AVESTAR Center for Operational Excellence of Clean Energy Plants

To address challenges in attaining operational excellence for clean energy plants, the U.S.Department of Energy’s National Energy Technology Laboratory has launched a world-class facility for Advanced Virtual Energy Simulation Training and Research (AVESTAR™). The AVESTAR Center brings together state-of-the-art, real time,high-fidelity dynamic simulators with operator training systems and 3D virtual immersive training systems into an integrated energy plant and control room environment. This presentation will highlight the AVESTAR Center simulators, facilities, and comprehensive training, education, and research programs focused on the operation and control of high-efficiency, near-zero-emission energy plants.

97 MATHEMATICS AND COMPUTING↗

AVESTAR Center for operational excellence of electricity generation plants

To address challenges in attaining operational excellence for clean energy plants, the U.S.Department of Energy’s National Energy Technology Laboratory has launched a world-class facility for Advanced Virtual Energy Simulation Training and Research (AVESTAR™). The AVESTAR Center brings together state-of-the-art, real time,high-fidelity dynamic simulators with operator training systems and 3D virtual immersive training systems into an integrated energy plant and control room environment.

97 MATHEMATICS AND COMPUTING↗

Radio frequency mixing modules for superconducting qubit room temperature control systems

As the number of qubits in nascent quantum processing units increases, the connectorized RF (radio frequency) analog circuits used in first generation experiments become exceedingly complex. The physical size, cost, and electrical failure rate all become limiting factors in the extensibility of control systems. We have developed a series of compact RF mixing boards to address this challenge by integrating I/Q quadrature mixing, intermediate frequency/LO (local oscillator)/RF power level adjustments, and direct current bias fine tuning on a 40 × 80 mm 2 four-layer printed circuit board with electromagnetic interference shielding. The RF mixing module is designed to work with RF and LO frequencies between 2.5 and 8.5 GHz. The typical image rejection and adjacent channel isolation are measured to be ~27 dBc and ~50 dB. By scanning the drive phase in a loopback test, the module short-term amplitude and phase linearity are typically measured to be 5 ×10 -4 (V pp /V mean ) and 1 ×10 -3 radian (pk-pk). The operation of the RF mixing board was validated by integrating it into the room temperature control system of a superconducting quantum processor and executing randomized benchmarking characterization of single and two qubit gates. We measured a single-qubit process infidelity of 9.3(3) × 10 -4 and a two-qubit process infidelity of 2.7(1) × 10 -2 .

47 OTHER INSTRUMENTATION↗

Digital Twin + AI: Control Room of the Future

A digital twin enhances power grid control room operations by providing real-time monitoring, predictive insights, simulation capabilities, remote control, training opportunities, data integration, and decision support. This technology empowers control room operators to effectively manage the grid, optimize performance, and ensure reliable and efficient energy distribution.

control room of the future↗

Incorporating Uncertainty of Wind Power Generation Forecast into Power System Operation, Dispatch, and Unit Commitment Procedures

An approach to evaluate the uncertainties of the balancing capacity, ramping capability, and ramp duration requirements is proposed. The approach includes three steps: forecast data acquisition, statistical analysis of retrospective information, and prediction of grid balancing requirements for a specified time horizon and a given confidence level. An assessment of the capacity and ramping requirements is performed using a specially developed probabilistic algorithm based on histogram analysis, incorporating sources of uncertainty - both continuous (wind and load forecast errors) and discrete (forced generator outages and start-up failures). A new method called the 'flying-brick' technique is developed to evaluate the look-ahead required generation performance envelope for the worst case scenario within a user-specified confidence level. A self-validation process is used to validate the accuracy of the confidence intervals. To demonstrate the validity of the developed uncertainty assessment methods and its impact on grid operation, a framework for integrating the proposed methods with an EMS system is developed. Demonstration through EMS integration illustrates the applicability of the proposed methodology and the developed tool for actual grid operation and paves the road for integration with EMS systems in control rooms.

