Safety-Related Instrumentation and Control Pilot Upgrade: Initial Scoping Phase Implementation and Lessons Learned

Abstract

In May 2016, the U.S. Nuclear Regulatory Commission (NRC) staff provided a digital instrumentation and control (I&C) regulatory infrastructure integrated action plan to the NRC for approval. One of the objectives of that plan was to establish a clear regulatory structure with reduced regulatory uncertainty to enable the expanded safe use of digital I&C in commercial nuclear reactors while continuing to ensure safety and security. To achieve this end, the NRC, with collaboration from industry, developed a streamlined License Amendment Request Alternate Review (AR) process for safety-related (SR) digital I&C upgrades. In spite of this effort, the industry has remained reluctant to perform such I&C upgrades because of perceived regulatory and financial risks associated with being the first or an early adopter of the AR process for SR I&C upgrades. The U.S. Department of Energy Light Water Reactor Sustainability Program at the Idaho National Laboratory performed Initial Scoping Phase research to help break this impasse by supporting a SR I&C Pilot Upgrade, working with MPR Associates, ScottMadden Inc., and Exelon Generation. Exelon’s Limerick Generating Station (LGS) was selected as the target for this research. This paper summarizes the Initial Scoping Phase engineering and operations, licensing, and project management activities necessary to bound the scope, schedule, and estimated cost of the project sufficiently to enable utility management authorization of Conceptual Design Phase activities. These efforts and associated products are intended to provide a template to support larger industry efforts to perform similar upgrades as a foundation stone for a digital transformation that will improve plant safety, reliability, and operational performance while lowering plant total cost of ownership. As a result of the combined effort of Exelon Generation and research participants, Conceptual Design Phase activities for the subject upgrade at LGS were approved by Exelon. Further, the U.S. Department of Energy also awarded a $50 million cost share award to Exelon in order to pave the way for SR I&C modernization and associated control room upgrades across the U.S. nuclear fleet. Additional research reports are planned for the Conceptual Design Phase, Detailed Design Phase, and the Implementation Phase of the LGS project to document the process followed and promulgate lessons learned to industry.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Hunton, Paul Joseph, England, Robert T., Herrell, David, Lawrie, Sean, Samselski, Mark. 2022-05-18. Safety-Related Instrumentation and Control Pilot Upgrade: Initial Scoping Phase Implementation and Lessons Learned. https://doi.org/10.1080/00295450.2022.2053808

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

ZiaCore Critical Experiment Demonstrates Key Technologies for Nuclear Energy Systems

ZiaCore is a LANL Laboratory Directed Research and Development (LDRD) project focused on developing and demonstrating key technologies for future nuclear energy systems. The project itself was split into three tasks: 1) Design of the ZiaCore Reactor, a UO2 fueled, graphite and zirconium-hydride (ZrH) moderated, heat pipe cooled micro-reactor 2) Development of the ZrH and heat pipes components 3) Performance of a critical experiment with a representative portion of the ZiaCore reactor incorporating the ZrH and heat pipes developed and made at LANL.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Operating Experience Data Analysis for Digital Instrumentation and Control System Reliability and Risk Assessment in Nuclear Power Plants

The implementation of advanced digital instrumentation and control (DI&C) systems in U.S. nuclear power plants (NPPs) can bring significant advancements in reliability, monitoring, and control capabilities. However, these systems also introduce new challenges, particularly in assessing risks such as common-cause failures (CCFs) and establishing robust reliability estimates for DI&C components. Addressing these challenges is critical for ensuring the safe and efficient operation of NPPs. Recently, Idaho National Laboratory was tasked by the U.S. Nuclear Regulatory Commission (NRC) to conduct a DI&C reliability study using operating experience data from the nuclear industry. The two operating experience data sources for the study are the Institute of Nuclear Power Operations’ Industry Reporting and Information System (IRIS) and the NRC’s Licensee Event Report database which is hosted at Idaho National Laboratory at https://lersearch.inl.gov/LERSearchCriteria.aspx. This report provides a comprehensive examination of DI&C systems, including their architecture, operational advantages, and associated challenges. It reviews existing industry DI&C studies and failure mode taxonomies, along with reliability data from various industries. Through a detailed analysis of these databases, the study provides insights into DI&C system performance. Considerations should be given to incorporate DI&C failure data into the NRC's Integrated Data Collection and Coding System and updating the Reliability and Availability Data System to support ongoing DI&C reliability studies. Recommendations are also provided for modeling DI&C reliability and CCF in probabilistic risk assessment, thereby supporting risk-informed decision-making and enhancing the reliability and safety of NPPs.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