Energy and water in the Western and Texas interconnects.

The Department of Energy's Office of Electricity has initiated a $60M program to assist the electric industry in interconnection-level analysis and planning. The objective of this effort is to facilitate the development or strengthening of capabilities in each of the three interconnections serving the lower 48 states of the United States, to prepare analyses of transmission requirements under a broad range of alternative futures and develop long-term interconnection-wide transmission expansion plans. The interconnections are the Western Interconnection, the Eastern Interconnection, and the Texas Interconnection. One element of this program address the support and development of an integrated energy-water Decision Support System (DSS) that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water stress for transmission and resource planning (the Eastern Interconnection is not participating in this element). Specific objectives include: (1) Develop an integrated Energy-Water Decision Support System (DSS) that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water stress for transmission and resource planning. (2) Pursue the formulation and development of the Energy-Water DSS through a strongly collaborative process between members of this proposal team and the Western Electricity Coordinating Council (WECC), Western Governors Association (WGA), the Electric Reliability Council of Texas (ERCOT) and their associated stakeholder teams. (3) Exercise the Energy-Water DSS to investigate water stress implications of the transmission planning scenarios put forward by WECC, WGA, and ERCOT. The goals of this project are: (1) Develop an integrated Energy-Water Decision Support System (DSS) that will enable planners to analyze the potential implications of water stress for transmission and resource planning. (2) Pursue the formulation and development of the Energy-Water DSS through a strongly collaborative process between Western Electricity Coordinating Council, Electric Reliability Council of Texas, Western Governors Association, and Western States Water Council. (3) Exercise the Energy-Water DSS to investigate water transmission planning scenarios.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Integrated Energy-Water Planning in the Western and Texas Interconnections

While long-term regional electricity transmission planning has traditionally focused on cost, infrastructure utilization, and reliability, issues concerning the availability of water represent an emerging issue. Thermoelectric expansion must be considered in the context of competing demands from other water use sectors balanced with fresh and non-fresh water supplies subject to climate variability. An integrated Energy-Water Decision Support System (DSS) is being developed that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water availability and cost for long-range transmission planning. The project brings together electric transmission planners (Western Electricity Coordinating Council and Electric Reliability Council of Texas) with western water planners (Western Governors’ Association and the Western States Water Council). This paper lays out the basic framework for this integrated Energy-Water DSS.

electricity↗

Analysis of Drought Impacts on Electricity Production in the Western and Texas Interconnections of the United States

Electricity generation relies heavily on water resources and their availability. To examine the interdependence of energy and water in the electricity context, the impacts of a severe drought to assess the risk posed by drought to electricity generation within the western and Texas interconnections has been examined. The historical drought patterns in the western United States were analyzed, and the risk posed by drought to electricity generation within the region was evaluated. The results of this effort will be used to develop scenarios for medium- and long-term transmission modeling and planning efforts by the Western Electricity Coordination Council (WECC) and the Electric Reliability Council of Texas (ERCOT). The study was performed in response to a request developed by the Western Governors Association in conjunction with the transmission modeling teams at the participating interconnections. It is part of a U.S. Department of Energy-sponsored, national laboratory-led research effort to develop tools related to the interdependency of energy and water as part of a larger interconnection-wide transmission planning project funded under the American Recovery and Reinvestment Act. This study accomplished three main objectives. It provided a thorough literature review of recent studies of drought and the potential implications for electricity generation. It analyzed historical drought patterns in the western United States and used the results to develop three design drought scenarios. Finally, it quantified the risk to electricity generation for each of eight basins for each of the three drought scenarios and considered the implications for transmission planning. Literature on drought impacts on electricity generation describes a number of examples where hydroelectric generation capacity has been limited because of drought but only a few examples of impact on thermoelectric generation. In all documented cases, shortfalls of generation were met by purchasing power from the market, albeit at higher prices. However, sufficient excess generation and transmission must be available for this strategy to work. Although power purchase was the most commonly discussed drought mitigation strategy, a total of 12 response strategies were identified in the literature, falling into four main categories: electricity supply, electricity demand response, alternative water supplies, and water demand response. Three hydrological drought scenarios were developed based on a literature review and historical data analysis. The literature review helped to identify key drought parameters and data on drought frequency and severity. Historical hydrological drought data were analyzed for the western United States to identify potential drought correlations and estimate drought parameters. The first scenario was a West-wide drought occurring in 1977; it represented a severe drought in five of the eight basins in the study area. A second drought scenario was artificially defined by selecting the conditions from the 10th-percentile drought year for each individual basin; this drought was defined in this way to allow more consistent analysis of risk to electricity generation in each basin. The final scenario was based upon the current low-flow hydro modeling scenario defined by WECC, which uses conditions from the year 2001. These scenarios were then used to quantify the risk to electricity generation in each basin. The risk calculations represent a first-order estimate of the maximum amount of electricity generation that might be lost from both hydroelectric and thermoelectric sources under a worst-case scenario. Even with the conservative methodology used, the majority of basins showed a limited amount of risk under most scenarios. The level of risk in these basins is likely to be amenable to mitigation by known strategies, combined with existing reserve generation and transmission capacity. However, the risks to the Pacific Northwest and Texas Basins require further study. The Pacific Northwest is vulnerable because of its heavy reliance on hydroelectric generation. Texas, conversely, is vulnerable because of its heavy dependence on thermoelectric generation, which relies on surface water for cooling, along with the fact that this basin seems to experience more severe drought events on average. Further modeling analysis will be performed in conjunction with the modeling teams at the participating interconnections (WECC and ERCOT) to explore the transmission implications of the drought scenarios in more detail. Given the first-order nature of this analysis, more detailed study of the potential impacts of drought on electricity generation is recommended. Future analyses should attempt to model the potential impacts of drought at the power-plant level, including potential mitigation strategies; include the effects of drought duration; understand the impacts of climate change; and consider economic impacts.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

