Component level modeling of materials degradation for insights into operational flexibility of Existing Coal Power Plants

Increasingly, coal-fired power plants are required to balance power grids by compensating for the variable electricity supply from renewable energy sources. Fossil-fueled power plants, originally designed to be base loaded, will increasingly need to operate on a load following or cyclic basis. This demanding requirement for operational flexibility needs insights into accelerated material degradation arising due to the harsh operating conditions (e.g., fatigue, early oxide exfoliation due to stresses) along with current damage mechanisms (fireside corrosion, creep and erosion) observed in service. Our research objective is to develop component level modeling toolkit for materials-based degradation for two key mechanisms that can accelerate with cyclic operations. In more detail, this includes the fireside corrosion/steam oxidation/erosion/creep/fatigue of superheaters/reheaters and steam pipework and also the water droplet erosion/ fatigue of last stage steam turbine blades degradation mechanisms, that demand routine and sometimes unplanned maintenance and repair. The innovation is in developing a computational fluid dynamics/finite element (CFD/FE) modeling toolkit for the component level models of the boilers and low-pressure steam turbines in coal power plants that can tackle multidisciplinary failure mechanisms occurring concurrently for extreme environment materials. Lifetime assessment in such environments also needs to account for the unit-specific analyses, operational history and fuel feedstock; this can only be obtained by destructive analysis of components. This, in turn, enables validation of the model toolkits utilizing service feedback data, improving the probability of time/temperature dependent life prediction.

20 FOSSIL-FUELED POWER PLANTS↗

Evaluation of Doped-LaCrO3 ceramics for high temperature sensor applications

The main objective of this work was to investigate the applicability of the doped-LaCrO3 system for electrical interconnects and sensor applications at temperatures >800°C. Various A- and B-site doping strategies were investigated, and the effect on their electrical conductivity, Seebeck coefficient, and thermal coefficient of expansion were characterized up to 1500ºC. Solid-state, co-precipitation and sol gel methods were used to synthesize the compositions, and the chemical/thermal stability, microstructural evolution, sintering and grain growth kinetics were investigated for these compositions by XRD, SEM and Rietveld methods. The materials showing the greatest promise were included within thick film thermistor and thermocouple sensor designs that were tested to 1500ºC in various gas environments (various pO2 concentrations).

20 FOSSIL-FUELED POWER PLANTS↗

Optimization of Operating Profit for the FEED of the PZAS Process for CO 2 Capture on a 460 MW NGCC

A rating model of PZAS (Piperazine with the Advanced Stripper) for a 460 MW natural gas combined cycle was developed from vendor-provided equipment performance data. Surrogate rating models were built and used to optimize variable profit of the system subject to natural gas and electricity price at a fixed value for CO 2 of $\$80$/tonne. Several process constraints were considered between ambient temperatures of 4.4 and 40.5 °C. Lower lean loading resulted in lower reboiler heat duty of about 2.2 GJ/tonne. Lean loading at 0.2 mol/equiv N was sufficient at an ambient temperature of 4.4 °C to maximize variable profit. Solvent precipitation was avoided even at low lean loading (0.18 mol/mol) in the absence of a trim cooler for the lean solvent between the absorber and the cold cross exchanger. Optimal CO 2 removal was always higher than the design case removal of 90% and achieved a peak of 93.6% for 4.4 ºC ambient temperature. Lean solvent rate was a significant driver of profitability. The maximum capacity of the compressor was a significant constraint on profitability. Increasing compressor capacity by 20–30% could increase variable profit by about 21% in the case of 0.18 lean loading at 4.4 °C ambient temperature. Furthermore, this increase in profit was lower at higher ambient temperature and higher lean loading. The breakeven gas price was $\$4.6$/MMBtu at high lean loading of 0.22 mol/mol. Below this value, profit was maximized by increasing the boiler heat rate. Above this value, profit could not be increased by burning additional natural gas, requiring a reduction in boiler heat rate and consequently, specific heat duty. At lower lean loading (0.2, 0.18 mol/mol), this transition in heat duty was not observed due to the lower heat duty. As the ambient temperature increased, a similar trend in heat duty was observed at 0.22 lean loading, but the transition to lower heat duty occurred earlier at $\$4$/MMBtu. This was because of the lower CO 2 production at higher ambient temperature, making the process unprofitable at a gas price higher than $\$3$/MMBtu unless the heat duty of the stripper and natural gas boiler is steeply decreased.

