Search NASA⌕ Search

SEARCH · Search NASA

Results for “grid interconnection”

Search indexed NASA NTRS and DOE OSTI research on propulsion, heat transfer, battery materials and energy systems. Follow report and document links to the original sources.

Quote a phrase for an exact phrase match. Source license links do not imply unrestricted reuse.

At least 487 records · Page 27

Integrating Renewable Generation into Grid Operations: Four International Experiences

International experiences with power sector restructuring and the resultant impacts on bulk power grid operations and planning may provide insight into policy questions for the evolving United States power grid as resource mixes are changing in response to fuel prices, an aging generation fleet and to meet climate goals. Australia, Germany, Japan and the UK were selected to represent a range in the level and attributes of electricity industry liberalization in order to draw comparisons across a variety of regions in the United States such as California, ERCOT, the Southwest Power Pool and the Southeast Reliability Region. The study draws conclusions through a literature review of the four case study countries with regards to the changing resource mix and the electricity industry sector structure and their impact on grid operations and planning. This paper derives lessons learned and synthesizes implications for the United States based on answers to the above questions and the challenges faced by the four selected countries. Each country was examined to determine the challenges to their bulk power sector based on their changing resource mix, market structure, policies driving the changing resource mix, and policies driving restructuring. Each countries’ approach to solving those changes was examined, as well as how each country’s market structure either exacerbated or mitigated the approaches to solving the challenges to their bulk power grid operations and planning. All countries’ policies encourage renewable energy generation. One significant finding included the low- to zero-marginal cost of intermittent renewables and its potential negative impact on long-term resource adequacy. No dominant solution has emerged although a capacity market was introduced in the UK and is being contemplated in Japan. Germany has proposed the Energy Market 2.0 to encourage flexible generation investment. The grid operator in Australia proposed several approaches to maintaining synchronous generation. Interconnections to other regions provides added opportunities for balancing that would not be available otherwise, and at this point, has allowed for integration of renewables.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Data Centers and Digital Assurance Workshop 3 – Mitigations for Digital Assurance Risks

The third session of the TADA (Technical Assistance for Digital Assurance) Data Centers Cohort, held on November 18, 2025, focused on developing mitigation strategies for digital assurance risks identified in previous workshops. Hosted by Idaho National Laboratory (INL) and ScottMadden, the session emphasized the application of Cyber-Informed Engineering (CIE) to data center infrastructure, particularly at the utility–data center interface. Participants revisited and ranked key digital assurance risks, including architecture and interface weaknesses, governance gaps, and AI-enabled threats. The workshop introduced the 12 principles of CIE, advocating for consequence-focused design, engineered controls, and secure information architecture to proactively reduce cyber-physical vulnerabilities. These principles were applied to critical data center systems such as power distribution, UPS, cooling, SCADA/BMS, and grid-forming batteries. The session also addressed governance challenges at the interconnection boundary, highlighting the need for clear roles in telemetry sharing, firmware management, and trip settings. Special attention was given to emerging risks from behind-the-meter (BTM) generation, including reverse-power flow and the integration of small modular reactors (SMRs), which shift data centers from large loads to complex generation nodes. Participants explored how interconnection agreements can serve as enforceable instruments for digital assurance, and reviewed gaps in current standards such as NERC CIP, IEC 62443, and IEEE 1547. The workshop concluded with pathways to standardization, including model agreement language, state-level programs, and expanded NERC guidance. INL also presented tools and frameworks for secure procurement and supplier risk management, reinforcing the need for integrated engineering and policy solutions to secure the evolving data center–grid ecosystem. Session 3 of 3.

