Search NASA⌕ Search

SEARCH · Search NASA

Results for “Project Management”

Search indexed NASA NTRS and DOE OSTI research on propulsion, heat transfer, battery materials and energy systems. Follow report and document links to the original sources.

Quote a phrase for an exact phrase match. Source license links do not imply unrestricted reuse.

At least 1,045 records · Page 58

Humboldt Bay Power Plant Decommissioning Progress Update - 16358

Decommissioning of the Pacific Gas and Electric (PG and E) Company Humboldt Bay Power Plant (HBPP) Unit 3 nuclear facility achieved several significant milestones in the summer and fall of 2015 when the RPV Segmentation Project completed, the Caisson Removal project began and the Unit 3 Refueling building (RFB) and Main Plant Ventilation system were released for Open Air Demolition (OAD). At the end of 2014 the Civil Works prime contractor Chicago Bridge and Iron (CB and I) was also awarded the contract to complete the RPV Segmentation. This work scope continued to use the First of a Kind (FOAK) segmentation equipment that was designed and fabricated for the HBPP Reactor Project. The preparation for RFB OAD was part of the original Civil Works contract scope. It was important that this work and the segmentation of the reactor shell be finished to allow a portion of the Refueling building to be demolished to continue the installation of the perimeter water cutoff wall and the caisson Support of Excavation (SOE) shoring system. The CB and I Civil Works contract endorsed the October 2012 HBPP Caisson Removal Feasibility Study approach to install a perimeter cutoff wall intended to stop movement of groundwater by installation of cement-bentonite (CB) backfill in a slurry wall trench excavated to a depth of 53 meters and tied into the Unit F clay layer. The CB and I on-site project manager and principal engineer from their home office re-evaluated the design approach outlined in their proposal and awarded contract. As CB and I further developed design plans, an option to complete the perimeter wall with Cutter Soil Mixing (CSM) technology was developed. CB and I described the CSM process as a modified trench cutter technique, to be used for both perimeter groundwater cutoff, and for caisson demolition SOE. CSM technology blends slurry while mixing soil on the down stroke, and injects cement into the blended soil cuttings on the upstroke to create a cemented 'cutoff wall'. CB and I proposed several variations for three key support elements: the perimeter cutoff wall; the dewatering well system; and the caisson SOE shoring system. The proposed alternatives brought many enhancements in the design and integration of the work to be executed. CB and I personnel were persistent in seeing their vision through that resulted in a significant benefit in worker safety and schedule enhancement (early finish by 5 months). (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Integration of National Laboratory and Low-Activity Waste Pretreatment System Technology Service Providers - 16435

The National Laboratories are a critical partner and provide expertise in numerous aspects of the successful execution of the Direct-Feed Low Activity Waste Program. The National Laboratories are maturing the technologies of the Low-Activity Waste Pretreatment System consistent with DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets', expectations. The National Laboratories continue to mature waste forms, i.e., glass and secondary waste grout, for formulations and predictions of long-term performance as inputs to performance assessments. The working processes with the National Laboratories have been developed in procurements, communications, and reporting to support the necessary delivery-based technology support. The relationship continues to evolve from planning and technology development to support of ongoing operations and integration of multiple highly coordinated facilities. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Lessons Learned in Implementation of Radiological Investigations of Small-Scale Sites in Port Hope, Ontario - 16534

The Port Hope Area Initiative is a $1.28 billion project for the remediation of historic low-level radioactive waste resulting from the operation of Eldorado Nuclear Limited and its private-sector predecessors between 1932 and 1988 in Port Hope and Port Granby, Ontario, approximately 100 km east of Toronto. Included in the project is the investigation of all 4,800 privately and publicly owned properties in Port Hope in order to identify and remediate an estimated 375 properties containing LLRW exceeding clean-up criteria. This paper discusses the progress of the investigations, the development of clean-up criteria, methodologies used to identify historic LLRW, and lessons learned to date. This paper will be of greatest interest to future project managers of similar investigations. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Safety analysis report for packaging shielding and nuclear criticality safety courses developed and conducted by Oak Ridge National Laboratory