Frequency Response Assessment and Improvement of Three Major North American Interconnections due to High Penetrations of Photovoltaic Generation

As photovoltaic (PV) generation penetration increases, the inertial and primary frequency response of North American electric grids after a generation loss disturbance will decrease. This change could negatively influence North American power grids frequency stability. This project produced a series of high PV penetration models from detailed, validated base models of all three U.S. interconnections (Eastern Interconnection, Western Electricity Coordinating Council, and Electric Reliability Council of Texas) so that the effects of increased PV generation on their frequency responses can be fully quantified. Mitigation strategies were also developed and validated using both software and hardware test beds.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Impacts of Spatial Resolution in a High-Fidelity Capacity Expansion Model: An ERCOT Case Study

Capacity expansion models are important tools in examining the evolution of the electric power sector. Embedded in these tools are many modeling choices with consequential impacts on computational burden and associated analysis. In this study, we adjust the spatial resolution of the Regional Energy Deployment System (ReEDS) to understand the implications of higher-fidelity modeling on energy system projections and model solve times. The native ReEDS regions capture the contiguous United States in 134 balancing areas whereas the regions in the higher-resolution version are defined by over 3,000 U.S. counties. Using both resolutions, we conduct a case study of the Texas Interconnection (The Electric Reliability Council of Texas [ERCOT]) to explore differences in model projections and to inform appropriate applications of high spatial resolution in a large-scale, applied capacity expansion model.

county↗

Impact of simultaneous activities on frequency fluctuations — comprehensive analyses based on the real measurement data from FNET/GridEye

Simultaneous human activities such as the Super Bowl game would cause certain impacts on frequency fluctuations in power systems. With the help of FNET/GridEye measurements, this work aims to give comprehensive analyses on the frequency fluctuations during Super Bowl LIV held on Feb. 2, 2020, so as to better understand several phenomena caused by simultaneous activities and help system operation and control. First, recent developments of FNET/GridEye are introduced briefly. Second, the frequency fluctuations of Eastern Interconnection (EI), western electricity coordinating council (WECC), and electric reliability council of Texas (ERCOT) power systems during Super Bowl LIV are analyzed. Third, frequency fluctuations of Super Bowl Sunday and ordinary Sundays in 2020 are compared. Finally, the differences of frequency fluctuations among different years during the Super Bowl and their change trend are also given. Furthermore, several possible explanations including the simultaneity of electricity consumption at the beginning of commercial breaks and the halftime show, the increasing usage of the Internet, and the increasing size of TV screens are illustrated in detail in this work.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Frequency Response Assessment and Enhancement of the U.S. Power Grids towards Extra-High Photovoltaic Generation Penetrations – an Industry Perspective