37 INORGANIC, ORGANIC, PHYSICAL, AND ANALYTICAL CH↗

Fitness-for-Service Analysis of Reactor Components under Flexible Load-Following Operating Conditions

Conventional power-generation plants, including nuclear plants, have been traditionally designed to provide a steady baseload energy capacity, optimizing output efficiency while minimizing variable costs. However, the growing adoption of large-scale renewable energy-generation systems, which rely on intermittent sources such as solar and wind, has introduced more variability into the energy supply in interconnected electricity grids. As a result, the next generation of power plants needs to operate in what is known as the load-following mode, requiring flexible adjustments in electricity production to align with the energy demand on the grid. This transition from the steady baseload operation to load-following operating conditions can significantly increase the number of times various plant components are exposed to transient stresses. This increased thermo-mechanical cycling can lead to accelerated material degradation, thereby elevating the risk of premature failure of a component. It becomes imperative to conduct a comprehensive analysis of fatigue, creep-fatigue, and stress corrosion cracking life, to assess the resilience of the various engineering components under these flexible load-following operating conditions. This study aims to develop a comprehensive numerical model of a light-water reactor pressure vessel (RPV) to investigate its degradation under various operating scenarios. This coupled thermo-mechanical finite element analysis evaluated the stress response of the RPV caused by considering fluctuations in thermal and mechanical loads caused by the varying pressure and temperature occurring during the load-following operation. Critical locations on the RPV are subsequently identified based on the stress response. The stress intensity factors for the postulated flaws at those locations are then calculated, followed by an evaluation of the reactor's life in accordance with the ASME Boiler and Pressure Vessel Code Section XI. This comprehensive life assessment covers a number of transients expected during the flexible load-following operation, providing invaluable insights into the RPV's structural integrity. Moreover, the development methodology can be adapted to other reactor components, as well as components of conventional power stations that are affected by varying operating conditions.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Oxide Semiconductor Sensors for Monitoring Advanced Energy Conversion and Manufacturing Processes at High Temperature

To optimize the operation and functionality of high temperature systems such as slagging gasifiers, coal boilers and glass/steel smelters, it is important to monitor temperature, corrosion and erosion of the refractory used in such systems. Both thermocouple and failure sensors (and arrays of these) would be useful to monitor the health of any refractory or coatings in these systems. Many of such type of sensors are installed into the systems through open access ports within the refractory; however, there are some disadvantages of this approach where corrosive/erosive gas and molten materials can penetrate and compromise the system. The current work presents the development and performance of refractory with embedded high temperature sensors such as thermocouples, thermistors, and various spallation/crack monitoring sensors, which may be used within a variety of refractory brick in different high temperature processes and applications. The objective of our work is to develop high-temperature sensors composed of electroceramic materials that are chemically stable at high temperatures (750°-1500°C) and high pressures (up to 1000 psi) that can be used in monitoring temperature, corrosion and erosion process in refractory used in high energy systems. The high-temperature sensors investigated in this work were composed of various oxide composites directly embedded into the refractory oxides. The composites used for this work were synthesized by a mixed-oxide route. Metal oxides were inserted within a matrix material composed of refractory oxides (Al2O3, ZrO2, etc.). The physical and electrical properties were specifically manipulated by altering the level of percolation of the conductive species (metal oxides) within the refractory constituent (refractory oxide). An example of one of these embedded sensors consisted of an electroceramic-based thermocouple fabricated with two separate oxide composite compositions which were patterned to produce a couple within the interior of a refractory matrix. The thermocouple successfully displayed thermoelectric voltage trend (as a function of temperature), and the voltage was 220.0 mV near 1400 °C. In addition, corrosion tests on the refractory embedded sensors were performed. To evaluate corrosion in the refractory was exposed to high-temperature glass compositions over a 90 h period. The penetration of the glass through the refractory could be monitored by both an amperometric and voltametric based sensor. With this experiment, it was demonstrated that the embedded sensor could dynamically monitor the corrosion process, and thus, provide real-time feedback on both temperature and the refractory health.