The US Department of Energy (DOE) Packaging Certification Program, Office of Packaging and Transportation, is offering Safety Analysis Report for Packaging (SARP) Shielding and Nuclear Criticality Safety (NCS) courses for SARP generalists and analysts. The SARP generalist course is designed for project managers, supervisors, NCS/shielding subject matter experts (SME), and SMEs in non-NCS/shielding technical areas (e.g., structural, thermal, package design) who need to better understand how NCS/shielding analyses fit into the broader body of SARP documentation. The generalist course provides an overview of the regulations and guidelines for the criticality and shielding analyses for a SARP and illustrates how the NCS/shielding chapters integrate with the other parts of the SARP. After course material is presented, students in the generalist course will review an actual SARP document to examine key elements of the shielding and criticality analyses. The analyst course provides detailed instructions on the radioactive material package shielding analyses and NCS evaluation fundamentals needed by analysts/practitioners (i.e., safety analysts and/or technical reviewers) to prepare and/or review technical analyses for the SARP documentation. The analyst course also provides an overview of regulations and guidelines, in addition to detailed in-class exercises associated with package shielding and NCS analyses. Analysis teams will be faced with staged SARP examples in which several important decision processes in the generation of a SARP will be demonstrated and discussed. The courses are offered at Oak Ridge National Laboratory's National Transportation Research Center. (authors)

11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS↗

Developing a new criticality methodology to support decommissioning of legacy plutonium facilities

To decommission a legacy plutonium finishing facility, a number of gloveboxes need to be disposed of. These gloveboxes have been in place since the 1960's and were operational until the 1980's. A period of initial clean out and decommissioning took place in the 1990's and the first gloveboxes were removed from the line in the early 2000's. Compliance with downstream waste handling facility requirements meant that the gloveboxes needed to be removed using intensive 'hands-on' methods in order to size reduce them to fit into 200 litre (55 gallon) drums. This is the standard approach for handling waste items known as Plutonium Contaminated Material (PCM) on the Sellafield site and was credited in the criticality safety case for the decommissioning of the gloveboxes as it allowed each waste drum to be individually assayed such that the fissile content of the waste could be known. Not only was this approach time-consuming and laborious but as it involved operators working with cutting tools in a highly contaminated area it was challenged as being overly restrictive to operations and potentially hazardous to the workers. In order to decommission the remaining nine gloveboxes in the facility, a new decommissioning approach and associated criticality methodology has been developed. Instead of intensive size reduction and waste drum assay, the gloveboxes will be removed with little or no size reduction and put into storage crates without assay. The criticality assessor will review the operational history of each glovebox, along with the decommissioning records and relevant plant data, to make an evidence-based judgement that the crated glovebox represents no greater a residual criticality risk than would have been realised from the equivalent number of PCM drums that the standard decommissioning approach would have generated. This method identifies, in conjunction with the plant personnel, a number of review points to ensure that before the glovebox is removed any bulk residue material has been recovered and no more than a safe amount of moderating material (fixative) has been added to fix any remaining fissile contamination. Finally, once these review points have been confirmed to be complete - through a stakeholder meeting with criticality safety, plant operators and project managers - the glovebox will be placed in a crate, and this crate will be declared a Low Criticality Risk crate. No formal assay will be required prior to exporting the crate to the downstream waste handling facility and no fissile mass value will be assigned to the contents of the crate. No further intrusive work will be required on the crate and it can be safely stored without any spacing requirements, pending final disposal. (author)

11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS↗

Cold Commissioning Simulant Selection for the Hanford Tank Waste Treatment Plant LAW Facility - 18465

