The EIC accelerator: design highlights and project status

The design of the electron-ion collider (EIC) at Brookhaven National Laboratory is well underway, aiming at a peak electron-proton luminosity of 10e+34 cm^-1·sec^-1. This high luminosity, the wide center-of-mass energy range from 29 to 141 GeV (e-p) and the high level of polarization require innovative solutions to maximize the performance of the machine, which makes the EIC one of the most challenging accelerator projects to date. The complexity of the EIC will be discussed, and the project status and plans will be presented.

43 PARTICLE ACCELERATORS↗

Beam-induced heat deposited in the EIC HSR screens

The beam screens of the Electron-Ion Collider (EIC) Hadron Storage Ring (HSR) have several beam-induced heat sources: the resistive-wall impedance, the electron cloud, and beam particle losses. This note discusses the heat load to the HSR screens from resistive-wall impedance and beam particle losses for different beam scenarios.

43 PARTICLE ACCELERATORS↗

Design Status of the Electron-Ion Collider

The Electron-Ion Collider is gearing up for "Critical Decision 2", theproject baseline with defined scope, cost and schedule.Lattice designs are beingfinalized, and preliminary component design is being carried out. Beam dynamicsstudies such as dynamic aperture optimization, instability and polarizationstudies, and beam-beam simulations are continuing in parallel. We report onthe latest developments and the overall status of the project, and presentthe plans for future activities.

43 PARTICLE ACCELERATORS↗

CRAB CAVITIES FOR ILC

Explore the source record for details and available documents.

73 NUCLEAR PHYSICS AND RADIATION PHYSICS↗

Eddy current studies for the beam screen of the Electron-Ion Collider hadron storage ring superconducting magnets

A copper-clad stainless steel beam screen will be installed in each of the Relativistic Heavy Ion Collider (RHIC) superconducting (SC) magnets used for making the Electron-Ion Collider (EIC) Hadron Storage Ring (HSR). Eddy currents are induced within conductors to oppose a changing magnetic flux. Eddy currents will appear on the EIC HSR beam screens during ramp up and ramp down, after a magnet quenches and when reversing the polarity of the γ transition jump quadrupoles during γ transition crossing. This study evaluates the magnitude of the eddy currents, the temperature increase due to Joule heating and the stress at the beam screens from the eddy-current induced force.

43 PARTICLE ACCELERATORS↗

Thermal conductivity of RHIC superconducting magnet insulation materials at low temperatures

The Electron-Ion Collider (EIC) is planned to be built upon the Relativistic Heavy Ion Collider (RHIC), which vacuum chamber will need to be upgraded to host the EIC hadron beams. For the beam pipe section running through the RHIC superconducting (SC) magnets, the baseline is to insert a screen that will get cooled by thermal contact to the 4.55 K beam pipe of RHIC. Knowing the material properties of the cold mass is thus crucial to understand which is the final temperature that the screen and the superconducting coils in the magnets will reach during the passage of the EIC beams. The thermal conductivities of two insulation materials in the RHIC superconducting magnets and a reference material were measured at cryogenic temperatures at the Magnet Science and Technology division of the National High Magnetic Field Laboratory (NHMFL). The measurements were performed in a Quantum Design physical property measurement system. This report explains the motivation behind this work and summarizes the measurement method and results.

43 PARTICLE ACCELERATORS↗

Pathways for a compact double-quarter wave cavity with low peak surface fields and large deflecting kick

This paper describes the parameter choices necessary to obtain a compact Double Quarter Wave (DQW) cavity with low peak surface fields – electric and magnetic – and large deflecting kick. The work is motivated by the space limitations and demanding crabbing voltage required for the crabbing system of the Electron-Ion Collider (EIC) and focuses on the optimization of the 197 MHz crab cavities for the EIC’s hadron ring. For a crabbing voltage of 11.5 MV, the optimized cavity is less than one meter long, showing a maximum peak surface magnetic field of 70 mT and a maximum peak surface electric field of 45 MV/m.

