Decommissioning Nuclear Facilities: First lessons Learned from UP1, Marcoule, France
On September 30, 1997, UP1, Marcoule Fuel reprocessing facility, dissolved its last spent Fuel rod. Final shutdown and stage 1 decommissioning began immediately after, under the supervision of CODEM , a consortium composed of The French Atomic Energy Commission, COGEMA, France fuel Cycle Company and EDF, the French Electricity Utility. The goal of the decommissioning program was to achieve stage 2 decommissioning , as per IAEA standards, within a period of about 15 years. 10 years later, a significant amount of decontamination and decommissioning works has been conducted with success. The contractual structure under which the program was launched has been profoundly modified, and the capacity of The French Atomic Energy Commission (CEA) and AREVA NC to complete full decommissioning programs has been confirmed. In the present document, we propose to examine the main aspects involved in the management of such decommissioning programs, and highlight, with significant examples, the main lessons learnt. In conclusion: As of 2007, UP1 decommissioning program proves to be a success. The choice of early decommissioning, the partnership launched between the French Atomic Energy Commission as owner of the site and decommissioning fund, with AREVA NC as operator and main contractor of the decommissioning works has been a success. The French Atomic Energy commission organized a contractual framework ensuring optimal safety conditions and work completion, while AREVA NC gained a unique experience at balancing the various aspects involved in the conduction of complete decommissioning programs. Although such a framework may not be applicable to all situations and facilities, it provides a positive example of a partnership combining institutional regulations and industrial efficiency.