Search indexed NASA NTRS and DOE OSTI research on propulsion, heat transfer, battery materials and energy systems. Follow report and document links to the original sources.

Quote a phrase for an exact phrase match. Source license links do not imply unrestricted reuse.

At least 19 records

Review of Potential Wigner Effect Impacts on the Irradiated Graphite in Decommissioned Hanford Reactors

This review of is motivated by the need to consider future disposal of the nine surplus Hanford Site production reactors (B, C, D, DR, F, H, KE, KW, and N) that are decommissioned as part of the Hanford Site Composite Analysis. The B Reactor has been designated as a museum. The other eight reactors will be evaluated in a future performance assessment before a final disposal facility can be authorized to construction or to receive this waste form. After a performance assessment is available, then the Hanford Site Composite Analysis would be updated to account for this additional source term. Disposal is currently assumed to occur in calendar year 2070 by one-piece removal to a projected disposal facility in the 200 West Area of the Hanford Site Central Plateau. The N Reactor core may also be disposed analogously to the single-pass reactors. It will further assume that the B Reactor will remain a museum permanently. The U.S. Department of Energy studied at least five decommissioning alternatives for long-term, safe management of radionuclide-contaminated materials inside the eight single-pass reactors (DOE/EIS-0119-FEIS, Decommissioning of Eight Surplus Production Reactors at the Hanford Site, Richland, Washington).

11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS↗

Special Considerations for the Removal and Disposal of Micro-Reactor Experiments

Idaho National Laboratory (INL) is preparing to host several microreactor experiments through 2030 and beyond. Two new test beds currently under development will operate as microreactor or nuclear system experiment user facilities. Test bed experiments will be performed in series, with each nuclear experiment installed, operated, and removed before installation of the subsequent experiment. The necessarily brief transition period between experiments introduces unique equipment removal and radioactive waste disposal challenges. This paper evaluates equipment removal and radioactive waste management topics associated with tight sequencing of nuclear experiments and presents some of the solutions and approaches currently planned to meet these special considerations for one such experiment, the Molten Chloride Reactor Experiment (MCRE), slated for operation at INL’s Laboratory for Operation and Testing in the United States (LOTUS). The MCRE project is a collaboration between Southern Company Services, TerraPower, and INL, among others, to provide integral nuclear data that will advance molten salt fast reactor technology. MCRE will be the first critical fast-spectrum circulating fuel system ever operated and the first experiment operated in the LOTUS test bed. The experiment will nominally operate at zero power with planned low power excursions as part of operational planning for MCRE has been to minimize at-power operations to limit fission product formation while still achieving experimental objectives. After the experiment is complete, MCRE will be allowed to radioactively decay for a short period (nominally 90 days) prior to system defueling, flushing, removal, and disposal of all MCRE equipment, readying the test bed for the next nuclear experiment. Equipment removal and radioactive waste disposal have been integral to MCRE project planning since the Cooperative Research and Development Agreement was formalized in 2021. Due to requirements for future use of the test bed, the MCRE system, of necessity, must be removed in a much shorter time frame than typical for historic reactor decommissioning projects at INL. This results in minimal time for radioactive decay, resulting in not only elevated radiation dose rates but also the presence of short-to-medium-lived isotopes not typically encountered in the reactor decommissioning and radioactive waste management space. Additional unique constraints placed on the project include lack of intrinsic remote-operations capabilities in the test bed, space constraints in the test bed once MCRE has been installed, and contamination minimization requirements to return the test bed to as-found conditions to enable future use. This paper discusses planned solutions to these challenges. Approaches for implementing remote or semi-remote technologies in a non-hot cell environment with limited space availability are discussed. The paper also summarizes the systems engineering approach for concept development and design of equipment removal systems, which are being implemented concurrent with the MCRE design phase, providing feedback to system designers to incorporate features enabling efficient and safe equipment removal approaches. The timing of this paper at a relatively early phase of the project is meant to highlight the importance of early planning for nuclear system decommissioning while reactor design is ongoing to allow design feedback on componentry driven from decommissioning system needs. As new, innovative nuclear reactor technologies enter the nuclear market sector, reactor experiments are crucial for providing new integral nuclear data that establish safe operational margins for technology advancement. Microreactor experiments at INL will require safe, effective, and timely decommissioning approaches, which in turn require nuclear systems designed to expedite decommissioning. In addition to the advancement of nuclear reactor technologies, these nuclear experiments provide an opportunity to demonstrate, deploy, and test new removal and disposal capabilities to support the next generation of nuclear reactor technology.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Decommissioning of the V1 Nuclear Power Plant Jaslovske Bohunice - 20270