Commissioning the Low-Activity Waste (LAW) Facility of the Hanford Tank Waste Treatment and Immobilization Plant (WTP) will require large volumes (∼2,000,000 liters) of a non-radioactive, chemically analogous waste simulant. Cold commissioning will provide for operator training in an integrated facility, demonstration of mechanical process equipment capacity, environmental performance demonstration of emissions control systems, and process control systems shakedown and tuning. Selection of the cold commissioning simulant is following a structured four-phase process to arrive at the preferred composition and recipe. Phases I, II and III are complete. Phase I laid the framework for decision making with preparation of a Project Management Plan, an update to the Simulant Development, Approval, Validation, and Documentation procedure, and a kickoff meeting to gather stakeholder input into the simulant definition and selection criteria. Phase II consisted of a comprehensive literature search and compilation of LAW simulant recipes, followed by initial screening against the selection criteria identified in Phase I. This process identified 72 candidate simulant recipes and down-selected 9 for further study. Phase III studies involved a) statistical comparisons of the similarity of candidate simulant compositions to the tank waste feed vector, b) process modelling of the commissioning sequence with each simulant to estimate glass former and simulant material consumption, offgas and effluent volumes and compositions, and product glass volumes and compositions, and c) evaluation of simulants against the immobilized LAW glass composition algorithm to determine allo able waste loading to ensure compliance with product specifications and process constraints. The results of these studies identified two of the candidate recipes to be carried forward to full-scale testing. Phase IV consists of testing these two recipes at vendor facilities to determine scalability, fabricability, and stability of the simulants when produced at industrial scale. Scalability is the ability to take a recipe from bench scale (1 to 40 liters) batch size to full scale (>35,000 liters) batch size. Fabricability is the ability of a recipe to be prepared in large batches without the need for complex or expensive mechanical equipment, heating, or cooling systems. Stability is the ability of a simulant to withstand long term storage and variations in environmental conditions without unacceptable changes in key characteristics (the set of chemical, physical, and rheological parameters that the simulant is intended to exhibit during cold commissioning tests). Simulants will also be tested for compatibility with other startup material (i.e., frit), tuning simulants, and environmental performance demonstration test spiking solutions to ensure against unexpected situations. Using a structured process is essential when making high impact decisions such as waste simulant selection. Proper planning and a clear explanation of how the decision process will unfold is key to obtaining stakeholder buy-in as more information is gathered. The documentation resulting from this structured selection process will be compiled and summarized in a Cold Commissioning Simulant Definition deliverable due to the Department of Energy 24 months before the start of Cold Commissioning. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

LAWPS Technology Maturation Program and Scaled Testing - 18488

The Technology Maturation Program for the Low-Activity Waste Pre-Treatment System (LAWPS) had been developed utilizing the guidance of DOE-Order 413.3B 'Program and Project Management for the Acquisition of Capital Assets' for Technology Readiness and Technology Maturation. The technology maturation plan (TMP) for LAWPS established principal technology elements (TE) for the proposed process, designated critical technology elements (CTE), and identified the necessary activities to mature the technologies for successful deployment of the LAWPS. The testing progress for the integrated engineering scale testing and support activities are presented. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Challenges of Transitioning Obsolete Legacy Systems to Decommissioning in NRU - 19047

The National Research Universal (NRU) Reactor permanently shut down on March 31, 2018 after over 60 years of service. The NRU reactor and its ancillary buildings are now being readied for decommissioning. The preparation for decommissioning will begin with the deactivation of NRU systems and the ancillary buildings. The focus of this paper will be to document some of the experiences of deactivating the Effluent Heat Recovery System (EHRS) and Building 440 which houses the Emergency Cooling Water Supply system for NRU. Both the EHRS and Building 440 are legacy and obsolete. The deactivation of the EHRS and Building 440 encountered a number of operational challenges such as lapses in maintenance and housekeeping, loss of motivation, and issues with work plans. Organizational challenges, lack of knowledge and expertise, lack of support, and conflicting intra-organizational priorities, are believed to influence the operational challenges. The impact of challenges encountered on the project is reviewed with an emphasis on Project Management and people. 'Lessons learned' based on the experiences of the authors is provided detailing, amongst other things, the importance of people in the success of deactivating the NRU reactor and its ancillary buildings. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Flowsheet Definition for the Tank Side Cesium Removal Unit and the Importance of Early Communication - 19142

