Valve Positioners, Level, Heater Controls etc. Electrical Drawings and Design have been completed with focus now on fabrication of the 26 Rittal Cabinets and 48 Relay Racks. All materials have been procured. EPICS will be used as a SCADA system communicating to S7 Controllers via OPC UA.

Patel, Pratik [Fermilab]↗

Controls Status of Fermilab's PIP-II Project

The Fermilab Proton Improvement Project II (PIP-II) is building a new Super Conducting Linear Accelerator (SCL) accelerating protons to 800 MeV for injection into the rest of the FNAL beam complex. Key progress since the last status report given at ICALEPCS includes the adoption of modern DevOps practices with continuous integration and GitOps-based deployments, commissioning of EPICS-based systems at the Cryomodule Test Facility, and integration of a Virtual Accelerator framework for application development ahead of installation. In parallel, web-based applications using Dart and Flutter have matured, providing secure, unified access to both EPICS and legacy ACNET data. Data acquisition and timing systems have also evolved. This paper presents the current state of controls, emphasizing these recent developments and outlining upcoming milestones as PIP-II approaches commissioning of its cryoplant in 2026 and the Warm Front End in 2027.

Crisp, D. B. [Fermilab]↗

Machine-Protection System for the PIP-II Linear Accelerator: Architecture and Data Processing Schemes

PIP-II at Fermilab features a brand-new, 800 MeV leading-edge Linear Accelerator (Linac) that will enable the Fermilab complex to deliver more than a megawatt of beam power to the Long Base-line Neutrino Facility (LBNF), requiring a robust Machine Protection System (MPS) to prevent beam-induced damage to delicate cryomodules and vacuum components. Signals in various accelerator components, in both analog and digital format, are collected and processed to assest the operating conditions of the accelerator. In the situation a potential damage is foreseen, the beam permit signal will be drop. A critical element of this system is the fast Analog Machine Protection System, a high-bandwidth platform designed for real-time beam loss monitoring. The system utilizes a modular, FPGA-based architecture to digitize signals from beam-sensing devices, such as AC Current Transformers (ACCTs), non-invasive Ring Pickups (RPUs) and beam scrapers. To eliminate both high frequency as well as 60 Hz noise that might be picked up in the industrial environment, data processing schemes beyond regular digital filtering are planned and implemented.

Wu, Jinyuan [Fermilab] (ORCID:0000000344329521)↗

Nb$_{3}$Sn SRF Photogun High Power Test at Cryogenic Temperatures

Superconducting RF (SRF) photoguns are emerging as promising candidates to produce highly stable electrons for Ultra fast Electron Diffraction/Microscopy (EUD/UEM) applications due to the ultrahigh shot-to-shot stability compared to room temperature RF photoguns. SRF technology was prohibitively expensive for industrial use until two recent advancements: Nb 3 Sn and conduction cooling. SRF gun can provide a CW operation capability while consuming only several Watts of RF power which eliminates the need of an expensive high power RF system and saves a facility footprint. Euclid is developing a continuous wave (CW), 1.5-cell, MeV-scale SRF conduction cooled photogun operating at 1.3 GHz. Here, in this paper, we present first high power results of the gun covered with Nb 3 Sn.

43 PARTICLE ACCELERATORS↗

Contactless Position Measurement System for Remote Alignment of Highly Reflective Objects

The Contactless Position Measurement System (CPMS) permits automatic alignment of highly-reflecting components that cannot or should not be touched by human hands, such as those used in SRF cavities. CPMS also has application during maintenance of fusion reactors, when the components in the reactor are radioactive. The length of time for which humans can handle the components in order to carry out maintenance or repairs is limited. We would like to measure the relative positions of such objects so we can bring them into alignment with motorized stages, thus eliminating the need for human contact. The CPMS is a computer vision system that measures the location of highly reflective components to within a fraction of a millimeter by finding the edges of silhouette images. This is done by placing a uniform, infrared backlight behind the components, and viewing each component with two low-aberration, infrared cameras. Each of these stereoscopic cameras are located within a coordinate system we set up with reference platforms, light sources, and survey cameras distributed around the perimeter of the string assembly room, or fusion reactor. We obtain stereoscopic silhouette images of each component, and we use these to determine the position of the component within our string assembly coordinate system. The CPMS combines the silhouette images with knowledge of the dimensions of the objects to obtain the relative positions of components in its field of view. These position measurements then allow us to mechanically maneuver the components into contact. Once we know where they are, we can move the components to where they are supposed to be with motorized stages or other mechanical means, check they are in the right place, and bolt them together. In Phase I, we built a prototype infrared backlights and cameras, tested it, wrote an analysis program to fit the images. At a range of 50 cm, we are able to measure the relative positions of two stainless steel flanges with an accuracy of 150 μm rms. The next steps are to test the analysis program with motorized stages, build a full-size prototype, and implement it in an cleanroom with SRF cavity assembly. This can be done in a cost effective way given the materials with which the system is designed. As Open Source Instruments achieved more in Phase I than anticipated, despite not receiving a Phase II SBIR grant, we hope to move forward with product development and sales with a testing partner.