The paper focuses on introducing the approach and method applied for decommissioning of the V1 nuclear power plant (further the 'V1 NPP') located in Jaslovske Bohunice in the Slovak Republic, to the conference participants. The Paper outlines activities and steps necessary to comply with the requirements contained in the decision of the Slovak government from 1999 regarding the early shutdown of the V1 NPP. The company responsible for the V1 NPP decommissioning is Jadrova a vyradovacia spolocnost, a.s., (further JAVYS) with the State as a sole shareholder. On the basis of the V1 NPP Decommissioning Conceptual Plan, out of four assessed options, JAVYS selected the immediate decommissioning option (the 'IDO') for the V1 NPP. On the basis of multi-criteria analysis, the IDO specified the approach of immediate and continuous dismantling of equipment followed by demolition of buildings and preparation of the site for its further potential use. The IDO also included the summary of technical, environmental, legislative information as well as the determination of assumed costs for decommissioning of the V1 NPP. Prior to commencement of the V1 NPP decommissioning, within the process of termination of operation, activities connected with de-fuelling, monitoring, processing of historical waste and, not to forget, the process of obtaining the license for the V1 NPP decommissioning were executed. JAVYS decided to divide the decommissioning process into two stages. In 2011, JAVYS obtained a license for the first stage of the V1 NPP decommissioning. Within this stage, dismantling of inactive equipment, demolitions of inactive buildings, monitoring of systems and preparatory works for the upcoming stage of decommissioning were implemented. In 2015, in line with the license for the 2. stage of the V1 NPP decommissioning, the activities of decontamination and dismantling of contaminated and active equipment as well as demolitions of remaining buildings began. In this stage radioactive waste (RAW) produced during the decommissioning is to be processed. After decontamination, the material fulfilling the free release criteria is to be released into the environment, the site is to be cleared from the scope of the Atomic Act and released from the surveillance of the national regulators. Future application of certain methods and techniques for decontamination and dismantling in similar environments might bring an added value to the operators. Paper includes a description of best practices for Nuclear Power Plant VVER type reactors decommissioning. Schedule comparison is given to show how the critical path of certain projects is being managed. Application of the International Standard for Decommissioning Costing (ISDC) methodology provides a uniform method which enables comparison of cost estimates to other nuclear facilities under decommissioning. The cost estimate for the V1 NPP decommissioning has been continuously updated based on more advanced and detailed information on the decommissioning activities and projects. Monitoring of progress of the V1 NPP decommissioning is performed via four key-performance indicators. The Earned Value Management (EVM) methodology is used for evaluating time and cost aspect of decommissioning activities while waste conditioning index is calculated by comparing the actually produced waste to planned values of waste for a respective monitored period. Radiological safety index is assessed by comparison of the personnel records on the individual yearly doses received by each respective employee to the boundary value. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Crack Growth Rate and Fracture Toughness of Stainless Steel Welds in Light Water Reactor Environment

Austenitic stainless steel welds play a crucial role in maintaining the structural integrity of light water reactors. Within the reactor core, stainless steel welds endure a harsh service environment including elevated temperature, corrosive coolant, and intense neutron irradiation. Long-term exposure to such a severe service environment could lead to performance degradation. To ensure the safe and economic operation of light water reactors, this study performed crack growth rate and fracture toughness tests on irradiated and thermally aged weld samples harvested from decommissioned reactor components. In a low-corrosion-potential environment, stainless steel welds showed resistance to stress corrosion cracking, and the measured crack propagation rates were comparable to those of wrought stainless steels under similar test conditions. However, a marked decline in fracture toughness was observed in weld samples, particularly in irradiated samples. Fracture instability was observed at ~0.8 dpa, significantly lower than those observed in wrought stainless steels. Further research at higher doses is needed to evaluate the dose dependence of irradiation-induced embrittlement, and to understand the interplay between thermal aging and neutron irradiation in stainless steel welds.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