17 WIND ENERGY↗

Linear Collider Test Facility: Twiss Parameter Analysis at the IP/Post-IP Location of the ATF2 Beam Line

At the first stage of the ATF2 beam tuning, vertical beam size is usually bigger than 3 {micro}m at the IP. Beam waist measurements using wire scanners and a laser wire are usually performed to check the initial matching of the beam through to the IP. These measurements are described in this paper for the optics currently used ({beta}{sub x} = 4cm and {beta}{sub y} = 1mm). Software implemented in the control room to automate these measurements with integrated analysis is also described. Measurements showed that {beta} functions and emittances were within errors of measurements when no rematching and coupling corrections were done. However, it was observed that the waist in the horizontal (X) and vertical (Y) plane was abnormally shifted and simulations were performed to try to understand these shifts. They also showed that multiknobs are needed in the current optics to correct simultaneously {alpha}{sub x}, {alpha}{sub y} and the horizontal dispersion (D{sub x}). Such multiknobs were found and their linearity and orthogonality were successfully checked using MAD optics code. The software for these multiknobs was implemented in the control room and waist scan measurements using the {alpha}{sub y} knob were successfully performed.

43 PARTICLE ACCELERATORS↗

Langston University - High Energy Physics (LU-HEP)

This final report is presented by Langston University (LU) for the project entitled "Langston University High Energy Physics" (LUHEP) under the direction of principal investigator (PI) and project director Professor Joel Snow. The project encompassed high energy physics research performed at hadron colliders. The PI is a collaborator on the DZero experiment at Fermi National Accelerator Laboratory in Batavia, IL, USA and the ATLAS experiment at CERN in Geneva, Switzerland and was during the entire project period from April 1, 1999 until May 14, 2012. Both experiments seek to understand the fundamental constituents of the physical universe and the forces that govern their interactions. In 1999 as member of the Online Systems group for Run 2 the PI developed a cross-platform Python-based, Graphical User Interface (GUI) application for monitoring and control of EPICS based devices for control room use. This served as a model for other developers to enhance and build on for further monitoring and control tasks written in Python. Subsequently the PI created and developed a cross-platform C++ GUI utilizing a networked client-server paradigm and based on ROOT, the object oriented analysis framework from CERN. The GUI served as a user interface to the Examine tasks running in the D\O\ control room which monitored the status and integrity of data taking for Run 2. The PI developed the histogram server/control interface to the GUI client for the EXAMINE processes. The histogram server was built from the ROOT framework and was integrated into the D\O\ framework used for online monitoring programs and offline analysis. The PI developed the first implementation of displaying histograms dynamically generated by ROOT in a Web Browser. The PI's work resulted in several talks and papers at international conferences and workshops. The PI established computing software infrastructure at LU and U. Oklahoma (OU) to do analysis of DZero production data and produce simulation data for the experiment. Eventually this included the FNAL SAM data grid system, the SAMGrid (SG) infrastructure, and the Open Science Grid software stacks for computing and storage elements. At the end of 2003 Snow took on the role of global Monte Carlo production coordinator for the DØ experiment. A role which continues til this day. In January of 2004 Snow started working with the SAMGrid development team to help debug, deploy, and integrate SAMGrid with DØ Monte Carlo production. Snow installed and configured SG execution and client sites at LUHEP and OUHEP, and a SG scheduler site at LUHEP. The PI developed a python based GUI (DAJ) that acts as a front end for job submission to SAMGrid. The GUI interfaces to the DZero Mone Carlo (MC) request system that uses SAM to manage MC requests by the physics analysis groups. DAJ significantly simplified SG job submission and was deployed in DZero in an effort to increase the user base of SG. The following year was the advent of SAMGrid job submission to the Open Science Grid (OSG) and LHC Computing Grid (LCG) through a forwarding mechanism. The PI oversaw the integration of these grids into the existing production infrastructure. The PI developed an automatic MC (Automc) request processing system capable of operating without user intervention (other than getting grid credentials), and able to submit to any number of sites on various grids. The system manages production at all but 2 sites. The system was deployed at Fermilab and remains operating there today. The PI's work in distributed computing resulted in several talks at international conferences. UTA, OU, and LU were chosen as the collaborating institutions that form the Southwest Tier 2 Center (SWT2) for ATLAS. During the project period the PI contributed to the online and offline software infrastructure through his work with the Run 2 online group, and played a major role in Monte Carlo production for DZero. During the part of the project period in which the PI served as MC production coordinator MC production increased very significantly. In the first year of the PI's tenure as production coordinator production was 159M events and 6.7~TB of data. During the last year of the project period production was 2,342~M events and 262~TB of data. That is a factor of 15 increase in events and 39 in data volume. The increase occurred with improvements in computer hardware and networks, through the use of grid technology on diverse resources, and through increased automation and efficiency of the production process. LU HEP developed and deployed the automatic MC request processing system in use at FNAL. The complementary strategies of automation and grid production served DZero well. Fermilab has recognized LU HEP's contribution to DZero by allowing the PI to devote full time to research activities by appointing him a guest scientist for the last six years of the project period.