Nonsynchronous generations such as photovoltaics (PVs) are expected to undermine bulk power systems (BPSs)' frequency response at high penetration levels. Though the underlying mechanism has been relatively well understood, the accurate assessment and effective enhancement of the U.S. interconnections, frequency response under extra-high PV penetration conditions remains an issue. In this paper, the industry-provided full-detail interconnection models were further validated by synchrophasor frequency measurements and realistically-projected PV geographic distribution information were used to develop extra-high PV penetration scenarios and dynamic models for the three main U.S. interconnections, including Eastern Interconnection (EI), Western Electricity Coordinating Council (WECC), and Electric Reliability Council of Texas (ERCOT). Up to 65% instantaneous PV and 15% wind penetration were simulated and the frequency response change trend of each U.S. interconnection due to the increasing PV penetration level were examined. Most importantly, the practical solutions to address the declining frequency response were discussed. This paper will provide valuable guidance for policy makers, utility operators and academic researchers not only in the U.S. but also other countries in the world.

14 SOLAR ENERGY↗

ERCOT Event on February 26, 2008: Lessons Learned

This report summarizes the event which occured on February 26, 2008, in which the Electric Reliability Council of Texas (ERCOT) called for an Emergency Electric Curtailment Plan (EECP) at 18:41 due to a worsening imbalance between generation and load which led to a decline in system frequency. The event is of special interest, and was widely reported on in the press, because wind generation played a partial role in the event. Other load-response events, which did not involve wind generation, have not received similar attention.

17 WIND ENERGY↗

Austin Sustainable and Holistic Integration of Energy Storage and Solar PV [Austin SHINES]. Final Report, Version 2