20 FOSSIL-FUELED POWER PLANTS↗

Front-End Engineering and Design: Project Tundra Carbon Capture System (Final Report)

As the next phase of Project Tundra, Minnkota Power Cooperative (MPC) completed a front-end engineering and design (FEED) study to install a post-combustion CO 2 capture system (CCS) at the MPC operated (Square Butte Electric Cooperative-owned) Milton R. Young Station (MRYS) Unit 2 (MRY2), a 477-MW power plant fueled by North Dakota lignite. The project team completed the FEED with Fluor’s Econamine FG Plus℠ (EFG+) technology and is taking the next steps leading up to start of construction. Team members included FEED technical lead Fluor Enterprises (Fluor); owner’s engineer and balance of plant (BOP) engineer Burns & McDonnell (BMcD); leading carbon capture consultants (David Greeson Consulting, Hunt International Energy Services); environmental consultants (AECOM, Agora Environmental), other BOP engineering consultants (Golder Associates, Nels); cost-share funding agency, the North Dakota Industrial Commission (NDIC); and the Energy & Environmental Research Center (EERC). Project Tundra’s goal is to implement carbon capture, utilization, and storage (CCUS) in North Dakota, while preserving the use of lignite. Future options could lead to revitalizing legacy oil fields and creating a new CO 2 enhanced oil recovery (EOR) industry. The topic of this report is the FEED study for the carbon dioxide capture portion of Project Tundra. Building on the findings of a pre-FEED study for MRY2, the key deliverables contained in this FEED study are: a) design, costing, and performance data needed to commence project financing activities; b) engineering and material balances required to file for all project permits; and c) a final project schedule. Based on the results of the previous pre-FEED study, MPC and its team evaluated two options to provide the large amount of steam needed to operate the CCS: 1) installation of new natural gas package boilers and a new pipeline to supply natural gas to the facility and 2) extraction of steam from the existing MRYS steam turbine generator. The FEED study was performed using the package boilers option, as it was deemed to have the lowest technical risk, overall cost, and cost uncertainty. A key feature of the design, however, was the mixing the natural gas boilers’ flue gas with the MRY2 flue gas. This increased the size of the CCS system. This design also enabled the tie-in of Unit 1 flue gas for times when Unit 2 is offline. The CCS was designed to capture a combined 12,978 short tons per day (STPD) of CO 2 from the flue gases produced by the existing MRY Unit 2 along with flue gas produced by the new boiler package within the CCS. The 12,978 STPD CO 2 capture is achieved by normally processing 100% of the total available MRY Unit 2 flue gas (considering full load operation) and 100% of the boiler package flue gas, then removing 90% of the CO 2 available from the processed flue gas streams.

01 COAL, LIGNITE, AND PEAT↗

Direct Air Capture of CO 2 and Delivery to Photobioreactors for Algal Biofuel Production (Final Report)

