NASA NTRS1998
The NASA/Mir Phase I Program is a precursor to the assembly and operations of the International Space Station (ISS). The Phase I Program covers a four-year period and encompasses over ten shuttle flights to the Mir, culminating with the flight of STS-91 in June 1998. The Mir-Orbiting Station (Mir-OS) provides an excellent environment, both onboard and on the ground, for learning and studying the characteristics associated with crew-tended operations on long duration missions. By the end of the Phase I program, NASA astronauts will have accumulated over two years of continuous operations experience working and living onboard the Mir-OS. Ground controllers, working in Russia and at remote sites in the United States, will have gained valuable experience in the generation, maintenance, and coordination of the information and products required to support the long duration crew members onboard the Mir-OS. The experience gained by the crew and ground support personnel in the area of long duration mission operations has resulted in a number of factors that need to be considered in the definition and implementation of the processes and products for the ISS. While there are many areas in which experience has been gained, this paper focuses on the lessons learned regarding the level of detail and flexibility of crew timelines. Provided in this paper is an overview of the characteristics associated with long duration mission timeline development and execution, a summary of applicable lessons learned identified and documented through participation in the NASA/Mir Phase I Program, a detailed discussion of "Gross Timelines" as implementation which addresses the lessons learned. Also discussed are the challenges that must be overcome in getting the ISS program to recognize, evaluate, and learn from the crew and ground controller experience gained through participation in the NASA/Mir Phase I Program.