Cracking Behavior of Irradiated Ex-Plant Materials

The cracking behavior of reactor core internal materials is a key factor for the long-term safety and availability of light water reactors. Subject to high-temperature coolant, thermal and mechanical loading, and neutron irradiation, reactor core internal materials are susceptible to several degradation mechanisms during power operation. To understand the long-term effects of neutron irradiation, irradiated materials harvested from a decommissioned reactor were studied for their cracking susceptibility and fracture resistance. Small compact-tension specimens were machined from different locations on the baffle plates with irradiation doses ranging from 0.06 to 48.5 dpa. Crack growth rate and fracture toughness J-resistance (J-R) curve tests were performed on these specimens in a simulated light water reactor environment, and the fracture morphologies of the tested samples were examined with a scanning electron microscope. All samples behaved similarly under cyclic loading, and no deteriorated corrosion-fatigue behavior was observed in the test environments. Under constant load, no elevated cracking susceptibility was observed either in these samples at low stress intensity factors. However, a rapid cracking behavior featuring very high crack growth rates was observed in several high-dose samples. This rapid crack growth behavior was activated when the applied stress intensity factor, K, was sufficiently high. Once activated, the rapid crack growth remained steady even when the K was lowered to the pre-activation level and stopped only when the K was reduced drastically. Yet, the rapid crack growth could be re-activated repeatedly in these samples by raising the K above the initial activation level. This rapid cracking response may be related to the severe irradiation embrittlement experienced by these samples. The J-R curve tests performed with these samples showed a significant decline in fracture toughness with increasing neutron irradiation. Local cracking at the crack tip facilitated by the severe irradiation embrittlement of this material may be responsible for the rapid crack growth behavior demonstrated by this decommissioned material.

36 MATERIALS SCIENCE↗

Validation Testing for Molten Chloride Reactor Experiment Equipment Removal and Disposal Techniques

The Molten Chloride Reactor Experiment (MCRE) will be the first reactor featuring a fast-spectrum molten chloride circulating nuclear fuel system in the world. Planning for equipment removal and disposal (ERD) of MCRE has identified several technology gaps due to the unique environment of this nuclear experiment. Some of the gaps arise from the application of existing disassembly and/or sizing methods to novel material forms or in novel configurations. Others arise from unknown material behavior. This paper summarizes proposed test plans for ERD validation experiments to address these complicated or unknown equipment removal procedures. At the Waste Management Symposia in 2024, the Idaho National Laboratory (INL) MCRE ERD team presented the challenges associated with hosting multiple nuclear experiments in series with only brief transition periods between systems. Such difficulties include higher dose rates, the presence of radioisotopes infrequently encountered in reactor decommissioning and radioactive waste management, lack of intrinsic remote-operations infrastructure in the test bed, space constraints in the test bed, and contamination minimization requirements. To address these challenges, remote or semi-remote technologies are planned to be implemented in a non-hot cell environment with limited space availability. The team also discussed how a systems engineering approach is being used for conceptual development and design of equipment removal systems to address these challenges. For example, to reduce constraints for the removal of more difficult components, non-activated, noncontaminated elements are planned to be taken out first where possible. Still, there are complexities associated with the remaining components. In this work, the operational framework for MCRE ERD was reviewed for technical gaps and open questions, and test plans were drafted to address these areas. The tests plans were written for the following categories: vision systems, pipe cutting, drill/grout/filler, flush salt, and miscellaneous, with the miscellaneous group consisting of tests like techniques for removing bearings and reflector bricks. The test plans explore material, infrastructure, and staffing requirements needed for test execution. The test plans additionally focus on the evaluation of success. Determining the outcome of a test is imperative - as these explorative actions have the potential to rearrange or re-scope planned ERD activities. Success criteria identified thus far include required tool output, required area(s), debris production and mitigation, and repeatability. Test plans are an essential aspect of the systems engineering approach to MCRE ERD. They are used as the beginning steps in defining use cases for the ERD system. Performance of the validation tests is expected to begin in the summer of 2025 and will take approximately 9 to 12 months to complete. Execution of these plans will be expedited by specifying test needs ahead of time, facilitating efficient interactions with any subcontractors tasked with running the requested tests. Evaluating the outcomes of these tests will inform MCRE ERD procedures and timing and will also identify additional technical constraints for the MCRE ERD System. This upfront process optimization effort will help the project save time and resources at the end of the experiment.