A mobile DAC system was designed and constructed to pair with photobioreactors growing algae for biofuel production. The DAC system was designed as a versatile research system, rather than a compact production unit. The system was constructed and mounted on a mobile skid to facilitate transportation to the algae production site. Within the DAC system, CO 2 was captured using amine-loaded monoliths that allow for high CO 2 uptake with low pressure drop. The CO 2 is collected using a Global Thermostat patented temperature/vacuum swing adsorption (TVSA) process. Amine sorbents and process conditions were optimized to produce 10 to >20 g CO 2 .h-1. The stability of the amine sorbents was also studied, with sorbent modifications made to improve stability to degradation by oxidation. An Algenol-developed Spirulina strain (Arthrospira platensis AB2293) was selected as the production cyanobacterial strain. AB2293 cultured was inoculum for outdoor production following PBR installation by Algenol. The PBR system was composed of three independent PBRs, with each PBR composed of four hanging bags internally recirculated by a liquid turnover pump. The PBRs were operated outdoors in Atlanta, GA, and integrated with the DAC system. Algae were grown with similar productivity using DAC-CO 2 as algae grown using pure CO 2 obtained commercially (Airgas). Throughout the experimental duration, no discoloration was observed, and cellular morphology was consistent between the two experimental treatments. An LCA including lifecycle greenhouse gas emissions, full life cycle inventory of the Algenol system and the DAC system and integrated DAC+PBR system was developed. Lifecycle greenhouse gas emissions were calculated for capture of carbon dioxide using input from Global Thermostat and the National Renewable Energy Laboratory. Three scenarios for energy provision were evaluated: a natural gas combined heat and power system sized to meet the electricity requirement, a natural gas combined heat and power system sized to meet the process heat requirements, and a system without on-site power that procures the electricity from the grid. In all three cases, as expected, the major contributor to the emissions is the energy consumption associated with the desorption step of the DAC process. The LCA quantified the reduced potential energy and greenhouse gas emissions of heat and mass integration of DAC and Algenol compared to unintegrated DAC and Algenol systems. A life cycle assessment of the role of sorbent productivity and lifetime was also developed. The development of more robust, oxidation resistant DAC sorbents may enable small reductions in energy requirements and in lifecycle greenhouse gas emissions and other environmental impacts. NREL performed techno-economic analysis (TEA) to identify the integration scenario most likely to achieve a 15% cost reduction target versus the baseline. Heat and mass integration of DAC and the PBR is critical to minimizing the MFSP. The baseline case utilizes no heat and mass integration, and the DAC system provides 100% of the CO 2 required by the photobioreactors (20 tonnes/hr), operating for 12 hours/day capturing 40 tonnes CO 2 /operating hour. The minimum fuel selling price (MFSP) of ethanol calculated from the baseline case was $10.68/gal ethanol. This corresponds with a targeted MFSP of $9.07/gal ethanol (or 15% reduction). This target was achieved by integration Option 2a with the greatest cost reduction of 17.8% (or $8.78/gal) and integration Option 2b with a cost reduction of 16.4% (or $8.93/gal). Reductions in MFSP are attributed to two primary process considerations: (a) CO 2 storage at night reduces the capital expenses associated with DAC (i.e., increasing on-stream time); and (b) distributed DAC scenarios (DAC-PBR integration Options 2a and 2b) make use of boiler and DAC CHP flue gas CO 2 (free). Direct air capture on-stream time was one of the largest contributors to MFSP reduction.

09 BIOMASS FUELS↗

Smart Refractory Sensors Development for Corrosion and Erosion Monitoring in High Temperature Systems

To optimize the operation and functioning of high temperature systems such as slagging gasifiers, coal boilers and glass/steel melters, it is important to monitor corrosion and erosion of refractory used in such systems. Corrosion test strategies are generally based on continuous gravimetric and chemical reactivity monitoring at operational temperatures (750°-1500°C). Both thermocouples and failure sensors and arrays would be useful to monitor the health of any refractory or coatings in these systems. Many of such type of sensors are installed into the systems through open access ports within the refractory; however, there are some disadvantages of this approach where corrosive/erosive gas and molten materials can penetrate and compromise the system. The current work presents the development and performance demonstration of smart refractory with embedded high temperature sensors such as thermocouples, thermistors, and various spallation/crack monitoring sensors, which may be used within a variety of refractory brick in different high temperature processes and applications. The main feature of this technology is that electroceramic based sensors are embedded into smart refractory without significantly impact to the intrinsic properties of the refractory. This technology circumvents the need to insert an isolated monolithic, stand-alone sensor into the refractory via an access port. This technological approach guarantees the integrity and the chemical stability of the materials used in the sensor fabrication within the harsh environment and does not introduce molten material (such as slag) penetration pathways within the refractory. One interesting and important aspect of this innovation is that these embedded sensors can be used to in situ monitoring processes such as chemical reactions and at the same time give information and a deeper understanding of the corrosion and erosion process of the refractory within the system. As stated above, the objective of our work is to develop high-temperature sensors composed of electroceramic materials that are chemically stable at high temperatures (750°-1500°C) and high pressures (up to 1000 psi) that can be used in monitoring corrosion and erosion process in refractory used in high energy systems. The high-temperature sensors investigated in this work were composed of various oxide composites directly embedded into the refractory oxides. The composites used for this work were synthesized by a mixed-oxide route. Metal oxides were inserted within a matrix material composed of refractory oxides (Al2O3, ZrO2, etc.). The physical and electrical properties were specifically manipulated by altering the level of percolation of the conductive species (metal oxides) within the refractory constituent (refractory oxide). Prior to the development of the high-temperature sensors, the oxides composites developed in this study were sintered up to 1600°C under oxidizing atmosphere in order to investigate densification, microstructural evolution, phase development, and their thermoelectrical performance as a function of the composition. The 4-point DC conductivity measurements were performed between 100°-1500°C. The sensors were fabricated from the composite materials by 3D-printing or screen-printing methods into the refractory brick during the consolidation process. An example of one of these embedded sensors consisted of an electroceramic-based thermocouple fabricated with two separate oxide composite compositions which were patterned to produce a couple within the interior of a refractory matrix. The thermocouple successfully displayed thermoelectric voltage trend (as a function of temperature), and the voltage was 220.0 mV around 1400 °C. Corrosion tests on the refractory embedded sensors were performed. To evaluate corrosion in the refractory brick an in-house glass composition was prepared and pressed into pellets and delivered into a pre-cut cavity in the brick. Corrosion experiments results showed the glass penetrated the brick over a 90 h period, and the penetration of the glass through the brick could be monitored by both an amperometric and voltametric based sensor. With this experiment, it was demonstrated that the embedded sensor could dynamically monitor the corrosion process.