24 - POWER TRANSMISSION AND DISTRIBUTION↗

Enabling Grid-Forming Control with Fault Ride-Through in Unbalanced Distribution Networks

Distribution networks are often unbalanced, causing oscillatory responses in inverter control designed for balanced conditions. Here, to address this problem, this paper proposes a novel time-domain transformation appropriate for inverter control and enables the decomposition of three-phase unbalanced signals into constant positive and negative components. Relations useful for calculating unbalanced active and reactive power are derived from first principle, providing insight into vector products of unbalanced three-phase signals. Furthermore, a grid-forming control effective under unbalanced conditions is developed, which delivers superior performance while meeting UNIFI1 specifications for grid-forming control under unbalanced conditions. specifications applicable to category 4 inverter-based resource, like setting and regulating frequency/voltage, providing voltage support, sharing active power, injecting negative sequence current, and riding through faults. A current limiter is proposed for safe fault ride-through and integrates with the grid-forming control featuring frequency/voltage droop controllers and current and voltage control loops. The transformation of interconnected inverters is formulated and stability of the proposed control analyzed to support robust parameter selections. The effectiveness of the proposed transformation and grid-forming control is demonstrated through analytical results and real-time simulation of a IEEE 123 distribution network on the Real-Time Digital Simulator. Comparison with existing methods shows that the proposed strategy satisfies the UNIFI specifications with a much better performance.

24 - POWER TRANSMISSION AND DISTRIBUTION↗

The Eastern Renewable Generation Integration Study: Insights on System Stress: Preprint

The Eastern Renewable Generation Integration Study (ERGIS) explores the operational impacts of the wide spread adoption of wind and solar photovoltaics (PV) resources in North America's Eastern and Quebec Interconnections. We explore the impact of large scale adoption of wind and solar generation on the unit commitment and economic dispatch of the largest coordinated power system in the world by simulating hourly and five-minute operations. Using NREL's high-performance computing capabilities and new methodologies to model operations, we found that the modeled system, as simulated with evolutionary change in 2026, could balance the variability and uncertainty of wind and solar PV at a five-minute level under a variety of conditions. Our simulations achieve instantaneous penetrations that exceed 50% of load while meeting an annual penetration of 30% on an energy basis. The system meets balanced load and supply in all intervals, with modest curtailment, using technologies and practices that are widely available today. However, a variety of the conditions present in these simulations deviate substantially from historical practice. In this work, we analyze potentially stressful system conditions that occur in the simulations and identify opportunities for innovation, regulatory reform, and changes in operating practices that require further analysis to enable the transition to a system with more wind and solar PV.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Model Guidance to Address Barriers to Combined Heat and Power and Waste Heat to Power

Congress directed that the US Department of Energy (DOE) initiate a review of interconnection rules to identify barriers to interconnection and ways to better integrate combined heat and power (CHP) and waste heat to power (WHP) in the electric grid. Oak Ridge National Laboratory (ORNL) supports DOE by providing technical assistance for CHP. DOE tasked ORNL with the interconnection review and development of model guidance to enable developers and CHP owners to interconnect more CHP. This report summarizes the work that DOE initiated in response to the congressional request.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Defining a Platform Approach and Market Participation: Data Driven Business Models for Solid State Transformer-Based Synthetic Inertia and Voltage Stability Controls (CRADA Final Report, Project 1, Mod 1)

The primary objective of this project is to determine the incremental value created with the medium voltage solid-state transformer (MV SST) technology to different stakeholders in view of the updated DER grid regulations. This includes studying the benefits of the MV SST technology in a range of use cases for EV and DER penetration including (1) “corridor charging” for EVs and (2) solar plus storage (FERC 2222). The potential customers of this technology include utilities for EV charging, DER installers who must meet utility interconnection requirements, balancing authorities, and DER aggregators. The traditional transformers on the grid could be a limiting factor for the EV-grid integration as the distribution transformers were not designed to handle the dynamic and fluctuating EV charging loads. Thus, the issues such as voltage fluctuations, increased losses and reduced efficiency [1] can negatively impact the grid operation. To address these challenges, transformers with flexibility and adaptability become imperative to meet the evolving energy demands. In this regard, the concept of Medium Voltage Solid-State Transformers.

