Pu-238 Production Progress at Idaho National Laboratory From December 2023 to November 2024
Idaho National Laboratory (INL) has continued in the effort to produce Pu-238 to support NASA deep space missions. In support of the production goal of contributing 700 g to the 1.5 kg per year constant rate production of Pu-238 heat source material in the United States by 2026. All available inner core positions of the Advanced Test Reactor (ATR) have been qualified for production for a 20% Np target, with efforts nearing completion for a 30% Np target further increasing production amounts. This includes the North East Flux Trap (NEFT), South Flux Trap (SFT), Inner A, H positions. With the completion of qualifying the inner core of ATR, work has started on the qualifying the outer core. The portion of the outer core that will produce Pu-238 includes the Large and Medium I positions. With the continued qualification work, INL is on track to contribute to the production goal by 2026.