Fermilab’s horizontal test stand upgrade overview and commissioning
Abstract
Cryo-assemblies with the low-beta Nb3Sn quadrupoles for the High Luminosity LHC (HL-LHC) upgrade will be tested at Fermilab’s magnet test facility. Total of 10 cryo-assemblies will be delivered to CERN within the US HL-LHC Accelerator Upgrade Project (AUP). The horizontal test stand at Fermilab already has been used for testing the existing LHC inner-triplet quadrupoles, but the stand and corresponding electrical and cryogenic sub-systems were not operational more than a decade. In order to restore the test stand functions and meet the design and test requirements for the high luminosity LHC magnets, the existing horizontal test facility at Fermilab underwent a significant refurbishment of the cryogenic and mechanical components. Most of the upgrades were completed and verified during so called zero-magnet test by late 2020, and then final commissioning of the upgraded test stand was completed during the first cryo-assembly test in 2023. These tests verified all the cryo-mechanical installations, as well as the test stand operations, including controlled cooldown and operation at 1.9 K, the helium recovery capabilities, magnet protection and process controls.
Explore related subjects
Keep this discovery
Explore connections, maps & timelines
Chlachidze, G., DiMarco, J., Feher, S., Nikolic, V., Nogiec, J., Orris, D., Rabehl, R., Stoynev, S., Tartaglia, M.. 2023-10-05. Fermilab’s horizontal test stand upgrade overview and commissioning. https://doi.org/10.2172/2008065
Cite the original work for its findings. Save a collection to share your selection of sources.