14 SOLAR ENERGY↗

Evaluation of Multi-Inverter Anti-Islanding with Grid Support and Ride-Through and Investigation of Island Detection Alternatives

As utility interconnected photovoltaic systems (PV) become integrated into the electrical power system (EPS) at an increasing rate, utilities and regulators have become concerned about the potential for increased voltage and frequency deviations as well as EPS reliability and resiliency. These concerns have initiated the need to amend the utility interconnection standard to allow advanced inverter control functionalities that provide: (1) reactive power control for voltage support, (2) real (active) power control for frequency support and (3) voltage and frequency ride- through for bulk system support. The new real and reactive power modulation are intended to reduce EPS voltage and frequency deviations by mimicking the droop and excitation controls of conventional generation. The new ride-through capabilities are needed to prevent a large quantity of generation from autonomously de-energizing or disconnecting in response to a voltage or frequency deviation. These changes, however, may have the potential to interfere with autonomous anti-islanding, especially when multiple inverters from different vendors are co-located on one bus. This report presents results from an investigation of multi-inverter autonomous anti- islanding with advanced functions, and the development of a means to mitigate adverse interaction between the two.

14 SOLAR ENERGY↗

Commercialization of Distribution System Load Modeling Tool for Improved DER Interconnection Studies

Residential and commercial buildings have huge potential to contribute value to improve grid resilience by participating grid services. To reveal the significant value, it is critical to estimate the grid service capability from these buildings. Unlike the large-scale distributed energy resources such as wind and solar farms, those buildings need to participate grid services in aggregation, not by individual. Therefore, it is important to appropriately group buildings for aggregation. The load profiles in the same group will have similar characteristics at the same time step, so grid operators can send the grid service signal to the customer group with a higher chance to respond at that time step. In this paper, we develop a load profile clustering method to classify the building-level load profiles for grid service capability estimation. In our two-step clustering approach, we first calculate the total load consumption for each building, clustering the load profiles based on energy consumption level. Then, we further cluster the load profiles in each energy cluster based on the load shape. The parameter selection for each clustering step is discussed. The proposed method is applied on actual building-level load profiles, and the results have proved the effectiveness of this method.

14 SOLAR ENERGY↗

Solid State Power Substations (SSPS): A Multi-Hierarchical Architecture from Substation to Grid Edge

With the growing deployment of distributed generation, or power electronic interfaced renewable energy and storage technologies, the nature and behavior of the grid is changing. Synchronous machine-driven asset contributions to the generation mix are shrinking, leading to concerns regarding grid stability. Furthermore, the scale of smaller distributed PE resources needed for managing the electrical network could dwarf the existing system leading to more complex optimization problems and communication interconnections. This paper introduces the concept of a hierarchal system of controllers that spans the grid edge or the customer end to distribution scale substations or solid-state power substation (SSPS). This concept focuses on minimizing the number of interfaces and optimization considerations in the grid by clustering resources into nodes and hubs. The work validates the concept in a controller hardware-in-the-loop (cHIL) platform.

Chinthavali, Madhu Sudhan↗

Queued Up: 2024 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2023 [Slides]

Electric transmission system operators (ISOs, RTOs, or utilities) require projects seeking to connect to the grid to undergo a series of impact studies before they can be built. This process establishes what new transmission equipment or upgrades may be needed before a project can connect to the system and assigns the costs of that equipment. The lists of projects in this process are known as “interconnection queues”. The amount of new electric capacity in these queues is growing dramatically, with nearly 2,600 gigawatts (GW) of total generation and storage capacity now seeking connection to the grid (over 95% of which is for zero-carbon resources like solar, wind, and battery storage). However, most projects that apply for interconnection are ultimately withdrawn, and those that are built are taking longer on average to complete the required studies and become operational. Data from these queues nonetheless provide a general indicator for mid-term trends in developer interest.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Renewable Electricity Futures. Operational Analysis of the Western Interconnection at Very High Renewable Penetrations