72 PHYSICS OF ELEMENTARY PARTICLES AND FIELDS↗

Ensuring operator reliability in digital control rooms - 102

The U.S. fleet of nuclear power plants is aging, and efforts are being made to modernize instrumentation and control systems including integration of digital human-machine interfaces (HMIs) into the control room. Automation and control technologies have advanced since original systems were installed in the plants. This presents unique opportunities and challenges in ensuring the replacements are a benefit to the operators and the overall safe and reliable operation of the plant. We discuss trends we have observed from assisting utilities in their modernization efforts. Automation and evolving control rooms come with their own host of problems that existing human factors and engineering methods fail to capture. Traditional approaches are analytical approaches to ensuring reliability. Here we discuss some of the shortfalls of these traditional approaches as plants become increasingly more complex. We suggest that ensuring reliability for modernized and next generation control room will require expanding the scope of what was traditionally considered human factors as well as exploring novel approaches and methodologies for dealing with complexity and rapidly advancing technology. (authors)

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

A HUMAN FACTORS META MODEL FOR U.S. NUCLEAR POWER PLANT CONTROL ROOM MODERNIZATION

Over the last several years, the United States (U.S.) Department of Energy (DOE) has sponsored human factors research and development (R&D) and human factors engineering (HFE) activities through its Light Water Reactor Sustainability (LWRS) program to modernize the main control rooms (MCR) of commercial nuclear power plants (NPP). Idaho National Laboratory (INL), in partnership with numerous commercial nuclear utilities, has conducted some of this R&D to enable the life extension of NPPs (i.e., provide the technical basis for the long-term reliability, productivity, safety, and security of U.S. NPPs). From these activities performed to date, a human factors meta model for U.S. NPP control room modernization can now be formulated. This paper discusses this emergent HFE meta model for NPP control room modernization, with the goal of providing an integrated high level roadmap and guidance on how to perform human factors R&D and HFE for those in the U.S. nuclear industry that are engaging in the process of upgrading their MCRs.

99 GENERAL AND MISCELLANEOUS↗

A human factors meta model for U.S. nuclear power plant control room modernization - 350

Over the last several years, the United States (U.S.) Department of Energy (DOE) has sponsored human factors research and development (R and D) and human factors engineering (HFE) activities through its Light Water Reactor Sustainability (LWRS) program to modernize the main control rooms (MCR) of commercial nuclear power plants (NPP). Idaho National Laboratory (INL), in partnership with numerous commercial nuclear utilities, has conducted some of this R and D to enable the life extension of NPPs (i.e., provide the technical basis for the long-term reliability, productivity, safety, and security of U.S. NPPs). From these activities performed to date, a human factors meta model for U.S. NPP control room modernization can now be formulated. This paper discusses this emergent HFE meta model for NPP control room modernization, with the goal of providing an integrated high-level road map and guidance on how to perform human factors R and D and HFE for those in the U.S. nuclear industry engaged in the process of upgrading their MCRs. (authors)

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

The evolution of the Human Systems and Simulation Laboratory in nuclear power research

The events at Three Mile Island in the United States brought about fundamental changes in the ways that simulation would be used in nuclear operations. The need for research simulators was identified to scientifically study human-centered risk and make recommendations for process control system designs. This paper documents the human factors research conducted at the Human Systems and Simulation Laboratory (HSSL) since its inception in 2010 at Idaho National Laboratory. The facility’s primary purposes are to provide support to utilities for system upgrades and to validate modernized control room concepts. In the last decade, however, as nuclear industry needs have evolved, so too have the purposes of the HSSL. Thus, beyond control room modernization, human factors researchers have evaluated the security of nuclear infrastructure from cyber adversaries and evaluated human-in-the-loop simulations for joint operations with an integrated hydrogen generation plant. Lastly, our review presents research using human reliability analysis techniques with data collected from HSSL-based studies and concludes with potential future directions for the HSSL, including severe accident management and advanced control room technologies.

21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS↗

Human factors design, verification, and validation for two types of control room upgrades at a nuclear power plant

This paper describes the NUREG-0711 based human factors engineering (HFE) phases and associated elements required to support design, verification and validation (V&V), and implementation of a new plant process computer (PPC) and turbine control system (TCS) at a representative nuclear power plant. This paper reviews ways to take a human-system interface (HSI) specification and use it when migrating legacy PPC displays or designing displays with new functionality. These displays undergo iterative usability testing during the design phase and then undergo an integrated system validation (ISV) in a full scope control room training simulator. Following the successful demonstration of operator performance with the systems during the ISV, the new system is implemented at the plant, first in the training simulator and then in the main control room.