21 - SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLAN↗

Inspection Status Report of Site A/Plot M (Report for 2020)

The Site A/Plot M, Decommissioned Reactor Site was inspected on September 24, 2020. Site A/Plot M is located in the Palos Area Preserves, operated by the Forest Preserve District of Cook County. The site was found to be in good condition with minimal erosional concerns across the grass covered mound at Plot M. Landscaping timbers installed along the footpath north of Plot M is effective in reducing erosion down the hill. Erosion concerns at Plot M are being addressed by Argonne National Laboratory (ANL). The bike trail installed by Cook County Forest Preserve to the east of Plot M has helped reduce traffic at the site. The Plot M monument appears solid with no visible cracks. The Site A monument has several cracks present that will possibly widen over time. No cause for a follow up inspection was identified.

54 ENVIRONMENTAL SCIENCES↗

Inspection Status Report of Site A/Plot M Report for 2023

The Site A/Plot M Decommissioned Reactor Site was inspected on June 6, 2023. Site A/Plot M is in the Palos Area Preserves, operated by the Forest Preserve District of Cook County. The site was found to be in good condition with negligible erosional concerns across the grass covered mound at Plot M. Landscaping timbers installed along the footpath of Plot M have been effective in reducing erosion down the eastern slope, thus, no additional timber steps are needed at this time. The bike trail, installed by Cook County Forest Preserve, located to the south and east of Plot M has helped to significantly reduce traffic at the site. The Site A and Plot M monuments were both replaced on May 1, 2021, and remain in good condition, despite a small amount of graffiti observed on both monuments at the time of the inspection. The 19 groundwater monitoring wells at Site A/Plot M were found to be secure and in good condition.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

D and D Research on KM-IT Platform - 20494

The Knowledge Management Information Tool (KM-IT) is a web-based system developed to maintain and preserve the Department of Energy's (DoE's) knowledge base. The system was developed by Florida International University's Applied Research Center (FIU-ARC) with the support of the D and D community including the DOE Office of Environmental Management, and with the collaboration and support of the DoE's Energy Facility Contractors Group (EFCOG) and the former ALARA Centers at Hanford and Savannah. The KM-IT system is a community driven system tailored to serve the technical issues faced by the workforce across the DOE Complex. This KM-IT web-based interactive system is operational and available for use at www.dndkm.org and is currently comprised of the following modules: Web Crawler, Hotline, Technology, Hanford's ALARA Center Reports, Specialist Directory, Lessons Learned, Best Practices, Video/Picture Library, Vendors and Industry News. The Web Crawler dynamically searches through the KM-IT repository as well as the web and displays search results based on the search criteria. The Hotline allows registered users to post questions/problems related to D and D and to receive solutions from a subject-matter specialist. The Technology module serves as repository of D and D technologies and contains technology/ demonstration fact sheets and vendor information. D and D community members can add Lessons Learned, Best Practices, and Pictures/Videos to the D and D repository, after a formal approval process. The Vendor module provides a directory of commercial vendors who provide D and D related technologies, supplies, and services. KM-IT makes an excellent use of the knowledge that exists within the D and D community by allowing D and D project managers around the DOE complex to collaborate by sharing innovative ideas, past experiences, and practices and by maintaining a directory of subject matter specialists. FIU has developed the dedicated module on KM-IT platform to publish D and D research being performed at FIU. This module highlights current EM research efforts and activities in support of D and D being performed at FIU/SRNL associated with fixatives and intumescent products. FIU will expand this module to include the recent and current D and D research being performed across multiple DOE EM sites, national labs and universities. FIU will collaborate with SRNL, INL, ANL and other universities to explore and publish D and D research activities on KM-IT. As a result, the user community will have a centralized location to review new D and D related research across the DOE EM complex. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Is there a Perfect D and D Plan - 20100