The Renewable Electricity Futures Study (RE Futures)--an analysis of the costs and grid impacts of integrating large amounts of renewable electricity generation into the U.S. power system--examined renewable energy resources, technical issues regarding the integration of these resources into the grid, and the costs associated with high renewable penetration scenarios. These scenarios included up to 90% of annual generation from renewable sources, although most of the analysis was focused on 80% penetration scenarios. Hourly production cost modeling was performed to understand the operational impacts of high penetrations. One of the conclusions of RE Futures was that further work was necessary to understand whether the operation of the system was possible at sub-hourly time scales and during transient events. This study aimed to address part of this by modeling the operation of the power system at sub-hourly time scales using newer methodologies and updated data sets for transmission and generation infrastructure. The goal of this work was to perform a detailed, sub-hourly analysis of very high penetration scenarios for a single interconnection (the Western Interconnection). It focused on operational impacts, and it helps verify that the operational results from the capacity expansion models are useful. The primary conclusion of this study is that sub-hourly operation of the grid is possible with renewable generation levels between 80% and 90%.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

Frequency Instability Problems in North American Interconnections

Alternating current power transmission and distribution systems in the United States operate at a nominal (target) frequency of 60 Hz. Large deviations from this frequency can cause network instability, and even small deviations can adversely affect sensitive end-use devices. Frequency deviations commonly result from a mismatch between energy supply and demand on a power network. If supply is insufficient to meet demand, the system frequency will decrease; if supply exceeds demand, frequency will increase. Over 100 balancing authorities within four electrical interconnections in North America manage power flows so that frequency will remain stable.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Probabilistic Deliverability Assessment of Distributed Energy Resources via Scenario-Based AC Optimal Power Flow

As electric grids decarbonize and distributed energy resources (DERs) become increasingly prevalent, interconnection assessments must evolve to reflect operational variability and control flexibility. This paper highlights key modeling limitations observed in practice and reviews approaches for modeling uncertainty. It then introduces a Probabilistic Deliverability Assessment (PDA) framework designed to complement and extend existing procedures. The framework integrates scenario-based AC optimal power flow (AC OPF), corrective dispatch, and optional multi-temporal constraints. Together, these form a structured methodology for quantifying DER utilization, deliverability, and reliability under uncertainty in load, generation, and topology. Outputs include interpretable metrics with confidence intervals that inform siting decisions and evaluate compliance with reliability thresholds across sampled operating conditions. A case study on Puerto Rico’s publicly available bulk power system model demonstrates the framework’s application using minimal input data, consistent with current interconnection practice. Across staged fossil generation retirements, the PDA identifies high-value DER sites and regions requiring additional reactive power support. Results are presented through mean dispatch signals, reliability metrics, and geospatial visualizations, demonstrating how the framework provides transparent, data-driven siting recommendations. The framework’s modular design supports incremental adoption within existing workflows, encouraging broader use of AC OPF in interconnection and planning contexts.

14 SOLAR ENERGY↗

Slow Wake Recovery and Low Turbulence Behind Wind Farms Parameterized in Mesoscale Simulations

Numerical weather prediction (NWP) and climate models equipped with wind-farm parameterizations (WFPs) can simulate cluster wake effects affecting downstream wind farms in both onshore and offshore environments. This study evaluates wake recovery behind a wind farm represented by the NWP-WFP approach in the Weather Research and Forecasting (WRF) model using either the Fitch et al. (2012) or Ma et al. (2022a, b) WFPs. Results are benchmarked against large-eddy simulations (LES) of an idealized offshore wind farm with aligned and staggered layouts under neutral atmospheric stability. Near-farm wake recovery is underestimated in NWP-WFP simulations due to its representation on a coarse mesoscale grid. This limitation leads to slow wake recovery through two interconnected mechanisms: (i) spatial gradients in the wind velocity field are weaker compared to LES and (ii) turbulence kinetic energy (TKE) remains low not because of excessive dissipation but due to insufficient shear production caused by these weakened gradients. For the scenario considered here, a wind-speed bias develops in the near-farm wake and persists into the far wake. Differences between the NWP-WFP simulations and LES emerge within a short distance downstream of the farm exit, where the mesoscale simulations recover too slowly. This reduced recovery contributes approximately 0.15-0.50 m s-1 to the near-farm wind-speed bias. The bias established in this region is not subsequently compensated for downstream but instead propagates into the far wake, where wind-speed differences of approximately 0.4-0.6 m s-1 remain up to 50 km downstream. Higher-resolution mesoscale simulations partially reduce this bias. Increasing turbine-added TKE or including subgrid wake effects provides additional improvement, but neither fully addresses the underlying cause. The slow wake recovery is not caused by limitations of the WFPs themselves, as it also occurs outside their region of influence, and adding subgrid wake effects does not significantly impact recovery. Rather, the slow wake recovery is a consequence of mesoscale flow representation. This behavior is not limited to regions downstream of the wind farm but is less visible within the farm, where wake recovery occurs simultaneously with turbine-induced momentum extraction. These results highlight the need for improved representations of wake recovery both within and downstream of wind farms. While enhanced subgrid modeling, shear-driven TKE production, and refined WFP formulations may improve intra-farm dynamics, accurately capturing near-farm wake recovery downstream remains challenging, as WFPs do not act in this region.

