Stochastic Analysis for Long Term Capital Structures, Systems, and Components Refurbishment and Replacement

Abstract

As commercial Nuclear Power Plants (NPPs) pursue extended plant operation in the form of Second License Renewal (SLR), opportunities exist for these plants to provide capital investments to ensure long-term safe and economic performance. At the current time, several utilities have announced an intention to pursue extended operation for one or more of their NPPs via SLR . The goal of this research is to develop a risk-informed approach to evaluate and prioritize plant capital investments made in preparation for, and during the period of, extended plant operations to support decisions for NPP operations. Since the capital investments are influenced by various factors, such as markets, safety and regulatory, the decision-making process of NPP operations should take into account relevant factors for balancing risks, costs and profits. The traditional method of capital budgeting is based on the priority list of candidate projects using economic measures such as benefit-investment ratio, net present value (NPV) and internal rate of return. In the literatures, the problem of capital budgeting or the variant can be represented by an appropriate knapsack problem. The knapsack approach to capital budgeting takes as input as investment, along with the cost and profit of each project. The objective of capital budgeting is to find the combination of the binary decisions for every investment such that the overall profit is as large as possible. The output is a collection of projects to be carried out, and we refer this selected collection of projects as a project portfolio. One limitation of traditional optimization models for capital budgeting is that they do not account for risk/uncertainty in profit and cost streams associated with individual projects, they do not account for risk in resource availability in future years [1,2,3]. Projects can incur cost over-runs, especially when projects are large, performed infrequently, and when there is risk regarding technical viability, external contractors, and/or suppliers of requisite parts and materials. Occasionally, projects are performed ahead of schedule and with cost savings. Planned budgets for capital improvements can be cut and key personnel may be lost. Or, there may be surprise windfalls in budgets for maintenance activities due to decreased costs for “unplanned” maintenance. In these cases, how should we resolve capital budgeting when we have risk forecasts for costs, profits and budgets? One approach we proposed in this summary is to re-solve the optimization models based on assumed statistical distributions of given parameters. If these distributions were not available, a two-stage stochastic optimization approach can be used to provide priority lists to decision-makers to support better risk-informed decisions [4, 5]. In this summary, we will only focus on the first approach.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Wang, Congjian, Mandelli, Diego, Popova, Ivilina, Hess, Stephen, St Germain, Shawn W, Smith, Curtis L. 2020-06-07. Stochastic Analysis for Long Term Capital Structures, Systems, and Components Refurbishment and Replacement. https://www.osti.gov/biblio/1632401

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Large language models for transportation research: Methodologies, state of the art, and future opportunities

The rapid rise of large language models (LLMs) is transforming transportation research, with significant advancements emerging between 2023 and 2025, a period marked by the inception and swift growth of adopting and adapting LLMs for various transportation applications. Despite these significant advancements, however, a systematic review and synthesis of the existing literature remains lacking. This paper aims to fill this gap by providing a comprehensive review of the methodologies and applications of LLMs in transportation. We explore key applications, including autonomous driving, travel behavior prediction, and general transportation-related queries, alongside LLM methodologies such as zero- or few-shot learning, prompt engineering, and fine-tuning. From the review, critical research gaps are identified. From the methodological perspective, many of the research limitations can be addressed by integrating LLMs with existing tools and refining LLM architectures. From the application perspective, research opportunities for LLMs to address various transportation challenges are also explored. By synthesizing these findings, this review not only presents the state-of-the-art LLM adoption and adaptation in transportation, but also proposes future research directions as well as insights and recommendations for policymakers and practitioners, paving the way for greater LLM-driven research innovations in transportation in the future.

42 ENGINEERING↗