Problems with many Deactivation and Demolition (D and D) projects arise not necessarily from the technical difficulty of the actions required in a given facility, but rather from lack of integration of the stove piped planning efforts; engineering, operations, environmental, radiological, human resources, etc. This paper will cover Polestar Technical Service, Inc. (Polestar) systems engineering approach to D and D planning based on the company's experience over the past 27 years. This systematic, four-pronged approach to planning is applicable to any D and D project and addresses several diverse topics in a cohesive and integrated manner. The four areas to be discussed are project scope, requirements, facility end state, work force and base operations. This approach progresses a facility through the typical DOE life-cycle from operations, through deactivation, into surveillance and maintenance (S and M) and to eventual demolition and site remediation. To achieve a final end state the approach brings together the efforts associated with identifying and managing the right set of requirements, detailing the scope of work, establishing the baseline, redefining the work processes, aligning the workforce resources with the work processes, and maintaining the base operations activities as the project progresses through the various life-cycle stages. Getting these building blocks right provides a solid framework for executing any D and D project. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Initial Progress on Tank Bottom Repair for the DOE EM Tank Waste R&D Program - 25089

Several years prior to the Lab23-EM001 Call Announcement, Washington River Protection Solutions (WRPS) had done a review in identifying tank repair feasibility. [1, 2] The most viable methods of repair identified for the Floor of a Primary Tank identified were Grout Stabilization and Polymer Grout. Grout Stabilization was described as a self-leveling grout which fills the entire bottom of the tank and creates a new or false bottom. These types of materials have been used at the Savannah River Site (SRS) to fill and close waste tanks as well as contaminated spaces within decommissioned reactors. No mention was made as to the chemical composition of these Stabilizing Grouts in the review, however, grouts used at SRS for the mentioned applications have always been a cementitious grout material. A thickness of approximately 12 inches was suggested in the review. It was also suggested that an additional polymeric coating could be applied to this fresh and clean grout surface.

BLUE, KAREEN↗

Nuclear Safety [Vol. 37, No. 2, April-June 1996]

Nuclear Safety is a journal that covers significant issues in the field of nuclear safety. Its primary scope is safety in the design, construction, operation, and decommissioning of nuclear power reactors worldwide and the research and analysis activities that promote this goal, but it also encompasses the safety aspects of the entire nuclear fuel cycle, including fuel fabrication, spent-fuel processing and handling, and nuclear waste disposal, the handling of fissionable materials and radioisotopes, and the environmental effects of all these activities. Table of Contents for this issue follows. GENERAL SAFETY CONSIDERATIONS: 97 The Nuclear Community and the Public: Cognitive and Cultural Influences on Thinking About Nuclear Risk, M. A. Meyer; 109 Twenty-Third Water Reactor Safety Information Meeting, D. A. Copinger; ACCIDENT ANALYSIS: 126 Analysis of a PWR LBLOCA Without SCRAM, Trevor N. Tyler, Rafael Macian-Juan and John H. Mahaffy; DESIGN FEATURES: 139 Vulnerability of Multiple-Barrier Systems, N. C. Lind; ENVIRONMENTAL EFFECTS: 149 A Study of Wet Catalytic Oxidation of Radioactive Spent Ion Exchange Resin by Hydrogen Peroxide, Xingchao Jian, Tianbao Wu, and Guichun Yun; 157 A Comparison Study and Resolution of Differences Between Emergency Response and Safety Analysis Codes Used at the Savannah River Site, A. A. Simpkins; OPERATING EXPERIENCES: 164 Reactor Shutdown Experience, Compiled by J. W. Cletcher; RECENT DEVELOPMENTS: 167 Reports, Standards, and Safety Guides, D. S. Queener; 172 Proposed Rule Changes as of Dec. 31,1995; ANNOUNCEMENTS: 178 American Nuclear Society 1997 Annual Meeting; 178 American Nuclear Society Nuclear Criticality and Safety Division Topical Meeting; 176 The Authors.