17 WIND ENERGY↗

Accelerated Thermal Cycling and Failure Mechanisms for BGA and CSP Assemblies

This paper reviews the accelerated thermal cycling test methods that are currently used by industry to characterize the interconnect reliability of commercial-off-the-shelf (COTS) ball grid array (BGA) and chip scale package (CSP) assemblies. Acceleration induced failure mechanisms varied from conventional surface mount (SM) failures for CSPs. Examples of unrealistic life projections for other CSPs are also presented. The cumulative cycles to failure for ceramic BGA assemblies performed under different conditions, including plots of their two Weibull parameters, are presented. The results are for cycles in the range of -30 C to 100 C, -55 C to 100 C, and -55 C to 125 C. Failure mechanisms as well as cycles to failure for thermal shock and thermal cycling conditions in the range of -55 C to 125 C were compared. Projection to other temperature cycling ranges using a modified Coffin-Manson relationship is also presented.

Ghaffarian, Reza↗

Accelerated Thermal Cycling and Failure Mechanisms

This paper reviews the accelerated thermal cycling test methods that are currently used by industry to characterize the interconnect reliability of commercial-off-the-shelf (COTS) ball grid array (BGA) and chip scale package (CSP) assemblies.

BGA CSP CBGA thermal cycle solder joint reliabilit↗

Advanced Power-Hardware-in-the-Loop Evaluation of Inverter-Based Resources (IBRs)

Power-hardware-in-the-loop evaluation of IBRs has become more and more important as it provides reliable testing results to investigate the real responses of inverters with interconnected systems. A successful laboratory PHIL testing gives confidence of the hardware system to be deployed and de-risk technology integration prior to field deployment. So far, there are two important applications for PHIL evaluation: (1) test stability and functionality of large utility inverters into the system when it interconnects to the distribution systems/microgrids; and (2) test the collective grid service that inverters can provide to the grid. For the first application, the PHIL evaluation has high requirements for the stability and accuracy of the PHIL interface as the close-loop in digital real time simulator (DRTS) should replicate the actual current and voltage dynamics in the inverter. This is challenging because of the delays, sensing errors, nonlinearities of inverters, and hardware bandwidth limitations of the elements in the HIL loop. For the second application, multiple inverters will be tested resulting in multiple PCCs, which naturally causes competing dynamics and oscillations among hardware inverters if traditional PHIL interface is used. Therefore, new PHIL interface should be developed to compromise between stability and accuracy and represent the dispatched grid services for the hardware inverters. In this presentation, we will share our latest work in developing PHIL interface in these two applications to address the two key challenges.

DERMS↗

Providencia Island White Papers: Overview of Technical Requirements for Interconnection

This issue brief provides an overview of key technical requirements for inverter-based resources - including distributed energy resources (DERs) - to support the reliable and safe operation of the Providencia Island electrical grid, and other island or isolated area mini-grid applications. With the planned increase in inverter-based resources and the introduction of energy storage, adopting Institute of Electrical and Electronics Engineers (IEEE) Std 1547-2018, including the more advanced performance capabilities for voltage and frequency ride-through, will simplify interconnection as well as help to maintain a safe, reliable grid on Providencia Island.

24 POWER TRANSMISSION AND DISTRIBUTION↗