The U.S. Department of Energy (DOE) tank operations contractor Washington River Protection Solutions, LLC (WRPS) is working toward the start of low-activity waste (LAW) treatment in direct feed mode as soon as 2022. WRPS is responsible for providing the pre-treated feed for this direct feed mode and had originally planned to use the Low Activity Waste Pretreatment System (LAWPS) to supply the initial feed in 2021. In September 2017, in response to a DOE-sponsored LAWPS program review, a new system was proposed to provide the initial feed during direct feed mode until a supplemental pretreatment capability is ready to begin processing feed. This system, known as the Tank Side Cesium Removal (TSCR) system, is based on the Savannah River Tank Closure Cesium Removal (TCCR) system and technology used to separate cesium out of reactor water at Fukushima. A preliminary flowsheet was needed to form the initial basis for future decisions and allow discussions between operations, project management, and the customer. The main goal of the TSCR flowsheet was to form a process flow diagram, process description, and much of the preliminary information to be used to help inform future decisions. When flowsheet development first began, little to no information was readily known and what was known needed to be compiled in one place and digestible by several audiences. The impacts of various parameters on the system also needed a vehicle for clear communication to varying audiences. While a more complicated model was being completed, a model of the process was created using Microsoft Excela which could have several parameters changed while maintaining basic logical requirements (such as treated waste volume cannot exceed the volume of the Interim LAW Storage Tank [ILST], must shutdown for so many days for column changeout, etc.). This program allowed the unit downtime, start dates, treatment rates, and several other variables to be modified and reflect the ILST storage volume as a function of mission progression. The model with several different parameters gathered from the various groups was combined into an early flowsheet of the TSCR process and created one of the first citable documents about TSCR implementation at Hanford. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

A Picture Speaks 360,000 Words - Virtual Reality as a Decommissioning Planning Tool - 19364

Whiteshell Laboratories, located in Manitoba, Canada, provided research facilities for the Canadian nuclear industry since the early 1960's. Decommissioning of Whiteshell Laboratories has been ongoing since 2002 under Atomic Energy of Canada (AECL) and, more currently, since 2015 under the WL Closure Project managed by Canadian Nuclear Laboratories (CNL). One of the key steps to ensuring safe decommissioning operations is effective planning, including pre-job briefings, and post-job verification and review. Effective planning involves clear and concise communication of the field conditions, system configurations, hazards, and task goals or achievements to front line employees, and task approvers and verifiers. In many instances, employees can enter, view, inspect, verify or otherwise familiarize themselves with the task and task location. However, in several cases, hazardous conditions in the task location make it difficult for employees to easily access the location themselves, due to hazardous conditions, PPE requirements, training qualification gaps or space limitations. Since 2016, 360 deg. cameras have been used to create a virtual 'tour' of the hazardous task locations at Whiteshell Laboratories, which can be viewed by one or all of the employees involved in a task, from a position of safety. This allows a task to be discussed with all employees involved without the need for added risk of exposure to dose or industrial hazards or costly PPE, and supports ALARA control techniques of removing the hazard by moving work planning walk downs away from hazardous locations and guarding the worker by limiting the time a worker is exposed to the hazard. This paper provides an overview of the technologies used to capture and present the 360 virtual tours, the benefits from a safety, schedule and cost perspective, and the limitations of the current implementation that could be improved upon in a future iteration. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

US EPA Superfund Radon Vapor Intrusion Screening Level (RVISL) Electronic Calculator - 20340

Currently, there is no U.S. Environmental Protection Agency (EPA) guidance on correlating soil or groundwater levels of radon with indoor radon concentrations at Superfund sites. EPA is developing the Radon Vapor Intrusion Level Calculator (RVISL) Calculator which is an online tool. The RVISL calculator: (1) lists three radon isotopes (Rn-219, Rn-220 and Rn-222) known to pose a potential cancer risk through the inhalation pathway; (2) provides generally recommended risk and Applicable or Relevant and Appropriate Requirements (ARAR) based preliminary remediation goals (PRG) for groundwater, soil gas (exterior to buildings and sub-slab) and indoor air for default target risk and ARAR based levels and exposure scenarios; and (3) allows calculation of site-specific PRGs based on user-defined target risk and ARAR based levels and exposure scenarios. EPA developed the RVISL calculator to help risk assessors, remedial project managers, and others involved with risk assessment and decision making at radioactively contaminated sites. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