The Austin SHINES project and solution is a software management platform, for an electric grid with a high penetration of dispersed photovoltaic (PV) solar generation sites, which maintains the traditional power quality and reliability associated with grid service. This project developed and deployed the platform as a Distributed Energy Resource Management System (DERMS), engaging multiple advanced controls, to evaluate operation and optimization of a fleet of diverse DER assets, installed at several locations among Austin Energy’s customers and distribution system. The project also produced a methodology to create a replicable DERMS template, adaptable to other regions and market structures. Last, Austin SHINES aimed to demonstrate the solution’s methodology would enable the DER grid ecosystem to serve load at a technical cost (System Levelized Cost of Electricity, or System LCOE) of less than the U.S. Department of Energy SHINES program metric of $0.14/kWh, in a defined boundary, while enabling a high penetration of distributed PV. Research was categorized in 6 reports (Final Deliverables = FD) listed below, with titles and descriptions indicating which area of understanding was investigated: FD-1: System Levelized Cost of Electricity (System LCOE) Methodology The creation and use of the System LCOE to Serve Load metric that encompasses the holistic, system-level costs and benefits of all resources, and enables them to be evaluated based on their ability to support an efficient and low-cost integrated grid ecosystem. FD-2: Software Platform Product Description The creation of new DER control methodologies deployable within a utility-grade software platform that enable DER's to maximize their benefit within a grid, that is capable of serving load enabling a high penetration of distributed PV generation. FD-3: Optimal Design Methodology Optimal design methodologies for individual DER installations that enable utilities to determine the optimal combinations and sizing for individual DER sites. FD-4: Austin SHINES Ownership and Operation Models for DER System Performance A comparison of multiple DER aggregation and ownership methodologies including direct utility control, third-party aggregator, and autonomous. FD-5: Economic Modeling & Optimization A comparison of multiple DER technology mixes and configurations within the distribution system, providing insight into an optimal blend of technologies that best enable the distribution system to serve load at the lowest cost at high penetrations of solar. FD-6: Fielded Assets Deployed DER assets within the Austin Energy SHINES circuits. Austin SHINES provided an opening for state-of-the-art technology products to be deployed, providing a rich opportunity for improving how each of the products perform as stand-alone products, and in concert with other complementary products. The Austin SHINES project comprised of two key metrics for System LCOE: SystemLCOE_SHINES<$0.14/kWh Modeled ΔSystemLCOE_SHINES/ΔSystemLCOE_Base≥20% at same solar penetration The System LCOE calculation uses the costs of the utility-owned infrastructure as it exists today, the cost of the DERs that exist in the system today, and the cost of the purchase of energy from ERCOT wholesale markets over the course of the calendar year. All costs are on an annualized basis. The capital and operating costs are derived from the rate case, which produces a yearly cost. The net cost of energy and services imported to the system is integrated over the test year, as is the load served and solar penetration. The first metric was easily achieved by every scenario considered. The goal was set when the Department of Energy’s SHINES Funding Opportunity Announcement was written in 2015 and was a more difficult target at the time. Due mostly to rapidly declining costs for DERs and the significant decrease in the Electric Reliability Council of Texas (ERCOT) energy market prices, which results in lower net cost of energy purchases, the System LCOE is well below this target for all scenarios considered. A fleet of DERs can assume different mixtures, each of which serves the load at a different LCOE. The optimal mixture of DERs serves load at the smallest System LCOE. The second metric (hereinafter %delta metric) asks that the holistic DERMS controls reduce the incremental cost above the baseline of going to a high solar penetration future by at least 20% as compared to the case of a DER deployment with no sophisticated controls (autonomous). Many comparison sets were created throughout this project. Physical technology was installed for informing utility engineering and testing several types of operational control schemes, through the DERMS. The types of operational control which were compared for valuation of the System LCOE Metric were: Holistic control = using the full suite of the DERMS platform to decide and optimize how/why the systems operate depending on weather, market, and reliability signal input. Autonomous control = a local mode at the asset site, wherein a schedule operates the asset, with visibility into performance only No control = the baseline for comparing value against the other two types of control The types of ownership control included: Direct Utility control = the utility dispatches a signal to each asset Third-Party Aggregator = a third party aggregates a fleet of assets and the utility dispatches one signal for all Autonomous = a local mode is set for operation at the asset site, wherein a schedule operates the asset, with visibility into performance only The types of control methodologies deployable within a utility-grade software platform included: Utility Peak Load Reduction = Lower transmission cost obligation Day-Ahead Energy Arbitrage = Realize economic value through price differential Real-Time Price Dispatch = Realize economic value from real-time price spikes Voltage support = Reduce losses and increase solar generation Distribution Congestion Management = Increase local grid reliability Demand Charge Reduction = Lower customer bills and realize system benefit The fielded assets deployed for the project were: Utility Scale Kingsbery Energy Storage System: 1.5 MW / 3 MWh Li-Ion battery storage Mueller Energy Storage System: 1.75 MW / 3.2 MWh Li-Ion battery storage, 7 Energy Storage Units (250 kW each) La Loma Community Solar: 2.6 MW Commercial Scale Aggregated storage installations at 3 sites, with existing solar (300+ kW): One 18 kW / 36 kWh Li-Ion battery storage Two 72 kW / 144 kWh Li-Ion battery storage Residential Scale Aggregated storage installations: -Six stationary battery storage systems (10 kWh each) at homes with existing solar -One Electric Vehicle installed as Vehicle-to-Grid (V2G) Utility-Controlled Solar via Smart Inverters at 12 homes Autonomously-Controlled Smart Inverters at 6 homes Over the course of the project, Austin SHINES undertook installing more than 3 MW of distributed battery energy storage, smart PV inverters, a DER control platform, and other enabling technologies utilizing customer and utility locations and aggregation models. All of these resources were to be integrated and optimized at the utility level. DER assets and control methodologies were designed to achieve a credible pathway to a System LCOE for energy delivered to load of $0.14//kWh or less by 2020, while maximizing distributed solar generation and maintaining acceptable standards of power quality. The project also established a template for other regions to follow, to maximize the adoption of distributed solar PV in support of an economic and efficient grid. In total, the Austin SHINES project added value to the DER subject area in each layer of integration. From utility, to commercial to residential scales, the sheer hierarchy of communication and coordination was a significant accomplishment in addition to learnings from what these communications revealed was unique to each. Economically, the most effective method demonstrated was the criticality of planning phases. Contingencies and multiple projection scenarios helped guide the project to deploy optimal design as close as feasible, in real world conditions. The project and reports will serve public benefit by outlining specific areas of DER strategy and installation where many stakeholders and needs can be addressed with improved efficiency. Overall, communities and utilities should use the results to guide the increasing options available for powering the grid with DER, renewables, and carbon considerate energy.

