Search NASA⌕ Search

Engineering topics

Sangroula, M.

Publications and source records attributed to Sangroula, M..

Thermal Analysis and Simulations of the Abort Kicker Magnets Systems for the Electron-Ion Collider

The Abort Kicker Magnets system used in the current Relativistic Heavy Ion Collider (RHIC) to steer the circulating beam into the dump will be subjected to higher heat loads in the Electron-Ion Collider (EIC). After analyzing the existing abort kicker magnets and running thermal simulations in ANSYS it was concluded that they may not be suitable for use as-is in the future EIC due to heat and impedance concerns in the magnets. Possible solutions include adding a round titanium-coated ceramic beam tube to help solve the heat and impedance concerns, but this will reduce the limiting aperture of the kicker magnet. Another possible solution to meet all the performance requirements for EIC would be to add titanium-coated ceramic plates with water-cooling and tapered transitions that significantly improve the impedance and lower the heat in the magnets with less reduction to the aperture.

43 PARTICLE ACCELERATORS↗

The EIC accelerator: design highlights and project status

The design of the electron-ion collider (EIC) at Brookhaven National Laboratory is well underway, aiming at a peak electron-proton luminosity of 10e+34 cm^-1·sec^-1. This high luminosity, the wide center-of-mass energy range from 29 to 141 GeV (e-p) and the high level of polarization require innovative solutions to maximize the performance of the machine, which makes the EIC one of the most challenging accelerator projects to date. The complexity of the EIC will be discussed, and the project status and plans will be presented.

43 PARTICLE ACCELERATORS↗

Thermal simulation of the EIC HSR interconnect module - RF fingers

The Electron Ion Collider (EIC) Hadron Storage Ring (HSR) will reuse most of the existing superconducting magnets from the RHIC storage ring. However, the existing beam vacuum chamber and stripline BPMs will not be compatible with the planned EIC hadron bunches that will have a 3x higher intensity and be 10x shorter, and some operational scenarios with large radial offsets of the beam in the vacuum chamber. To address these challenges, a copper coated beam screen will be implemented, the existing RHIC stripline BPMs will be shielded and an interconnect module design, including new BPM will be installed adjacent to the existing BPMs. A thermal analysis of the new arc BPM interconnect housing has been conducted to assess the heating caused by beam induced resistive wall heating and electron cloud heating. An analysis of the BPM module has been made and reported separately. This report will focus on the other side of the interconnect module, containing the RF fingers.

43 PARTICLE ACCELERATORS↗

Updates on the Wake Potential Calculations for the Electron-ion Collider with ECHO3D

ECHO3D has been used for calculating the geometric impedance and short-range wakefields for several EIC (Electron-Ion Collider) beamline vacuum components in the past few years. This note summarizes the wake potential calculations conducted in 2023 with ECHO3D for components from both the hadron storage ring (HSR) and the electron storage ring (ESR). For the HSR, calculations have been carried out for the polarimeter, the beam screen with pump slots and the bellow with pump ports. For the ESR, the short-range wake potential for the flange weld as well as various designs of the storage ring cavity have been calculated.

43 PARTICLE ACCELERATORS↗

Electron-Ion Collider Design Status

The Electron-Ion Collider (EIC) is being designed for construction at Brookhaven National Laboratory. Activities have been focused on beam-beam simulations, polarization studies, and beam dynamics, as well as on maturing the layout and lattice design of the constituent accelerators and the interaction region. The latest design advances will be presented.

43 PARTICLE ACCELERATORS↗

Summary of the CeC Experiment in RHIC Run 21

The coherent electron cooling (CeC) experiment at RHIC is crucial for determining the feasibility of this technique for cooling the hadron beam in the electron-ion collider (EIC) and reaching the luminosity of 10 34 cm -1 s -1 . During RHIC Run 21, various progresses have been made including successfully commissioning the time resolved diagnostic beam line (TRDBL), achieving the key performance parameters (KPP) of the system and the development of novel methods for accurate alignment of the electron beam with the ion beam. While the longitudinal cooling of the ion beam with cooling time of 100 hours was observed during Run 21, it was related to the traditional electron cooling since the cooling rate was not as sensitive to the energy of the electron beam as what one would expect from the CeC. In Run 21, we were not able to observe the longitudinal cooling of the ion beam caused by CeC and the main challenges are identified as the insufficient stability of the electrons' energy. The sources of the energy jitter have been identified and we are making improvements to the stability of the CeC system for Run 22.

43 PARTICLE ACCELERATORS↗