THERMAL STRUCTURAL AND SHOCK EVENT EVALUATIONS OF THE FUELING PELLET INJECTION SYSTEM FOR ITER

The US is among seven partner nations in a collaborative effort to design, build, and demonstrate fusion’s ability to be a large-scale carbon free energy source. Each country has its own Domestic Agencies (DA) that contribute directly to the ITER project. US ITER, which is a DOE Office of Science project managed by Oak Ridge National Laboratory, is developing world class engineering solutions to the design, construction, and assembly of the burning plasma experiment that can demonstrate the scientific and technological feasibility of fusion. US ITER’s scope includes completing the preliminary and final design, qualifying materials and processes for manufacture and testing, executing manufacturing, and delivering the Fueling Pellet Injection System (FPIS) to the ITER site for assembly. The US-ITER FPIS system is designed to inject cryogenically frozen pellets of deuterium-tritium (D-T) into the plasma. The FPIS has two main functions: 1. Provide a steady supply of deuterium and tritium fuel, 2. Mitigating the impact of edge localized modes on the plasma facing components. The FPIS will have the capability to reside in three port cells within a tritium second barrier containment cask. Each pellet cask contains three flight tubes linking with penetrations on the torus cryopump housing and vacuum vessel (VV): two for the magnetic high field side (HFS) pellet injection and one for the magnetic low field side (LFS) pellet injection. This paper presents results of the thermal-structural analyses of the FPIS flight tube structural components when subjected to various loads such as electromagnetic (EM) loads, nuclear heating, seismic, and operational, and dynamic shock events. The resulting temperatures and stresses under combined conditions have been found to satisfy the design criteria to ensure safe and reliable operation of the FPIS flight tubes within the vacuum vessel.

Martinez, Oscar↗

A code inspection process for security reviews

In recent years, it has become more and more evident that software threat communities are taking an increasing interest in Grid infrastructures. To mitigate the security risk associated with the increased numbers of attacks, the Grid software development community needs to scale up effort to reduce software vulnerabilities. This can be achieved by introducing security review processes as a standard project management practice. The Grid Facilities Department of the Fermilab Computing Division has developed a code inspection process, tailored to reviewing security properties of software. The goal of the process is to identify technical risks associated with an application and their impact. This is achieved by focusing on the business needs of the application (what it does and protects), on understanding threats and exploit communities (what an exploiter gains), and on uncovering potential vulnerabilities (what defects can be exploited). The desired outcome of the process is an improvement of the quality of the software artifact and an enhanced understanding of possible mitigation strategies for residual risks. This paper describes the inspection process and lessons learned on applying it to Grid middleware.

99 GENERAL AND MISCELLANEOUS↗

Integrating Safeguards and Security with Safety into Design

There is a need to minimize security risks, proliferation hazards, and safety risks in the design of new nuclear facilities in a global environment of nuclear power expansion, while improving the synergy of major design features and raising operational efficiency. In 2008, the U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA) launched the Next Generation Safeguards Initiative (NGSI) covering many safeguards areas. One of these, launched by NNSA with support of the DOE Office of Nuclear Energy, was a multi-laboratory project, led by the Idaho National Laboratory (INL), to develop safeguards by design. The proposed Safeguards-by-Design (SBD) process has been developed as a structured approach to ensure the timely, efficient, and cost effective integration of international safeguards and other nonproliferation barriers with national material control and accountability, physical security, and safety objectives into the overall design process for the nuclear facility lifecycle. A graded, iterative process was developed to integrate these areas throughout the project phases. It identified activities, deliverables, interfaces, and hold points covering both domestic regulatory requirements and international safeguards using the DOE regulatory environment as exemplar to provide a framework and guidance for project management and integration of safety with security during design. Further work, reported in this paper, created a generalized SBD process which could also be employed within the licensed nuclear industry and internationally for design of new facilities. Several tools for integrating safeguards, safety, and security into design are discussed here. SBD appears complementary to the EFCOG TROSSI process for security and safety integration created in 2006, which focuses on standardized upgrades to enable existing DOE facilities to meet a more severe design basis threat. A collaborative approach is suggested.