20 FOSSIL-FUELED POWER PLANTS↗

Front-End Engineering Design for Piperazine with the Advanced Stripper

This Department of Energy (DOE) funded project was executed with the goal of preparing a Front-End Engineering Design (FEED) for the capture and compression of 90% of the CO2 that would normally be emitted from an existing natural gas combined cycle (NGCC) plant. The FEED focused on the application of the piperazine advanced stripper (PZAS) process at Mustang Station of the Golden Spread Electric Cooperative (GSEC), which consists of two gas turbines with common heat recovery steam generator (HRSG). The University of Texas at Austin (UT) served as the prime contractor, and subcontracted AECOM Technical Services and Trimeric Corporation to support FEED development. This project team has worked together to advance PZAS for more than a decade. ExxonMobil, Chevron, and Total provided project co-funding. The objectives of this work included: 1. To advance engineering design such that a comprehensive estimate for the total installed cost of a full-scale PZAS CO2 Capture Plant with CO2 compression can be developed on an existing NGCC power plant. a. These detailed costs can also be used to qualify PZAS and other related second generation (2G) amine scrubbing processes for use on cogeneration facilities in refineries and chemical plants that use gas turbines with HRSGs to produce steam. b. These detailed costs will help qualify 2G amine scrubbing for use on NGCC power plants and establish a more accurate baseline cost to be used as a target by other capture technologies. 2. To provide cost details to be used in the economic optimization of the process features of PZAS and other 2G amine scrubbing processes. 3. To provide DOE with a more detailed understanding of carbon capture costs in a commercial application, enabling DOE to better design its R&D program to improve the economics for carbon capture. 4. To provide the host site and cost share partners with the information necessary to determine whether a commercial project to capture and use CO2 for enhanced oil recovery (EOR) or for sequestration can be justified (when accounting for the 45Q tax credit). A key component of the FEED is the estimated total installed cost, which provides a basis for the likely capital investment necessary to implement the PZAS carbon capture process at this location and scale. In combination with the included economic analysis, which accounts for potential revenue from the produced CO2, potential avenues to profitability are explored. The major findings of the FEED are as follows: The Mustang Station PZAS CO2 Capture Plant estimated total project cost of $698 MM of which $384 MM was direct costs. The annual operating costs were $32.6 MM. The total investment for a PZAS facility at Mustang Station is $725 MM. This estimate includes owner’s cost of $25 million and a contingency of $110 MM. • The study estimated the CO2 capture plant at Mustang Station would generate CO2 at $110/tonne for EOR, assuming a 12% IRR (internal rate of return) and an 85% capacity factor. For CO2 storage, the same case would achieve a 12% IRR at about $114/tonne. At a capacity factor of 52%, the storage and EOR cases would break even when carbon is priced ~$150/tonne. The economic analysis determined that the capacity factor and utility pricing, among other variable factors, had a significant effect on the economics and will need additional studied. • The energy penalty of the PZAS plant would be about 46 MW in connected power and 35 MW in operating load. The natural gas requirement (for the Gas Boiler package) would be about 354 MMBTU/hr. • The FEED revealed no major risks in process maturity. However, some areas were outlined for further engineering during detailed design, which included the Gas Boiler system, general arrangement and site layout, air coolers, schedule development, and optimization of the process for higher CO2 removal. • If PZAS were to be implemented at another host site, additional opportunities for cost reduction for would include cost reduction through use of cooling water and steam extraction.

03 NATURAL GAS↗