Summary Report for the C50 Cryomodule Project

The Thomas Jefferson National Accelerator Facility has recently completed the C50 cryomodule refurbishment project. The goal of this project was to enable robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project included removal, refurbishment and reinstallation of ten CEBAF cryomodules at a rate of three per year. The refurbishment process included reprocessing of SRF cavities to eliminate field emission and to increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New 'dogleg' couplers were installed between the cavity and helium vessel flanges to intercept secondary electrons that produce arcing in the fundamental Power Coupler (FPC). Other changes included new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuner. Damaged or worn components were replaced as well. All ten of the refurbished cryomodules are now installed in CEBAF and are currently operational. This paper will summarize the performance of the cryomodules.

11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS↗

JLAB UPGRADE AND HIGH CURENT CAVITY DEVELOPMENTS

We present the status and recent results from the development of new SRF cavities for the CEBAF 12 GeV upgrade and for future light source applications. The JLab 12 GeV upgrade requires ten new high-performance CW cryomodules. These will each contain eight seven-cell cavities of a "low-loss" design with HOM damping sufficient for ~1mA of continuous current. Jlab has fabricated and tested a number of such cavities and demonstrated compliance with all 12 GeV project requirements with conventional BCP cavity processing. Recently we have also electro-polished several cavities of this type and shown significantly better performance than the standard BCP. This processing method could provide improved operational margin and lower cryogenic loads at the CEBAF working point. For future light source applications such as FELs or ERLs, cavities with higher beam current capability are desirable. Jlab has developed a high-current cavity for such applications with a cell shape optimized to minimize HOM power extraction and maximize the BBU threshold. We report on the latest tests of this design and on plans to assemble a two-cavity cryomodule for testing with beam in the recirculation loop of the JLab FEL.

Preble, Joseph↗

Overview of the First Five Refurbished CEBAF Cryomodules

The Thomas Jefferson National Accelerator Facility is currently engaged in a cryomodule refurbishment project known as the C50 project. The goal of this project is robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project includes removing, refurbishing and replacing ten CEBAF cryomodules at a rate of three per year. Refurbishment includes reprocessing of SRF cavities to eliminate field emission and increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New "dogleg" couplers between the cavity and helium vessel flanges will intercept secondary electrons that produce arcing at the 2 K ceramic window in the fundamental Power Coupler (FPC). Modifications of the external Q (Qext) of the FPC will allow higher gradient operations. Other changes include new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuner. Any damaged or worn components will be replaced as well. Currently, five refurbished cryomodules have been installed in CEBAF and are currently operational. This paper will summarize the test results and current operational experience.

Drury, Michael↗

HOM Survey of the First CEBAF Upgrade Style Cavity Pair

The planned upgrade of the Continuous Electron Beam Accelerator Facility (CEBAF) at the Thomas Jefferson National Accelerator Laboratory (JLab) requires ten new superconducting rf (SRF) cavity cryomodules to double the beam energy to the envisaged 12 GeV. Adequate cavity Higher Order Mode (HOM) suppression is essential to avoid multipass, multibunch beam break-up (BBU) instabilities of the recirculating beam. We report on detailed HOM surveys performed for the first two upgrade style cavities tested in a dedicated cavity pair cryomodule at 2K. The safety margin to the BBU threshold budget at 12 GeV has been assessed.

43 PARTICLE ACCELERATORS↗

Overview of the First Five Refurbished CEBAF Cryomodules

The Thomas Jefferson National Accelerator Facility is currently engaged in a cryomodule refurbishment project known as the C50 project. The goal of this project is robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project includes removing, refurbishing and replacing ten CEBAF cryomodules at a rate of three per year. Refurbishment includes reprocessing of SRF cavities to eliminate field emission and increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New "dogleg" couplers between the cavity and helium vessel flanges will intercept secondary electrons that produce arcing at the 2 K ceramic window in the fundamental Power Coupler (FPC). Modifications of the external Q (Qext) of the FPC will allow higher gradient operations. Other changes include new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuner. Any damaged or worn components will be repla

11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS↗

Solid Waste Management Requirements Definition for Advanced Life Support Missions: Results

Prior to determining what Solid Waste Management (SWM) technologies should be researched and developed by the Advanced Life Support (ALS) Project for future missions, there is a need to define SWM requirements. Because future waste streams will be highly mission-dependent, missions need to be defined prior to developing SWM requirements. The SWM Working Group has used the mission architecture outlined in the System Integration, Modeling and Analysis (SIMA) Element Reference Missions Document (RMD) as a starting point in the requirement development process. The missions examined include the International Space Station (ISS), a Mars Dual Lander mission, and a Mars Base. The SWM Element has also identified common SWM functionalities needed for future missions. These functionalities include: acceptance, transport, processing, storage, monitoring and control, and disposal. Requirements in each of these six areas are currently being developed for the selected missions. This paper reviews the results of this ongoing effort and identifies mission-dependent resource recovery requirements.

Alazraki, Michael P.↗

A Simulation Study Comparing Incineration and Composting in a Mars-Based Advanced Life Support System

The objective of this study is to compare incineration and composting in a Mars-based advanced life support (ALS) system. The variables explored include waste pre-processing requirements, reactor sizing and buffer capacities. The study incorporates detailed mathematical models of biomass production and waste processing into an existing dynamic ALS system model. The ALS system and incineration models (written in MATLAB/SIMULINK(c)) were developed at the NASA Ames Research Center. The composting process is modeled using first order kinetics, with different degradation rates for individual waste components (carbohydrates, proteins, fats, cellulose and lignin). The biomass waste streams are generated using modified "Eneray Cascade" crop models, which use light- and dark-cycle temperatures, irradiance, photoperiod, [CO2], planting density, and relative humidity as model inputs. The study also includes an evaluation of equivalent system mass (ESM).

Hogan, John↗

Modeling of Solid Waste Processing Options in BIO-Plex

BIO-Plex is a ground-based test bed currently under development by NASA for testing technologies and practices that may be utilized in future long-term life support missions. All aspects of such an Advanced Life Support (ALS) System must be considered to confidently construct a reliable system, which will not only allow the crew to survive in harsh environments, but allow the crew time to perform meaningful research. Effective handling of solid wastes is a critical aspect of the system, especially when recovery of resources contained in the waste is required. This is particularly important for ALS Systems configurations that include a Biomass Production Chamber. In these cases, significant amounts of inedible biomass waste may be produced, which can ultimately serve as a repository of necessary resources for sustaining life, notably carbon, water, and plant nutrients. Numerous biological and physicochemical solid waste processing options have been considered. Biological options include composting, aerobic digestion, and anaerobic digestion. Physicochemical options include pyrolysis, SCWO (supercritical water oxidation), various incineration configurations, microwave incineration, magnetically assisted gasification, and low temperature plasma reaction. Modeling of these options is a necessary step to assist in the design process. A previously developed top-level model of BIO-Plex implemented in MATLAB Simulink (r) for the use of systems analysis and design has been adopted for this analysis. Presently, this model only considered incineration for solid waste processing. Present work, reported here, includes the expansion of this model to include a wider array of solid waste processing options selected from the above options, bearing in mind potential, near term solid waste treatment systems. Furthermore, a trade study has also been performed among these solid waste processing technologies in an effort to determine the ideal technology for long-term life support missions.