14 SOLAR ENERGY↗

Analysis of Unit-Level Changes in Operations with Increased SPP Wind from EPRI/LCG Balancing Study

Wind power development in the United States is outpacing previous estimates for many regions, particularly those with good wind resources. The pace of wind power deployment may soon outstrip regional capabilities to provide transmission and integration services to achieve the most economic power system operation. Conversely, regions such as the Southeastern United States do not have good wind resources and will have difficulty meeting proposed federal Renewable Portfolio Standards with local supply. There is a growing need to explore innovative solutions for collaborating between regions to achieve the least cost solution for meeting such a renewable energy mandate. The Department of Energy funded the project 'Integrating Midwest Wind Energy into Southeast Electricity Markets' to be led by EPRI in coordination with the main authorities for the regions: SPP, Entergy, TVA, Southern Company and OPC. EPRI utilized several subcontractors for the project including LCG, the developers of the model UPLAN. The study aims to evaluate the operating cost benefits of coordination of scheduling and balancing for Southwest Power Pool (SPP) wind transfers to Southeastern Electric Reliability Council (SERC) Balancing Authorities (BAs). The primary objective of this project is to analyze the benefits of regional cooperation for integrating mid-western wind energy into southeast electricity markets. Scenarios were defined, modeled and investigated to address production variability and uncertainty and the associated balancing of large quantities of wind power in SPP and delivery to energy markets in the southern regions of the SERC. DOE funded Oak Ridge National Laboratory to provide additional support to the project, including a review of results and any side analysis that may provide additional insight. This report is a unit-by-unit analysis of changes in operations due to the different scenarios used in the overall study. It focuses on the change in capacity factors and the number of start-ups required for each unit since those criteria summarize key aspects of plant operations, how often are they called upon and how much do they operate. The primary analysis of the overall project is based on security-constrained unit commitment (SCUC) and economic dispatch (SCED) simulations of the SPP-SERC regions as modeled for the year 2022. The SCUC/SCED models utilized for the project were developed through extensive consultation with the project utility partners, to ensure the various regions and operational practices are represented as best as possible in the model. SPP, Entergy, Oglethorpe Power Company (OPC), Southern Company, and the Tennessee Valley Authority (TVA) actively participated in the project providing input data for the models and review of simulation results and conclusions. While other SERC utility systems are modeled, the listed SERC utilities were explicitly included as active participants in the project due to the size of their load and relative proximity to SPP for importing wind energy.

17 WIND ENERGY↗

Integrated Agent-Based and Production Cost Modeling Framework for Renewable Energy Studies

The agent-based framework for renewable energy studies (ARES) is an integrated approach that adds an agent-based model of industry actors to PLEXOS and combines the strengths of the two to overcome their individual shortcomings. It can examine existing and novel wholesale electricity markets under high penetrations of renewables. ARES is demonstrated by studying how increasing levels of wind will impact the operations and the exercise of market power of generation companies that exploit an economic withholding strategy. The analysis is carried out on a test system that represents the Electric Reliability Council of Texas energy-only market in the year 2020. The results more realistically reproduce the operations of an energy market under different and increasing penetrations of wind, and ARES can be extended to address pressing issues in current and future wholesale electricity markets.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Integrated Energy-Water Planning in the Western and Texas Interconnections