05 NUCLEAR FUELS↗

Modular, Mobile Systems for the Treatment of Contaminated Water at Three Magnox Sites in the United Kingdom - 20421

Veolia Nuclear Solutions (VNS), and its mitigated entity, Veolia Nuclear Solutions Federal Services (VNSFS), are designing, overseeing the fabrication and installation, and supporting the commissioning of highly mobile and modular skid-based water treatment systems to assist in the decommissioning of three Magnox reactor sites based in the U.K. These Modular Active Effluent Treatment Plants (MAETP) will be deployed at the Chapelcross, Hinkley Point A, and Dungeness A sites to process contaminated water through the use of ion exchange systems and/or filtration units. At the time of writing, two systems have been installed and inactively commissioned, and the third system is expected to be delivered in 2020. Veolia has utilized a multi-national team of engineers, based in the UK and the US, to effectively leverage the best of Veolia expertise in the design and delivery of mobile, modular systems. The VNS team continues to refine the modular, mobile, and scalable approach to water processing system delivery, and has successfully patented the evolving technology for proprietary protection. The intent of this technology investment is to improve the functionality, mobility, and modularity, resulting in a system which can be adapted to a broad range of throughput and isotope removal requirements to achieve the most cost effective, flexible system possible for customers. Designing, fabricating, and factory-testing the modules off site followed by onsite installation, testing, start-up, and commissioning ensures expedited delivery and setup, as well as cost savings for nuclear applications. For the MAETP systems, VNS's previous nuclear site experience and ongoing Research and Development (R and D), combined with the resulting mobile/modular water processing systems developed and successfully deployed by VNS, have proven to be important inputs for the successful end-design of the systems, materials selection, system testing and commissioning. The lessons learned in the development and continued enhancement of the patented systems described in this paper will prove useful in advancing and deploying future systems for other nuclear sites, where rapid customizing and cost-effective implementation are critical factors. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Treatment of Problematic Reactive Metal Wastes Using the GeoMelt{sup R} In-Container Vitrification (ICV{sup TM}) Process - 20326

Decommissioning of sodium-cooled reactors and fast reactor technologies has generated a number of reactive metal waste configurations that are problematic to treat and typically lack cost effective treatment methods and disposition options. As a result, Veolia Nuclear Solutions, under contract with Idaho National Laboratory (owned by the U.S. Department of Energy and managed and operated by Battelle Energy Alliance, LLC) demonstrated its GeoMelt{sup R} In-Container Vitrification (ICV){sup TM} technology to safely convert sodium metal to a non-reactive vitrified oxide form. The demonstration project, supported by glass formulation and crucible testing, consisted of a series of ICV{sup TM} melts that processed elemental sodium into stable non-reactive glass. INL is currently implementing GeoMelt{sup R} technology as a means to safely and reliably convert radioactive reactive metal residues that contaminate sodium cooled reactor components into waste forms that comply with existing disposition pathways. Reactive metal wastes require treatment in order to remove the Resource Conservation and Recovery Act (RCRA) reactivity and ignitability characteristics to comply with land disposal restrictions. GeoMelt{sup R}, which is an alternative to other potential treatment approaches, provides a robust approach that chemically converts the reactive metals to an inert oxide while also immobilizing radionuclides in a vitrified waste form with durability equal to or better than vitrified nuclear fuel reprocessing wastes (very robust and inert waste forms). Most other treatment approaches generate hydrogen gas which is problematic. In 2016, Veolia Nuclear Solutions first demonstrated the effectiveness of the GeoMelt{sup R} ICV{sup TM} process in deactivating reactive sodium metal. Crucible, bench-scale, and engineering-scale demonstrations were conducted on several surrogate waste configurations with various ratios of sodium metal and glass formers. Each ratio and configuration demonstrated complete deactivation of the surrogate sodium metal. Follow-on work in 2017 demonstrated the deactivation of reactive sodium by GeoMelt{sup R} ICV{sup TM} at a higher waste loading relative to previously demonstrated work performed in 2016; the higher waste loading optimized glass chemistry while enhancing the economical full-scale treatment of reactive metals. Additionally, follow-on demonstration testing in 2018 and 2019 focused on more complex shapes and other reactive-metals (mocked up Experimental Breeder Reactor II [EBR-II] subassembly, sodium filled heat exchanger, and a can containing sodium potassium alloy) which were all performed at engineering scale. Veolia Nuclear Solutions designed, installed, and commissioned in September 2018, at Perma-Fix Northwest in Richland Washington, a 10-metric ton full-scale GeoMelt unit (GeoMelt{sup R} Richland) for the treatment of reactive metal wastes. As of September 2019, over 900 55-gallon drums containing a total of around 3,500 lb of sodium with low levels of radioactivity have been treated at GeoMelt{sup R} Richland, with resulting glass monoliths disposed at the Nevada National Security Site (NNSS). A full-scale radiological demonstration melt on an actual EBR-II subassembly has also been performed using the full-scale melter in 2019. The GeoMelt{sup R} technology is a proven radioactive waste treatment technology capable of immobilizing radioactive wastes, including bulk rubble such as drums and other steel vessels usually without pretreatment. Utilizing the GeoMelt{sup R} technology to treat reactive metals eliminates pretreatment steps resulting from having to separate the reactive metal from steel containers or jackets as GeoMelt{sup R} can easily operate at temperatures sufficient to melt the steel and expose the reactive metal for treatment. Eliminating handling steps of reactive metals is a significant safety advantage since reactive metals are pyrophoric. The results generated as a part of the 2018-2019 demonstration program are presented in the paper. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Analysis of attenuation data from the decommissioned ZIon unit 1 reactor pressure vessel beltline weld