21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS↗

CORBA-Based Distributed Software Framework for the NIF Integrated Computer Control System

The National Ignition Facility (NIF), currently under construction at the Lawrence Livermore National Laboratory, is a stadium-sized facility containing a 192-beam, 1.8 Megajoule, 500-Terawatt, ultra-violet laser system together with a 10-meter diameter target chamber with room for nearly 100 experimental diagnostics. The NIF is operated by the Integrated Computer Control System (ICCS) which is a scalable, framework-based control system distributed over 800 computers throughout the NIF. The framework provides templates and services at multiple levels of abstraction for the construction of software applications that communicate via CORBA (Common Object Request Broker Architecture). Object-oriented software design patterns are implemented as templates and extended by application software. Developers extend the framework base classes to model the numerous physical control points and implement specializations of common application behaviors. An estimated 140 thousand software objects, each individually addressable through CORBA, will be active at full scale. Many of these objects have persistent configuration information stored in a database. The configuration data is used to initialize the objects at system start-up. Centralized server programs that implement events, alerts, reservations, data archival, name service, data access, and process management provide common system wide services. At the highest level, a model-driven, distributed shot automation system provides a flexible and scalable framework for automatic sequencing of work-flow for control and monitoring of NIF shots. The shot model, in conjunction with data defining the parameters and goals of an experiment, describes the steps to be performed by each subsystem in order to prepare for and fire a NIF shot. Status and usage of this distributed framework are described.

42 ENGINEERING↗

Regulatory Aspects of the Human Factors Engineering Process in Control Room Modernization

This report describes the basic aspects of control room modernization projects in the U.S. nuclear industry and the need for supplementary guidance on the integration of human factors considerations into the licensing and regulatory aspects of digital upgrades. The report pays specific attention to the integration of principles described in NUREG-0711 (Human Factors Engineering Program Review Model) and how supplementary guidance can help to raise general awareness in the industry regarding the complexities of control room modernization projects created by many interdependent regulations, standards and guidelines. The report also describes how human factors engineering principles and methods provided by various resources and international standards can help in navigating through the process of licensing digital upgrades. In particular, the integration of human factors engineering guidance and requirements into the process of licensing digital upgrades can help reduce uncertainty related to development of technical bases for digital upgrades that will avoid the introduction of new failure modes.

99 GENERAL AND MISCELLANEOUS↗

Human Factors Engineering Aspects of Modifications in Control Room Modernization

This report describes the basic aspects of control room modernization projects in the U.S. nuclear industry and the need for supplementary guidance on the integration of human factors considerations into the licensing and regulatory aspects of digital upgrades. The report pays specific attention to the integration of principles described in NUREG-0711 (Human Factors Engineering Program Review Model) and how supplementary guidance can help to raise general awareness in the industry regarding the complexities of control room modernization projects created by many interdependent regulations, standards and guidelines. The report also describes how human factors engineering principles and methods provided by various resources and international standards can help in navigating through the process of licensing digital upgrades. In particular, the integration of human factors engineering guidance and requirements into the process of licensing digital upgrades can help reduce uncertainty related to development of technical bases for digital upgrades that will avoid the introduction of new failure modes.

97 MATHEMATICS AND COMPUTING↗

Strategy for Migration of Traditional to Hybrid Control Boards in a Nuclear Power Plant

This strategy document describes the NUREG-0711 based human factors engineering (HFE) phases and associated elements required to support design, verification and validation (V&V), and implementation of new digital control room elements in a legacy analog main control room (MCR). Information from previous planning and analysis work serves as the foundation for creating a human-machine interface (HMI) specification for distributed control systems (DCSs) to be implemented as part of nuclear power plant (NPP) modernization. This document reviews ways to take the HMSI specification and use it when migrating legacy displays or designing displays with new functionality. These displays undergo iterative usability testing during the design phase and then an integrated system validation (ISV) in the full-scope control room training simulator. Following successful demonstration of operator performance using the systems during the ISV, the new DCS is implemented at the plant, first in the training simulator and then in the MCR. This document concludes with a sample project plan, including a 15-month timeline from DCS design through implementation. Included is a discussion of how the U.S. Department of Energy’s Human System Simulation Laboratory (HSSL) can be used to support design and V&V activities. This report completes a Level 4 (M4) milestone under the U.S. Department of Energy’s (DOE’s) Light Water Reactor Sustainability (LWRS) Program.