Safety-Related Instrumentation and Control Pilot Upgrade (Initial Scoping Phase Implementation Report)

Abstract

This research report (1) describes the process followed and products developed during the SR I&C Pilot Project Initial Scoping Phase, and (2) captures lessons learned. Exelon Generation and LWRS collaborated to develop a Digital Transformation Strategy as part of a larger Advanced Concept of Operations. The proposed SR I&C Pilot Upgrade provides a foundation stone for this Digital Transformation that will improve plant safety, reliability, and operational performance while lowering plant Total Cost of Ownership (TCO). Initial Scoping Phase activities for this Pilot Project have been performed in accordance with industry processes that have been adapted to better support digital upgrades. These processes include IP-ENG-001, Standard Design Process (SDP), NISP-EN-04, Standard Digital Engineering Process (SDEP), and Electric Power Research Institute (EPRI) Report 3002011816, Digital Engineering Guide (DEG). Completing Initial Scoping Phase Engineering and Operations, Licensing, and Project Management Activities was necessary to sufficiently bound the scope, schedule, and estimated cost of the Project to enable utility management to authorize moving into the Conceptual Design Phase. A significant finding of the Business Case Analysis (BCA) methodology developed and applied as part of this effort was that the growth rate of material costs for sustaining the operation of obsolete SR I&C equipment is accelerating. This directly contributed to the Project Economic Analysis created to justify continuing the Project. Project Initial Scoping Phase lessons learned have also been captured to assist the larger industry in understanding the Digital Transformation Strategy and SR I&C Pilot Project Initial Scoping Phase efforts. This is in keeping with the public/private partnership that has been established between the Department of Energy (DOE) and Exelon for this effort with engagement from the NRC. By addressing first-of-a-kind (FOAK) risks and capturing lessons learned, the SR I&C Pilot Upgrade Project addresses technical, regulatory, and business risks to enable subsequent implementers of similar upgrade.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Hunton, Sr., Paul Joseph, England, Robert T., Segner, Gerald, Samselski, Mark, Bonanni, George, Heaney, Paul, Herrell, David, Jessup, William, Kerrigan, Mike, Lawrie, Sean. 2020-09-01. Safety-Related Instrumentation and Control Pilot Upgrade (Initial Scoping Phase Implementation Report). https://doi.org/10.2172/1662013

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

ZiaCore Critical Experiment Demonstrates Key Technologies for Nuclear Energy Systems

ZiaCore is a LANL Laboratory Directed Research and Development (LDRD) project focused on developing and demonstrating key technologies for future nuclear energy systems. The project itself was split into three tasks: 1) Design of the ZiaCore Reactor, a UO2 fueled, graphite and zirconium-hydride (ZrH) moderated, heat pipe cooled micro-reactor 2) Development of the ZrH and heat pipes components 3) Performance of a critical experiment with a representative portion of the ZiaCore reactor incorporating the ZrH and heat pipes developed and made at LANL.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Operating Experience Data Analysis for Digital Instrumentation and Control System Reliability and Risk Assessment in Nuclear Power Plants

The implementation of advanced digital instrumentation and control (DI&C) systems in U.S. nuclear power plants (NPPs) can bring significant advancements in reliability, monitoring, and control capabilities. However, these systems also introduce new challenges, particularly in assessing risks such as common-cause failures (CCFs) and establishing robust reliability estimates for DI&C components. Addressing these challenges is critical for ensuring the safe and efficient operation of NPPs. Recently, Idaho National Laboratory was tasked by the U.S. Nuclear Regulatory Commission (NRC) to conduct a DI&C reliability study using operating experience data from the nuclear industry. The two operating experience data sources for the study are the Institute of Nuclear Power Operations’ Industry Reporting and Information System (IRIS) and the NRC’s Licensee Event Report database which is hosted at Idaho National Laboratory at https://lersearch.inl.gov/LERSearchCriteria.aspx. This report provides a comprehensive examination of DI&C systems, including their architecture, operational advantages, and associated challenges. It reviews existing industry DI&C studies and failure mode taxonomies, along with reliability data from various industries. Through a detailed analysis of these databases, the study provides insights into DI&C system performance. Considerations should be given to incorporate DI&C failure data into the NRC's Integrated Data Collection and Coding System and updating the Reliability and Availability Data System to support ongoing DI&C reliability studies. Recommendations are also provided for modeling DI&C reliability and CCF in probabilistic risk assessment, thereby supporting risk-informed decision-making and enhancing the reliability and safety of NPPs.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