43 PARTICLE ACCELERATORS↗

A BEAM SCREEN TO PREPARE THE RHIC VACUUM CHAMBER FOR EIC HADRON BEAMS: CONCEPTUAL DESIGN AND REQUIREMENTS

The Electron Ion Collider (EIC) Hadron Storage Ring (HSR) will use the existing Relativistic Heavy Ion Collider storage rings, including the superconducting magnet arcs [1]. The vacuum chambers in the superconducting magnets and the cold mass interconnects were not designed for EIC beams and so must be updated to reduce resistive-wall heating and to suppress e-clouds. To do so without compromising the EIC luminosity goal, a stainless steel beam screen with colaminated copper and a thin layer of amorphous carbon will be installed. This paper describes the main requirements that our solution for the hadron ring vacuum chamber needs to satisfy, including impedance, aperture limitations, vacuum, thermal and structural stability, mechanical design, installation and operation. The conceptual design of the beam screen currently under development is introduced.

43 PARTICLE ACCELERATORS↗

EIC Hadron Beamline Vacuum Studies

Ninety percent of the EIC hadron ring vacuum chamber consists of cold-bore sections running through and interconnecting 4.55 K RHIC superconducting (SC) magnets. The EIC operating specification requires shorter bunches and 3x higher intensity beams which are not appropriate for the present RHIC stainless steel cold-bore beam tube. The intensity and emittance of the hadron beams will degrade due to interactions with residual gas or vacuum instabilities arising from the expected resistive-wall (RW) heating, electron clouds, and beam-induced desorption mechanisms. Without strategies to limit RW heating, major cryogenic system modifications are needed to prevent SC magnet quenches. The SC magnet cold-bore beam tubes will be equipped with a high RRR copper-clad stainless steel screen to significantly reduce RW heating and so the effect on the SC magnet cryogenic heat load and temperature. A thin amorphous carbon film applied to the beam-facing copper surface will suppress electron cloud formation. This paper discusses the vacuum requirements imposed by the EIC hadron beams and the plans to achieve the necessary vacuum and thermal stability that ensure acceptable beam quality and lifetime.

43 PARTICLE ACCELERATORS↗

Cryogenic RF tests of US LARP DQW SPS-series cavities

Crab cavities are one of the several components included in the luminosity upgrade of the Large Hadron Collider (HL-LHC). For nominal operation, the cavities have to provide a nominal deflecting kick of 3.4 MV per cavity in Continuous Wave operation at 2 K. The requirement for an unjacketed cavity – bare cavity equipped with Higher-Order Mode (HOM) filters and field antenna – is to reach at least a deflecting voltage of 4.1 MV (20% margin) with the heat load to the 2 K bath below 10 W. Cryogenic RF tests confirmed the required performances in bare cavities, with several cavities exceeding the required voltage by more than 50%. However, the first tests of a Double-Quarter Wave (DQW) cavity with one out of three HOM filters did not reach the required voltage. The present paper describes the studies and tests conducted to understand the limiting factor in the operation of a DQW cavity with HOM filters in the most up-to-date prototypes produced in the US and based on the DQW SPS-series design. The recipe to meet the performance specification for a bare DQW cavity with HOM filters and exceed the voltage requirement by more than 35% is discussed.

43 PARTICLE ACCELERATORS↗

Niobium-coated copper cavities for the eRHIC crabbing system

Crabbing of hadron bunches in particle colliders requires high kick voltages in the order of MV. The crabbing system of the High Luminosity Large Hadron Collider (HL-LHC) will be using Double-Quarter Wave (DQW) and Radio-Frequency Dipole (RFD) cavities, both compact deflecting cavity designs fabricated from bulk Nb sheets. In the same fashion, the baseline crabbing system for the electron Relativistic Heavy Ion Collider (eRHIC) will consist of a series of DQWcavities. Encouraging cryogenic RF performances of a Nb/Cu Quarter-Wave Resonator (QWR) and the proposal of a niobium-coated copper (Nb/Cu) Wide- OpenedWaveguide (WOW) cavity for deflecting purposes stimulated the necessity to review the possibilities of Nb/Cu cavities for the future crabbing system of eRHIC. This note will study the feasibility of usingWOW cavities for the eRHIC crabbing system and will compare the expected performances of DQW and WOW cavities based on the latest cryogenic RF results.

42 ENGINEERING↗