While long-term regional electricity transmission planning has traditionally focused on cost, infrastructure utilization, environmental impact, and reliability, the availability of water is an emerging issue. Toward this growing need, thermoelectric expansion should consider competing demands from other water use sectors balanced with fresh and non-traditional water supplies subject to climate variability. To address this need the Department of Energy's Office of Electricity Delivery and Energy Reliability supported an integrated planning project with funding through the American Reinvestment and Recovery Act (2009). Specifically, an integrated energy-water analysis was performed to support transmission system planners in the Western and Texas Interconnections to explore the potential implications of water availability and cost for long-term transmission planning. The project brought together electric transmission planners (e.g., Western Electricity Coordinating Council (WECC) and the Electric Reliability Council of Texas (ERCOT)) with western water planners (e.g., Western Governors' Association and the Western States Water Council). Efforts were organized into ten specific tasks: (1) project coordination and outreach; (2) thermoelectric water use; (3) non-thermoelectric water use; (4) water availability; (5) water cost; (6) environmental risk; (7) climate variability; (8) energy for water; (9) decision support system interface; and, (10) transmission planning support. Major accomplishments associated with this effort include: For the first time water availability was used to inform generation expansion planning by WECC and ERCOT. For the first time, projections of intensifying drought and its effect on reservoir levels, and thermal effluent discharge permitting were used to inform operational and expansion planning by ERCOT. Water withdrawal and consumption were characterized for each power plant in the WECC and ERCOT service areas/regions. Water use factors were also developed for a range of unit processes that allowed projection of future water demands related to electric generation expansion planning. Working with state water managers current and future water use (withdrawal and consumption) were projected throughout the Western United States at an 8-digit Hydraulic Unit Code (HUC-8) level (over 1200 watersheds). In a similar fashion water availability and cost were mapped across the Western United States. Considered were five different sources of water: unappropriated surface water, unappropriated groundwater, appropriated water, municipal wastewater and brackish groundwater. Water basins (at the HUC-8 level) were mapped across the Western United States with regard to their potential for conflicts between aquatic and riparian species and habitats listed under the Endangered Species Act and water availability for future energy development. Water planners were engaged through the Western States Water Council and thus reflects their membership of the 17 contiguous western states (i.e., Texas up through the Dakotas and West). Power plants at greatest risk to the impacts of drought were identified. The analysis considered the hazards of low flows, insufficient reservoir storage, and elevated water temperatures under intensifying drought conditions projected for the future. The electricity used to provide water-related services was mapped at a county level throughout the Western U.S. Considered was the electricity required for interbasin conveyance, agricultural pumping, drinking water and wastewater services. To communicate our results the project has produced 6 journal articles, 1 book chapter, 11 reports, and 47 presentations at related conferences.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

Review of the Recent Frequency Performance of the Eastern, Western and ERCOT Interconnections

The reliable operation of an electric power system depends on careful management of the balance between generation and load to ensure that system frequency is maintained within narrow bounds around a scheduled value. Yet, maintaining frequency at the scheduled value is challenging because the load served is continuously changing, and occasionally, events such as the sudden loss of a large generation plant or large amount of load, cause frequency to deviate abruptly. This report reviews the recent history of frequency performance for all three U.S. interconnections: Eastern, Western, and the Electric Reliability Council of Texas (ERCOT). The review is based on data collected by the North American Electric Reliability Corporation (NERC). The review focuses on frequency response, which measures the performance of the interconnections immediately following sudden, large imbalances between load and generation. Trends in frequency response are presented and preliminary efforts are made to relate frequency response to other aspects of frequency performance and to examine aspects of the methods used to calculate frequency response.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

Comprehensive Well to Wheel Analysis for Plug-in-Hybrid Electric Vehicles in the U.S.

The U.S. electric power infrastructure is a strategic national asset that is underutilized most of the time. With the proper changes in the operational paradigm, it could generate and deliver the necessary energy to fuel the majority of the U.S. light-duty vehicle (LDV) fleet. In doing so, it would reduce greenhouse gas emissions, improve the economics of the electricity industry, and reduce the U.S. dependency on foreign oil. This paper estimates the regional percentages of the energy requirements for the U.S. LDV stock that could potentially be supported by the existing infrastructure, based on the 12 modified North American Electric Reliability Council regions, as of 2002. For the United States as a whole, about 70% of LDV fleet in the U.S. could be supported by the existing infrastructure with some degree of load management. This has an estimated gasoline displacement potential of 6.5 million barrels of oil equivalent per day, or approximately 52% of the nation's oil imports. The paper also discusses the impact on overall emissions of criteria gases and greenhouse gases as a result of shifting emissions from millions of individual vehicles to a few hundred power plants. Overall, PHEVs could reduce greenhouse gas emissions with regional variations dependent on the local generation mix. Total NOX emissions may or may not increase, dependent on the use of coal generation in the region. Any additional SO2 emissions associated with the expected increase in generation from coal power plants would need to be cleaned up to meet the existing SO2 emissions constraints. Particulate emissions would increase in 8 of the 12 regions. The emissions in urban areas are found to improve across all pollutants and regions as the emission sources shift from millions of tailpipes to a smaller number of large power plants in less-populated areas. This paper concludes with a discussion about possible grid impacts as a result of the PHEV load as well as the likely impacts on the plant and technology mix of future generation-capacity expansions.