98 NUCLEAR DISARMAMENT, SAFEGUARDS, AND PHYSICAL P↗

DRAINING HAZARDOUS FLUIDS DURING BUILDING 221-1F DEACTIVATION AT THE SAVANNAH RIVER SITE

Several years ago, SRS completed a four year mission to decommission {approx}250 excess facilities. As part of that effort, SRS deactivated multiple facilities (e.g. Building 247-F, Naval Fuels Facility, and Building 211-F, Outside Facilities for F-Canyon) that contained extensive piping systems filled with hazardous material (e.g. nitric acid). Draining of hazardous materials from piping was successfully completed in all facilities without incident. In early 2009, the decommissioning program at SRS was restarted as a result of funding made available by the American Recovery & Reinvestment Act (ARRA). Under ARRA, draining of piping containing hazardous material was initiated in multiple facilities including Building 221-1F (or A-Line). This paper describes and reviews the draining of piping containing hazardous materials at A-Line, with emphasis on an incident involving the draining of nitric acid. The paper is intended to be a resource for engineers, planners, and project managers, who face similar draining challenges.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

A Systematic Approach for Evaluation of Capture Zones at Pump and Treat Systems Part 1

A Systematic Approach for Evaluation of Capture Zones at Pump and Treat Systems presents a systematic approach for the evaluation of capture zones at pump and treat systems, and provides an overview of a recently published USEPA document on the topic (EPA 600/R-08/003, January 2008). The target audience for the course is project managers who review those analyses and/or make decisions based on these types of analyses. This course will highlight:The importance of capture zone analysis during ground water remediation, particularly for sites requiring containmentKey concepts of capture, such as "target capture zones" and "converging lines of evidence"Typical errors made in capture zone analysisIn addition, steps associated with a systematic approach for capture zone analysis will be discussed. These steps include the following:Step 1: Review site data, site conceptual model, and remedy objectivesStep 2: Define site-specific Target Capture Zone(s)Step 3: Interpret water levelsPotentiometric surface maps (horizontal) and water level difference maps (vertical)Water level pairs (gradient control points)Step 4: Perform calculations (as appropriate based on site complexity)Estimated flow rate calculationCapture zone width calculationModeling (analytical and/or numerical) to simulate water levels, in conjunction with particle tracking and/or transport modelingStep 5: Evaluate concentration trends Step 6: Interpret actual capture based on steps 1-5, compare to Target Capture Zone(s), and assess uncertainties and data gaps Examples will be used to demonstrate key aspects of capture zone analysis.

Source record↗

The CHPRC Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan

The scope of the CH2M Hill Plateau Remediation Company, LLC (CHPRC) Groundwater and Technical Integration Support (Master Project) is for Pacific Northwest National Laboratory staff to provide technical and integration support to CHPRC. This work includes conducting investigations at the 300-FF-5 Operable Unit and other groundwater operable units, and providing strategic integration, technical integration and assessments, remediation decision support, and science and technology. The projects under this Master Project will be defined and included within the Master Project throughout the fiscal year, and will be incorporated into the Master Project Plan. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the CHPRC Groundwater and Technical Integration Support (Master Project) and all releases associated with the CHPRC Soil and Groundwater Remediation Project. The plan is designed to be used exclusively by project staff.

300 FF-5 Operable Unit↗

Novel Earned Value Management System Maturity Framework and Its Relation to Project Performance

Earned value management systems (EVMS) are used by industry practitioners to successfully manage projects and programs; however, there has been no past study to characterize and evaluate the impact of EVMS maturity on project performance. This paper introduces a novel framework, developed to measure the EVMS maturity, composed of 56 attributes arrayed across ten subprocesses, which together make up an integrated project/program management system. This paper describes how the framework was conceived and developed, based on literature review and data collected from industry workshops. Then, it examines the relationship between EVMS maturity and ten project performance metrics through statistical analyses. The study analyzed project data from 35 projects and programs worth over $21.8 billion in total cost. For this sample, results showed statistically significant differences between projects with high and low EVMS maturity; on average, projects exhibiting high EVMS maturity have 54% less cost overruns and 19% less change orders versus their performance measurement baseline. Higher maturity projects and programs also achieve better customer satisfaction, meet business objectives more often, and are more often in compliance with EVMS standards and guidelines. This paper contributes to the body of knowledge by providing a practical and novel framework for assessing the maturity of earned value management systems. Practitioners can use the framework to improve their integrated project and program management.

99 GENERAL AND MISCELLANEOUS↗