In order to examine the attenuation of radiation damage through the thickness of an irradiated reactor pressure vessel (RPV), four segments were acquired from the Zion Unit 1 power plant RPV after the plant was decommissioned. The Zion Unit 1 RPV Beltline Weld Segment 1 was cut into seven blocks, consisting of five base metal and two beltline welds from the high fluence region of the segment. Through-wall test specimens were machined and tested. Specimens included those used for Charpy impact, Master Curve fracture toughness testing, and chemical analysis. The observed through-thickness ductile-to-brittle transition temperatures in the beltline weld deviated significantly from the expected behavior based on the attenuation of fast fluence as a function of depth into the RPV. Beginning at the inside surface, the 41-J Charpy transition temperature was either flat or slightly increasing until the ¾ -T location. The results of a simple, model-based analysis of the Zion beltline weld material that included the irradiation conditions and material chemistry were generally consistent with industry trend curves and the standard attenuation model, rather than the observed data. Although there was no archive material from the RPV available to permit measurement of the unirradiated properties, fracture toughness specimens fabricated from archive surveillance weld were used to obtain an estimate of the initial through-thickness values of the Charpy transition temperature. The Charpy shifts obtained using this approach were similarly in disagreement with the predictions of the US NRC Regulatory Guide 1.99, Rev. 2. However, testing of irradiated Charpy specimens taken from the RPV following post-irradiation annealing (10 hr. at 500 °C) provided a quite different estimate of the unirradiated properties which improved the agreement between the inferred through-thickness Charpy shifts and exponential attenuation model included in Regulatory Guide 1.99/2. In conclusion, the analysis of the Zion data and data obtained in previous post-mortem examinations of decommissioned RPVs indicates that more work is needed to understand the through-thickness properties of RPV materials in order to properly assess through-wall damage attenuation.

Charpy impact↗

Contaminant Migration Modeling to Support the In Situ Decommissioning of Hardened Nuclear Facilities - 20215

The decommissioning of hardened nuclear facilities provides a unique challenge in balancing current worker dose with exposure to future receptors and media. In situ decommissioning (ISD) is a cost-effective and safe option for the closure of such facilities but requires a detailed understanding of the threat that radioactive and hazardous constituents remaining in the facilities pose to groundwater and surrounding surface water. The Savannah River Site (SRS) extensively employs contaminant migration models within the decommissioning process to develop site-specific removal, grouting, and monitoring strategies in support of safe and effective final end states of nuclear facilities. This work discusses the use of contaminant migration modeling in the ISD process at SRS, including specific examples from the closure of P-Reactor and R-Reactor, Building 235-F, F-Canyon and F/H Laboratory Complex. Migration models developed during the closure of P-Reactor and R-Reactor were divided into four source areas: the reactor vessel, the process area, the disassembly basin, and the purification wing. Each source area was assigned a specific inventory and migration pathway and was then subject to varying hypothetical removal, capping, and grouting schemes. Modeling indicated that groundwater Maximum Concentration Limits (MCLs) might be exceeded if no action was taken for eleven and ten constituents of concern (COCs) at P-Reactor and R-Reactor, respectively. These exceedances could occur in as few as 200 to 500 years. Alternatively, the migration modeling demonstrated that the selected ISD actions reduced contaminant mobility which allowed for significant radioactive decay and resulted in fewer predicted exceedances of groundwater MCLs (five COCs for P-Reactor; eight COCs for R-Reactor). In response to the modeling results for P-Reactor and R-Reactor, effectiveness monitoring programs were developed to target contaminants, specific to each reactor, that may migrate to groundwater. Contaminant migration modeling also revealed that roof collapse was a large factor in the release of COCs to the environment, giving rise to roof improvements, and an inspection and vegetation control program to ensure roof stability over time. Contaminant migration modeling is also aiding in the closure planning for hardened facilities in F Area. Building 235-F housed the Actinide Billet Line, which produced Np-237 billets for irradiation in SRS reactors, and the Plutonium Fuel Form (PuFF) facility that produced Pu-238 heat sources for the space program. As a result of these missions, areas within Building 235-F contain considerable residual amounts of both Pu-238 and Np-237. Contaminant migration modeling of Building 235-F was originally performed in 2012 to identify the feasibility of ISD and the amount of radioactive material removal required to prevent the exceedance of groundwater MCLs. The original model indicated that a 60% reduction in the PuFF facility Pu-238 inventory could keep groundwater concentrations below standards, while Np-237 did not pose a threat to groundwater. However, updates to the model with an emphasis on source impact pathways revealed that, due to the orientation of the source areas relative to groundwater flow, no amount of reasonable removal of Pu-238 would keep groundwater concentrations below MCLs and that Np-237 could be a large contributor to localized MCL exceedances. With this insight, the refined 2019 model is being used to assist in the development of grouting plans specific to each facility source area, where bentonite may be utilized to slow the migration of Pu-238 and its daughter products from the PuFF facility and a reducing grout may decrease Np-237 transport by ensuring the nuclide remains in the less mobile +IV oxidation state. The beginning phases of contaminant migration modeling are underway for F-Canyon and associated facilities using lessons learned from the Reactors and Building 235-F. A contaminant migration pathway, similar to the pathway used for the reactor vessels, is being developed for the hot and warm canyons. The F-Canyon inventories are being spatially refined to identify specific and localized source zones, comparable to Building 235-F, that may impact groundwater. Contaminant migration modeling provides vital input within the ISD process, from facility investigation to post closure effectiveness monitoring, making it a valuable tool in the development of safe and effective end states for hardened nuclear facilities at SRS. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Feedback from International Decommissioning Planning Projects - 20269

Decommissioning of Nuclear Power Plants is an increasing reality in many countries with nuclear power. Already many years before final shutdown, planning of the decommissioning work is usually started in order to understand for example the costs, waste volume capacity and licensing work needed. In many countries it is required to have a final decommissioning plan before any decommissioning work is allowed to start. Westinghouse has been involved in international decommissioning planning for more than 30 years, where the first 20 years was mostly funding and preliminary plans due to that decommissioning was many years away. However, as many more plants are now moving into decommissioning, the focus has shifted to final decommissioning plans with budgets instead of funding plans, strategic decisions instead of choices, waste volume specifications instead of estimates and a defined approach instead of what ifs. Westinghouse has developed a methodology based on the planning and execution of many decommissioning projects in Europe, America and Asia. That international experience and understanding helps the customers to adopt a systematic planning process where strategy development is done with the end state in mind, where the goals are clearly outlined and the starting point described. The process and steps to reach the desired end state need to be clearly defined and all options/alternatives evaluated from a cost/benefit point of view. This is followed by a thorough and quantitative risk analysis in order to give solid recommendations and credible conclusions. One important feedback has been that real decommissioning experience from reference projects is invaluable for an efficient and timely progress in order not to spend unnecessary time and effort on understanding the barriers and links between different activities in decommissioning. Skilled project managers or engineers can drive the project forward, but without decommissioning experience previously gained, valuable lessons learned are not used and the same mistakes can be made again. Many utilities have invested in knowledge transfer from other decommissioning projects through site visits, exchange programs and supplier meetings, which is a valuable asset and way of implementing lessons learned from performed decommissioning projects into the planning process. (authors)